Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kannur PH Sn 3 AE
Date: 04/10/2025

Work has been completed | 100% Completed

9.6 KM pipe laid 915 nos FHTC given. Road restoration-6 km

Kannur PH Sn 3 AE
Date: 10/09/2025

Work in progress | 90% Completed

9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km

Kannur PH Sn 3 AE
Date: 30/08/2025

Work in progress | 90% Completed

9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km

Kannur PH Sn 3 AE
Date: 08/08/2025

Work in progress | 90% Completed

9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km

Kannur PH Sn 3 AE
Date: 31/07/2025

Work in progress | 90% Completed

9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km

Kannur PH Sn 3 AE
Date: 19/07/2025

Work in progress | 90% Completed

9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km

Kannur PH Sn 3 AE
Date: 14/07/2025

Work in progress | 90% Completed

9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km

Kannur PH Sn 3 AE
Date: 30/06/2025

Work in progress | 90% Completed

9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km

Kannur PH Sn 3 AE
Date: 27/06/2025

Work in progress | 90% Completed

9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km

Kannur PH Sn 3 AE
Date: 23/06/2025

Work in progress | 72% Completed

9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km

Kannur PH Sn 3 AE
Date: 17/06/2025

Work in progress | 72% Completed

9.3 KM pipe laid 870 nos FHTC given. Road restoration-3.4km

Kannur PH Sn 3 AE
Date: 29/05/2025

Work in progress | 72% Completed

9.3 KM pipe laid 870 nos FHTC given. Road restoration-3.4km

Kannur PH Sn 3 AE
Date: 19/05/2025

Work in progress | 72% Completed

9.3 KM pipe laid 870 nos FHTC given. Road restoration-3.4km

Kannur PH Sn 3 AE
Date: 03/05/2025

Work in progress | 70% Completed

9.3 KM pipe laid 870 nos FHTC given

Kannur PH Sn 3 AE
Date: 05/04/2025

Work in progress | 65% Completed

9.3 KM pipe laid 860 nos FHTC given

Kannur PH Sn 3 AE
Date: 27/03/2025

Work in progress | 65% Completed

9.3 KM pipe laid 860 nos FHTC given

Kannur PH Sn 3 AE
Date: 03/03/2025

Work in progress | 65% Completed

9.3 KM pipe laid 860 nos FHTC given

Kannur PH Sn 3 AE
Date: 22/02/2025

Work in progress | 60% Completed

9.3 KM pipe laid 860 nos FHTC given

Kannur PH Sn 3 AE
Date: 12/02/2025

Work in progress | 60% Completed

9.3 KM pipe laid 860 nos FHTC given

Kannur PH Sn 3 AE
Date: 07/02/2025

Work in progress | 60% Completed

9.3 KM pipe laid 860 nos FHTC given

Kannur PH Sn 3 AE
Date: 01/02/2025

Work in progress | 60% Completed

9.3 KM pipe laid 860 nos FHTC given

Kannur PH Sn 3 AE
Date: 29/01/2025

Work in progress | 60% Completed

9.3 KM pipe laid 860 nos FHTC given

Kannur PH Sn 3 AE
Date: 24/01/2025

Work in progress | 60% Completed

9.3 KM pipe laid 860 nos FHTC given

Kannur PH Sn 3 AE
Date: 22/01/2025

Work in progress | 60% Completed

9.3 KM pipe laid 860 nos FHTC given

Kannur PH Sn 3 AE
Date: 18/01/2025

Work in progress | 60% Completed

9.3 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 16/01/2025

Work in progress | 60% Completed

9.3 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 10/01/2025

Work in progress | 60% Completed

9.3 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 04/01/2025

Work in progress | 60% Completed

9.3 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 31/12/2024

Work in progress | 60% Completed

9.3 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 24/12/2024

Work in progress | 60% Completed

9.3 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 21/12/2024

Work in progress | 60% Completed

9.3 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 20/12/2024

Work in progress | 60% Completed

9.2 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 17/12/2024

Work in progress | 60% Completed

9 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 16/12/2024

Work in progress | 60% Completed

8.8 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 10/12/2024

Work in progress | 60% Completed

8.8 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 07/12/2024

Work in progress | 60% Completed

