All updates

Kozhikode WestHill Distribution Sn - 1/1 - AE
Date: 21/08/2024

Work has been completed | 100% Completed

work completed

Kozhikode PH Dn EE
Date: 20/04/2024

Work has been completed | 100% Completed

Work in progress

Kozhikode PH Dn EE
Date: 04/04/2024

Work in progress | 83% Completed

Work in progress

Kozhikode PH Dn EE
Date: 12/03/2024

Work in progress | 80% Completed

Work in progress

Kozhikode PH Dn EE
Date: 01/03/2024

Work in progress | 78% Completed

Work in progress

Kozhikode PH Dn EE
Date: 14/02/2024

Work in progress | 75% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 27/01/2024

Work in progress | 68% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 11/01/2024

Work in progress | 65% Completed

Work in progress

Kozhikode PH Dn EE
Date: 11/12/2023

Work in progress | 63% Completed

Work in progress

Kozhikode PH Dn EE
Date: 28/11/2023

Work in progress | 60% Completed

Work in progress

Kozhikode PH Dn EE
Date: 09/11/2023

Work in progress | 52% Completed

Work in progress

Kozhikode PH Dn EE
Date: 27/10/2023

Work in progress | 50% Completed

work started

Kozhikode PH Dn EE
Date: 17/10/2023

Work in progress | 45% Completed

work started

Kozhikode PH Dn EE
Date: 14/09/2023

Work in progress | 36% Completed

work started

Kozhikode PH Dn EE
Date: 05/09/2023

Work in progress | 35% Completed

work started

Kozhikode PH Dn EE
Date: 17/08/2023

Work in progress | 20% Completed

work started

Kozhikode PH Dn EE
Date: 07/08/2023

Work in progress | 15% Completed

work started

Kozhikode PH Dn EE
Date: 24/07/2023

Work has started | 0% Completed

Site Handed Over

Kozhikode PH Dn EE
Date: 12/07/2023

Work has started | 0% Completed

Work not yet started

Kozhikode PH Dn EE
Date: 05/07/2023

Work has started | 0% Completed

Work not yet started

Kozhikode PH Dn EE
Date: 30/06/2023

Work has started | 0% Completed

Site not handed over

Kozhikode PH Dn EE
Date: 20/06/2023

Work has started | 0% Completed

Site not handed over

Kozhikode PH Dn EE
Date: 13/06/2023

Work has started | 0% Completed

Site not handed over

Kozhikode PH Dn EE
Date: 08/06/2023

Work has started | 0% Completed

Site not handovered

Kozhikode PH Dn EE
Date: 05/06/2023

Work has started | 0% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 01/06/2023

Work has started | 0% Completed

Agreement Executed