| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 21/08/2024 |
Work has been completed | 100% Completed
work completed
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work has been completed | 100% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 83% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 80% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 01/03/2024 |
Work in progress | 78% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 75% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 68% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 11/01/2024 |
Work in progress | 65% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work in progress | 63% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 28/11/2023 |
Work in progress | 60% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 09/11/2023 |
Work in progress | 52% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 27/10/2023 |
Work in progress | 50% Completed
work started
| Kozhikode PH Dn EE |
| Date: 17/10/2023 |
Work in progress | 45% Completed
work started
| Kozhikode PH Dn EE |
| Date: 14/09/2023 |
Work in progress | 36% Completed
work started
| Kozhikode PH Dn EE |
| Date: 05/09/2023 |
Work in progress | 35% Completed
work started
| Kozhikode PH Dn EE |
| Date: 17/08/2023 |
Work in progress | 20% Completed
work started
| Kozhikode PH Dn EE |
| Date: 07/08/2023 |
Work in progress | 15% Completed
work started
| Kozhikode PH Dn EE |
| Date: 24/07/2023 |
Work has started | 0% Completed
Site Handed Over
| Kozhikode PH Dn EE |
| Date: 12/07/2023 |
Work has started | 0% Completed
Work not yet started
| Kozhikode PH Dn EE |
| Date: 05/07/2023 |
Work has started | 0% Completed
Work not yet started
| Kozhikode PH Dn EE |
| Date: 30/06/2023 |
Work has started | 0% Completed
Site not handed over
| Kozhikode PH Dn EE |
| Date: 20/06/2023 |
Work has started | 0% Completed
Site not handed over
| Kozhikode PH Dn EE |
| Date: 13/06/2023 |
Work has started | 0% Completed
Site not handed over
| Kozhikode PH Dn EE |
| Date: 08/06/2023 |
Work has started | 0% Completed
Site not handovered
| Kozhikode PH Dn EE |
| Date: 05/06/2023 |
Work has started | 0% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 01/06/2023 |
Work has started | 0% Completed
Agreement Executed