8.8 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 05/12/2024

Work in progress | 60% Completed

8.8 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 02/12/2024

Work in progress | 60% Completed

8.8 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 29/11/2024

Work in progress | 60% Completed

8.8 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 26/11/2024

Work in progress | 60% Completed

8.8 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 22/11/2024

Work in progress | 60% Completed

8.8 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 19/11/2024

Work in progress | 60% Completed

8.8 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 16/11/2024

Work in progress | 60% Completed

8.8 KM pipe laid 850 nos FHTC given

Kannur PH Sn 3 AE
Date: 12/11/2024

Work in progress | 60% Completed

8.8 KM pipe laid 843 nos FHTC given

Kannur PH Sn 3 AE
Date: 08/11/2024

Work in progress | 60% Completed

8.8 KM pipe laid 835 nos FHTC given

Kannur PH Sn 3 AE
Date: 07/11/2024

Work in progress | 60% Completed

8.8 KM pipe laid 835 nos FHTC given

Kannur PH Sn 3 AE
Date: 04/11/2024

Work in progress | 60% Completed

8.8 KM pipe laid 820 nos FHTC given

Kannur PH Sn 3 AE
Date: 02/11/2024

Work in progress | 60% Completed

8.5 KM pipe laid 810 nos FHTC given

Kannur PH Sn 3 AE
Date: 30/10/2024

Work in progress | 60% Completed

8.5 KM pipe laid 810 nos FHTC given

Kannur PH Sn 3 AE
Date: 28/10/2024

Work in progress | 60% Completed

8.3 KM pipe laid 805 nos FHTC given

Kannur PH Sn 3 AE
Date: 26/10/2024

Work in progress | 60% Completed

8.3 KM pipe laid 805 nos FHTC given

Kannur PH Sn 3 AE
Date: 24/10/2024

Work in progress | 60% Completed

8.3 KM pipe laid 805 nos FHTC given

Kannur PH Sn 3 AE
Date: 21/10/2024

Work in progress | 59% Completed

8 KM pipe laid 790 nos FHTC given

Kannur PH Sn 3 AE
Date: 18/10/2024

Work in progress | 58% Completed

7.8 KM pipe laid 780 nos FHTC given

Kannur PH Sn 3 AE
Date: 16/10/2024

Work in progress | 58% Completed

7.8 KM pipe laid 780 nos FHTC given

Kannur PH Sn 3 AE
Date: 14/10/2024

Work in progress | 57% Completed

7.6 KM pipe laid 760 nos FHTC given

Kannur PH Sn 3 AE
Date: 10/10/2024

Work in progress | 57% Completed

7.3 KM pipe laid 730 nos FHTC given

Kannur PH Sn 3 AE
Date: 07/10/2024

Work in progress | 57% Completed

7 KM pipe laid 710 nos FHTC given

Kannur PH Sn 3 AE
Date: 04/10/2024

Work in progress | 55% Completed

6.6 KM pipe laid 690 nos FHTC given

Kannur PH Sn 3 AE
Date: 01/10/2024

Work in progress | 55% Completed

6.6 KM pipe laid 690 nos FHTC given

Kannur PH Sn 3 AE
Date: 28/09/2024

Work in progress | 55% Completed

6.6 KM pipe laid 690 nos FHTC given

Kannur PH Sn 3 AE
Date: 26/09/2024

Work in progress | 55% Completed

6.6 KM pipe laid 690 nos FHTC given

Kannur PH Sn 3 AE
Date: 23/09/2024

Work in progress | 55% Completed

6 KM pipe laid 650 nos FHTC given

Kannur PH Sn 3 AE
Date: 20/09/2024

Work in progress | 55% Completed

6 KM pipe laid 650 nos FHTC given

Kannur PH Sn 3 AE
Date: 18/09/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 12/09/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 09/09/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 06/09/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 03/09/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 30/08/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 27/08/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 24/08/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 22/08/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 19/08/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 16/08/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 12/08/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 08/08/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 05/08/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 02/08/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 30/07/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 27/07/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 23/07/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 20/07/2024

