Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Cherpu AE
Date: 24/03/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 15/03/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 10/03/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 08/03/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 04/03/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 28/02/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 23/02/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 14/02/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 11/02/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 09/02/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 01/02/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 28/01/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 25/01/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 21/01/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 19/01/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 18/01/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 12/01/2022

Work has been completed | 100% Completed

32 nos of fhtc provided and final bill submitted

Cherpu AE
Date: 04/01/2022

Work has been completed | 100% Completed

32 nos of fhtc provided

Cherpu AE
Date: 31/12/2021

Work has been completed | 100% Completed

32 nos of fhtc provided

Cherpu AE
Date: 27/12/2021

Work has been completed | 100% Completed

32 nos of fhtc provided

Cherpu AE
Date: 22/12/2021

Work in progress | 46% Completed

15 nos of fhtc provided

Cherpu AE
Date: 18/12/2021

Work in progress | 46% Completed

15 nos of fhtc provided

Cherpu AE
Date: 14/12/2021

Work in progress | 46% Completed

15 nos of fhtc provided

Cherpu AE
Date: 10/12/2021

Work in progress | 46% Completed

15 nos of fhtc provided

Cherpu AE
Date: 04/12/2021

Work in progress | 45% Completed

15 nos of fhtc provided

Cherpu AE
Date: 24/11/2021

Work in progress | 45% Completed

15 nos of fhtc provided

Cherpu AE
Date: 20/11/2021

Work in progress | 49% Completed

15 nos of fhtc provided

Cherpu AE
Date: 15/11/2021

Work in progress | 49% Completed

15 nos of fhtc provided

Cherpu AE
Date: 10/11/2021

Work in progress | 49% Completed

15 nos of fhtc provided

Cherpu AE
Date: 06/11/2021

Work in progress | 49% Completed

15 nos of fhtc provided

Cherpu AE
Date: 01/11/2021

Work in progress | 49% Completed

15 nos of fhtc provided

Cherpu AE
Date: 26/10/2021

Work in progress | 49% Completed

15 nos of fhtc provided

Cherpu AE
Date: 21/10/2021

Work in progress | 49% Completed

15 nos of fhtc provided

Cherpu AE
Date: 16/10/2021

Work in progress | 49% Completed

15 nos of fhtc provided

Cherpu AE
Date: 11/10/2021

Work in progress | 49% Completed

15 nos of fhtc provided

Cherpu AE
Date: 04/10/2021

Work in progress | 49% Completed

15 nos of fhtc provided

Cherpu AE
Date: 28/09/2021

Work in progress | 49% Completed

15 nos of fhtc provided

Cherpu AE
Date: 25/09/2021

Work in progress | 49% Completed

15 nos of fhtc provided

Cherpu AE
Date: 22/09/2021

Work in progress | 0% Completed

quotation for 32 nos approved and work is started

Cherpu AE
Date: 17/09/2021

Work has started | 0% Completed

major work global tendered at circle level

Cherpu AE
Date: 13/09/2021

Work has started | 0% Completed

major work global tendered at circle level

Cherpu AE
Date: 09/09/2021

Work has started | 0% Completed

major work global tendered at circle level

Cherpu AE
Date: 05/09/2021

Work has started | 0% Completed

major work global tendered at circle level

Cherpu AE
Date: 31/08/2021

Work has started | 0% Completed

major work global tendered at circle level

Cherpu AE
Date: 29/08/2021

Work has started | 0% Completed

global tender invited at circle office

Irinjalakuda AEE
Date: 26/08/2021

Work in progress | 0% Completed

global tender invited at circle office

Cherpu AE
Date: 24/08/2021

Work has started | 0% Completed

non starter

Cherpu AE
Date: 18/08/2021

Work has started | 0% Completed

non starter

Cherpu AE
Date: 06/08/2021

Work has started | 0% Completed

work not started

Irinjalakuda AEE
Date: 28/07/2021

Work has started | 0% Completed

global tender invited at circle level

Irinjalakkuda PH Dn EE
Date: 11/07/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 07/07/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 06/07/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 05/07/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 02/07/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 01/07/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 30/06/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 29/06/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 28/06/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 25/06/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 23/06/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 21/06/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 18/06/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 16/06/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 15/06/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 11/06/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 10/06/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 03/06/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 02/06/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 01/06/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 31/05/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 29/05/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 28/05/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 27/05/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 26/05/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 25/05/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 24/05/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 22/05/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 21/05/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 20/05/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 19/05/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 18/05/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 16/05/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 14/05/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 13/05/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 12/05/2021

Work has started | 0% Completed

Global tender arranged at Circle level.

Irinjalakkuda PH Dn EE
Date: 11/05/2021

Work has started | 0% Completed

Global tender invited at circle level

Irinjalakkuda PH Dn EE
Date: 10/05/2021

Work has started | 0% Completed

Global tender invited at circle level

Irinjalakkuda PH Dn EE
Date: 07/05/2021

Work has started | 0% Completed

Global tender invited at circle level

Irinjalakkuda PH Dn EE
Date: 06/05/2021

Work has started | 0% Completed

Global tender invited at circle level

Irinjalakkuda PH Dn EE
Date: 04/05/2021

Work has started | 0% Completed

Global tender invited at circle level

Irinjalakkuda PH Dn EE
Date: 02/05/2021

Work has started | 0% Completed

Global tender invited at circle level

Irinjalakkuda PH Dn EE
Date: 29/04/2021

Work has started | 0% Completed

Global tender invited at circle level

Irinjalakkuda PH Dn EE
Date: 26/04/2021

Work has started | 0% Completed

Global tender invited at circle level

Irinjalakkuda PH Dn EE
Date: 15/04/2021

Work has started | 0% Completed

No offer received. Directed to split and arrange at lower level

Irinjalakkuda PH Dn EE
Date: 07/04/2021

Work has started | 0% Completed

No offer received. Directed to split and arrange at lower level

Irinjalakkuda PH Dn EE
Date: 30/03/2021

Work has started | 0% Completed

No offer received. Directed to split and arrange at lower level

Irinjalakkuda PH Dn EE
Date: 27/03/2021

Work has started | 0% Completed

No offer received. Directed to split and arrange at lower level

Irinjalakkuda PH Dn EE
Date: 22/03/2021

Work has started | 0% Completed

No offer received. Directed to split and arrange at lower level

Irinjalakkuda PH Dn EE
Date: 10/03/2021

Work has started | 0% Completed

No offer received. Directed to split and arrange at lower level

Irinjalakkuda PH Dn EE
Date: 01/03/2021

Work has started | 0% Completed

No offer received. Directed to split and arrange at lower level

Irinjalakkuda PH Dn EE
Date: 26/02/2021

Work has started | 0% Completed

No offer received. Directed to split and arrange at lower level

Irinjalakkuda PH Dn EE
Date: 22/02/2021

Work in progress | 0% Completed

No offer received. Directed to split and arrange at lower level

Irinjalakkuda PH Dn EE
Date: 19/02/2021

Work has started | 0% Completed

No offer received.

Irinjalakkuda PH Dn EE
Date: 16/02/2021

Work has started | 0% Completed

No offer received.

Irinjalakkuda PH Dn EE
Date: 10/02/2021

Work has started | 0% Completed

Tendered