| Kollam PH Dn EE |
| Date: 02/10/2021 |
Work has been completed | 100% Completed
work completed
| Kollam PH Dn EE |
| Date: 29/09/2021 |
Work has been completed | 100% Completed
work has been completed
| Kollam PH Dn EE |
| Date: 26/09/2021 |
Work has been completed | 100% Completed
Work has been completed
| Kollam PH Dn EE |
| Date: 23/09/2021 |
Work has been completed | 100% Completed
work has been completed
| Kollam PH Dn EE |
| Date: 20/09/2021 |
Work has been completed | 100% Completed
work completed
| Kollam PH Dn EE |
| Date: 17/09/2021 |
Work has been completed | 100% Completed
work completed
| Kollam PH Dn EE |
| Date: 14/09/2021 |
Work has been completed | 100% Completed
work completed
| Kollam PH Dn EE |
| Date: 11/09/2021 |
Work has been completed | 100% Completed
work completed
| Kollam PH Dn EE |
| Date: 09/09/2021 |
Work has been completed | 100% Completed
work completed
| Kollam PH Dn EE |
| Date: 06/09/2021 |
Work has been completed | 100% Completed
work completed
| Kollam PH Dn EE |
| Date: 16/08/2021 |
Work has been completed | 100% Completed
work completed
| Kollam PH Dn EE |
| Date: 11/08/2021 |
Work has been completed | 100% Completed
10000 connections given.
| Kollam PH Dn EE |
| Date: 10/08/2021 |
Work in progress | 98% Completed
9858 connections given
| Kollam PH Dn EE |
| Date: 09/08/2021 |
Work in progress | 97% Completed
9758 connections are given
| Kollam PH Dn EE |
| Date: 07/08/2021 |
Work in progress | 96% Completed
9658 connections are given
| Kollam PH Dn EE |
| Date: 06/08/2021 |
Work in progress | 95% Completed
9578 connections are given
| Kollam PH Dn EE |
| Date: 05/08/2021 |
Work in progress | 94% Completed
9458 connections are given
| Kollam PH Dn EE |
| Date: 03/08/2021 |
Work in progress | 94% Completed
9438 connections are given
| Kollam PH Dn EE |
| Date: 02/08/2021 |
Work in progress | 92% Completed
9218 connections are given
| Kollam PH Dn EE |
| Date: 30/07/2021 |
Work in progress | 92% Completed
9218 connections are given
| Kollam PH Dn EE |
| Date: 28/07/2021 |
Work in progress | 91% Completed
9168 connections are given
| Kollam PH Dn EE |
| Date: 27/07/2021 |
Work in progress | 91% Completed
9120 connections are given
| Kollam PH Dn EE |
| Date: 25/07/2021 |
Work in progress | 90% Completed
9080 connections are given
| Kollam PH Dn EE |
| Date: 22/07/2021 |
Work in progress | 90% Completed
9080 connections are given
| Kollam PH Dn EE |
| Date: 19/07/2021 |
Work in progress | 88% Completed
8743 connections are given
| Kollam PH Dn EE |
| Date: 15/07/2021 |
Work in progress | 88% Completed
8743 connections are given
| Kollam PH Dn EE |
| Date: 09/07/2021 |
Work in progress | 87% Completed
8743 connections are given.
| Kollam PH Dn EE |
| Date: 06/07/2021 |
Work in progress | 87% Completed
8709 connections are given.
| Kollam PH Dn EE |
| Date: 04/07/2021 |
Work in progress | 87% Completed
8709 connections are given.
| Kollam PH Dn EE |
| Date: 02/07/2021 |
Work in progress | 87% Completed
8709 connections are given.
| Kollam PH Dn EE |
| Date: 30/06/2021 |
Work in progress | 87% Completed
8709 connections are given.
| Kollam PH Dn EE |
| Date: 28/06/2021 |
Work in progress | 87% Completed
8684 connections given.
| Kollam PH Dn EE |
| Date: 24/06/2021 |
Work in progress | 86% Completed
8663 connections are given.
| Kollam PH Dn EE |
| Date: 23/06/2021 |
Work in progress | 86% Completed
8623 connections are given
| Kollam PH Dn EE |
| Date: 22/06/2021 |
Work in progress | 86% Completed
8623 connections given
| Kollam PH Dn EE |
| Date: 21/06/2021 |
Work in progress | 86% Completed
8604 connections are given.
