| Valakom PH Sn AE |
| Date: 27/06/2024 |
Work has been completed | 100% Completed
5 km pipe laid.work completed
| Valakom PH Sn AE |
| Date: 18/04/2024 |
Work has been completed | 100% Completed
5 km pipe laid.work completed
| Valakom PH Sn AE |
| Date: 30/03/2024 |
Work in progress | 98% Completed
5 km pipe laid.
| Valakom PH Sn AE |
| Date: 27/03/2024 |
Work in progress | 98% Completed
5 km pipe laid.
| Valakom PH Sn AE |
| Date: 25/03/2024 |
Work in progress | 98% Completed
5 km pipe laid.
| Valakom PH Sn AE |
| Date: 22/03/2024 |
Work in progress | 98% Completed
5 km pipe laid.
| Valakom PH Sn AE |
| Date: 18/03/2024 |
Work in progress | 86% Completed
4.3km pipe laid work in progress
| Valakom PH Sn AE |
| Date: 11/03/2024 |
Work in progress | 86% Completed
4.3km pipe laid work in progress
| Valakom PH Sn AE |
| Date: 04/03/2024 |
Work in progress | 86% Completed
4.3km pipe laid work in progress
| Valakom PH Sn AE |
| Date: 29/02/2024 |
Work in progress | 86% Completed
4.3km pipe laid work in progress
| Valakom PH Sn AE |
| Date: 26/02/2024 |
Work in progress | 60% Completed
3km pipeline laid work in progress
| Valakom PH Sn AE |
| Date: 23/02/2024 |
Work in progress | 60% Completed
3km pipeline laid work in progress
| Valakom PH Sn AE |
| Date: 21/02/2024 |
Work in progress | 60% Completed
3km pipeline laid work in progress
| Valakom PH Sn AE |
| Date: 19/02/2024 |
Work in progress | 60% Completed
3km pipeline laid work in progress
| Valakom PH Sn AE |
| Date: 15/02/2024 |
Work in progress | 60% Completed
3km pipeline laid work in progress
| Valakom PH Sn AE |
| Date: 14/02/2024 |
Work in progress | 60% Completed
3km pipeline laid
| Valakom PH Sn AE |
| Date: 12/02/2024 |
Work in progress | 34% Completed
1.7km pipeline laid
| Valakom PH Sn AE |
| Date: 09/02/2024 |
| Valakom PH Sn AE |
| Date: 08/02/2024 |
Work in progress | 34% Completed
1.7km pipeline laid
| Valakom PH Sn AE |
| Date: 07/02/2024 |
| Valakom PH Sn AE |
| Date: 03/02/2024 |
Work in progress | 34% Completed
1.7km pipeline laid
| Valakom PH Sn AE |
| Date: 02/02/2024 |
Work in progress | 34% Completed
1.7km pipeline laid
| Valakom PH Sn AE |
| Date: 31/01/2024 |
| Valakom PH Sn AE |
| Date: 29/01/2024 |
| Valakom PH Sn AE |
| Date: 27/01/2024 |
Work in progress | 34% Completed
1.7km pipeline laid.
| Valakom PH Sn AE |
| Date: 25/01/2024 |
Work in progress | 34% Completed
1.7km pipeline laid.
| Valakom PH Sn AE |
| Date: 24/01/2024 |
Work in progress | 34% Completed
1.7km pipeline laid.
| Valakom PH Sn AE |
| Date: 23/01/2024 |
| Valakom PH Sn AE |
| Date: 22/01/2024 |
Work in progress | 34% Completed
1.7km pipeline laid.
| Valakom PH Sn AE |
| Date: 20/01/2024 |
Work in progress | 34% Completed
1.7km pipeline laid.