| Malaparamba Aug-Med Sn - AE |
| Date: 01/12/2024 |
Work has been completed | 100% Completed
Work completed
| Kozhikode PH Dn EE |
| Date: 25/10/2024 |
Work in progress | 90% Completed
Interconnection work pending. waiting for shutdown and road cutting permission from KRFB
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 40% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 13% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 13/03/2024 |
Work has started | 0% Completed
Site Handed Over
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work has started | 0% Completed
Site Handed Over
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work has started | 0% Completed
Work order Issued
| Kozhikode PH Dn EE |
| Date: 12/01/2024 |
Work has started | 0% Completed
Work order Issued
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work has started | 0% Completed
Work order issued
| Kozhikode PH Dn EE |
| Date: 29/11/2023 |
Work has started | 0% Completed
Work order issued
| Kozhikode PH Dn EE |
| Date: 31/10/2023 |
Work has started | 0% Completed
Work order issued