| Kottarakkara PH Dn EE |
| Date: 01/12/2023 |
Work has been completed | 100% Completed
Completed
| Valakom Sub Dn AEE |
| Date: 30/11/2023 |
Work in progress | 80% Completed
Erection work completed. electrical installation pending
| Valakom Sub Dn AEE |
| Date: 27/11/2023 |
Work in progress | 65% Completed
pump supplied
| Valakom Sub Dn AEE |
| Date: 22/11/2023 |
Work in progress | 65% Completed
pump supplied
| Valakom Sub Dn AEE |
| Date: 20/11/2023 |
Work in progress | 65% Completed
pump supplied
| Valakom Sub Dn AEE |
| Date: 17/11/2023 |
Work in progress | 65% Completed
pump supplied
| Valakom Sub Dn AEE |
| Date: 13/11/2023 |
Work in progress | 65% Completed
pump supplied
| Valakom Sub Dn AEE |
| Date: 09/11/2023 |
Work in progress | 65% Completed
pump supplied
| Valakom Sub Dn AEE |
| Date: 07/11/2023 |
Work in progress | 65% Completed
pump supplied
| Valakom Sub Dn AEE |
| Date: 04/11/2023 |
Work in progress | 65% Completed
pump supplied
| Valakom Sub Dn AEE |
| Date: 02/11/2023 |
Work in progress | 65% Completed
pump supplied
| Valakom Sub Dn AEE |
| Date: 30/10/2023 |
Work in progress | 65% Completed
pump supplied
| Valakom Sub Dn AEE |
| Date: 27/10/2023 |
Work in progress | 65% Completed
pump supplied
| Valakom Sub Dn AEE |
| Date: 25/10/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 18/10/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 16/10/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 11/10/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 06/10/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 04/10/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 29/09/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 26/09/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 21/09/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 19/09/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 11/09/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 07/09/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 01/09/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 14/08/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 08/08/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 04/08/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 29/07/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 25/07/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 22/07/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 18/07/2023 |
Work in progress | 65% Completed
Pump Supplied Allied accesseries pending. Part bill submitted
| Valakom Sub Dn AEE |
| Date: 11/07/2023 |
Work in progress | 65% Completed
Pump Supplied. Allied accesseries pending. Part bill submitted
| Valakom Sub Dn AEE |
| Date: 10/07/2023 |
Work has started | 0% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 04/07/2023 |
Work in progress | 65% Completed
Pump Supplied
| Valakom Sub Dn AEE |
| Date: 01/07/2023 |
Work in progress | 65% Completed
Pump Supplied. Allied accesseries pending. Part bill submitted
| Kottarakkara PH Dn EE |
| Date: 27/06/2023 |
Work in progress | 65% Completed
Pump Supplied. Allied accesseries pending. Part bill submitted
| Valakom Sub Dn AEE |
| Date: 17/06/2023 |
Work has started | 0% Completed
Agreement executed
| Valakom Sub Dn AEE |
| Date: 15/06/2023 |
Work has started | 0% Completed
Agreement executed
| Valakom Sub Dn AEE |
| Date: 12/06/2023 |
Work has started | 0% Completed
Agreement executed
| Valakom Sub Dn AEE |
| Date: 08/06/2023 |
Work has started | 0% Completed
Agreement executed
| Valakom Sub Dn AEE |
| Date: 06/06/2023 |
Work has started | 0% Completed
Agreement executed
| Valakom Sub Dn AEE |
| Date: 02/06/2023 |
Work has started | 0% Completed
Agreement executed
| Valakom Sub Dn AEE |
| Date: 29/05/2023 |
Work has started | 0% Completed
Agreement executed
| Valakom Sub Dn AEE |
| Date: 25/05/2023 |
Work has started | 0% Completed
Agreement executed
| Valakom Sub Dn AEE |
| Date: 22/05/2023 |
Work has started | 0% Completed
Agreement executed
| Valakom Sub Dn AEE |
| Date: 18/05/2023 |
Work has started | 0% Completed
Agreement executed
| Valakom Sub Dn AEE |
| Date: 15/05/2023 |
Work has started | 0% Completed
Agreement executed
| Valakom Sub Dn AEE |
| Date: 11/05/2023 |
Work has started | 0% Completed
Agreement executed
| Valakom Sub Dn AEE |
| Date: 09/05/2023 |
Work has started | 0% Completed
Agreement executed
| Valakom Sub Dn AEE |
| Date: 05/05/2023 |
Work has started | 0% Completed
Agreement executed
| Valakom Sub Dn AEE |
| Date: 02/05/2023 |
Work has started | 0% Completed
Agreement executed
| Valakom Sub Dn AEE |
| Date: 24/04/2023 |
Work has started | 0% Completed
Agreement executed
| Kottarakkara PH Dn EE |
| Date: 18/04/2023 |
Work in progress | 0% Completed
Agreement Executed
| Valakom Sub Dn AEE |
| Date: 17/04/2023 |
Work has started | 0% Completed
Work tendered
| Kottarakkara PH Dn EE |
| Date: 13/04/2023 |
Work in progress | 0% Completed
Agreement executed
| Valakom Sub Dn AEE |
| Date: 10/04/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 04/04/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 01/04/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 30/03/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 28/03/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 25/03/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 23/03/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 21/03/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 18/03/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 15/03/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 13/03/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 10/03/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 08/03/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 06/03/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 03/03/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 01/03/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 27/02/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 24/02/2023 |
Work has started | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 22/02/2023 |
Work in progress | 0% Completed
Work tendered
| Valakom Sub Dn AEE |
| Date: 20/02/2023 |
Work has started | 0% Completed
Work tendered