| Kollam PH Dn EE |
| Date: 18/06/2021 |
Work in progress | 86% Completed
8604 connections are given.
| Kollam PH Dn EE |
| Date: 17/06/2021 |
Work in progress | 86% Completed
8584 connections are given.
| Kollam PH Dn EE |
| Date: 15/06/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19
| Kollam PH Dn EE |
| Date: 14/06/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 13/06/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 12/06/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 10/06/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 09/06/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 03/06/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 02/06/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 01/06/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 31/05/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 30/05/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 25/05/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 24/05/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 22/05/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 19/05/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 17/05/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 16/05/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 14/05/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 13/05/2021 |
Work in progress | 85% Completed
No progress of work due to increased spread of covid 19.
| Kollam PH Dn EE |
| Date: 10/05/2021 |
Work in progress | 85% Completed
8534 connections are given.
| Kollam PH Dn EE |
| Date: 03/05/2021 |
Work in progress | 85% Completed
8514 connections are given.
| Kollam PH Dn EE |
| Date: 30/04/2021 |
Work in progress | 85% Completed
8494 connections are given.
| Kollam PH Dn EE |
| Date: 29/04/2021 |
Work in progress | 84% Completed
8459 connections given.
| Kollam PH Dn EE |
| Date: 27/04/2021 |
Work in progress | 84% Completed
8434 connections are given
| Kollam PH Dn EE |
| Date: 26/04/2021 |
Work in progress | 84% Completed
8409 connections given.
| Kollam PH Dn EE |
| Date: 23/04/2021 |
Work in progress | 84% Completed
8397 connections given.
| Kollam PH Dn EE |
| Date: 20/04/2021 |
Work in progress | 84% Completed
8377 connections given
| Kollam PH Dn EE |
| Date: 16/04/2021 |
Work in progress | 83% Completed
work restarted
| Kollam PH Dn EE |
| Date: 08/04/2021 |
Work in progress | 83% Completed
Additional agreement executed on 23/03/2021 for providing balanced connection as per revised TS
| Kollam PH Dn EE |
| Date: 30/03/2021 |
Work in progress | 83% Completed
Additional agreement to be executed for providing balanced connection as per revised TS
| Kollam PH Dn EE |
| Date: 17/03/2021 |
Work in progress | 83% Completed
Revised TS sanctioned on 16/03/2021 for 878 Lakhs
| Kollam PH Dn EE |
| Date: 13/03/2021 |
Work in progress | 83% Completed
Awaiting Revised TS
| Kollam PH Dn EE |
| Date: 08/03/2021 |
Work in progress | 83% Completed
Awaiting revised TS
| Kollam PH Dn EE |
| Date: 25/02/2021 |
Work in progress | 83% Completed
Revised AS approved by GoK.
| Kollam PH Dn EE |
| Date: 23/02/2021 |
Work in progress | 83% Completed
Awaiting GO for revised AS.
| Kollam PH Dn EE |
| Date: 17/02/2021 |
Work in progress | 83% Completed
Awaiting for Revised AS.
| Kollam PH Dn EE |
| Date: 12/02/2021 |
Work in progress | 83% Completed
Awaiting for Revised AS.
| Kollam PH Dn EE |
| Date: 05/02/2021 |
Work in progress | 83% Completed
SHPSC approved for revised AS proposal.Awaiting GO.
| Kollam PH Dn EE |
| Date: 29/01/2021 |
Work in progress | 83% Completed
Revised AS sanctioned in the 26 th SHPSC held on 17.12.32020 for an amount of Rs. 9.27 crores .Estimate submitted for revised TS
| Kollam PH Dn EE |
| Date: 25/11/2020 |
Work in progress | 83% Completed
Out of 10000 water connections, 8324 Nos of water connections given. As per the demand of Kollam corporation during the core committee meeting held on 12.06.2020, additional 1676 nos of connections from the list of consumers in the 2nd phase of AMRUT SAAP year 16-17 is incorporated and submitted to the secretary Kollam corporation for an amount of Rs.9.2752 Crores for getting revised A.S including tender excess of 5.64%. Placed in 25th SHPSC. Deferred.