Work in progress | 48% Completed

5.2 KM pipe laid 600 nos FHTC given

Kannur PH Sn 3 AE
Date: 19/07/2024

Work in progress | 48% Completed

5.2 KM pipe laid 550 nos FHTC given

Kannur PH Sn 3 AE
Date: 17/07/2024

Work in progress | 48% Completed

5.2 KM pipe laid 550 nos FHTC given

Kannur PH Sn 3 AE
Date: 15/07/2024

Work in progress | 43% Completed

4.3 KM pipe laid 410 nos FHTC given

Kannur PH Sn 3 AE
Date: 10/07/2024

Work in progress | 43% Completed

4.3 KM pipe laid 410 nos FHTC given

Kannur PH Sn 3 AE
Date: 06/07/2024

Work in progress | 43% Completed

4.3 KM pipe laid 410 nos FHTC given

Kannur PH Sn 3 AE
Date: 03/07/2024

Work in progress | 43% Completed

4.3 KM pipe laid 410 nos FHTC given

Kannur PH Sn 3 AE
Date: 01/07/2024

Work in progress | 42% Completed

4.3 KM pipe laid 400 nos FHTC given

Kannur PH Sn 3 AE
Date: 27/06/2024

Work in progress | 42% Completed

4.3 KM pipe laid 400 nos FHTC given

Kannur PH Sn 3 AE
Date: 24/06/2024

Work in progress | 42% Completed

4.3 KM pipe laid 400 nos FHTC given

Kannur PH Sn 3 AE
Date: 22/06/2024

Work in progress | 42% Completed

4.3 KM pipe laid 400 nos FHTC given

Kannur PH Sn 3 AE
Date: 18/06/2024

Work in progress | 42% Completed

4.3 KM pipe laid 400 nos FHTC given

Kannur PH Sn 3 AE
Date: 13/06/2024

Work in progress | 42% Completed

4.3 KM pipe laid 400 nos FHTC given

Kannur PH Sn 3 AE
Date: 10/06/2024

Work in progress | 42% Completed

4.3 KM pipe laid 400 nos FHTC given

Kannur PH Sn 3 AE
Date: 05/06/2024

Work in progress | 42% Completed

4.3 KM pipe laid 400 nos FHTC given

Kannur PH Sn 3 AE
Date: 01/06/2024

Work in progress | 42% Completed

4.3 KM pipe laid 400 nos FHTC given

Kannur PH Sn 3 AE
Date: 29/05/2024

Work in progress | 40% Completed

4 KM pipe laid 350 nos FHTC given

Kannur PH Sn 3 AE
Date: 25/05/2024

Work in progress | 40% Completed

4 KM pipe laid 350 nos FHTC given

Kannur PH Sn 3 AE
Date: 22/05/2024

Work in progress | 40% Completed

4 KM pipe laid 350 nos FHTC given

Kannur PH Sn 3 AE
Date: 18/05/2024

Work in progress | 40% Completed

4 KM pipe laid 350 nos FHTC given

Kannur PH Sn 3 AE
Date: 14/05/2024

Work in progress | 30% Completed

3.5 KM pipe laid 300 nos FHTC given

Kannur PH Sn 3 AE
Date: 10/05/2024

Work in progress | 30% Completed

3.5 KM pipe laid 300 nos FHTC given

Kannur PH Sn 3 AE
Date: 07/05/2024

Work in progress | 30% Completed

3 KM pipe laid 250 nos FHTC given

Kannur PH Sn 3 AE
Date: 02/05/2024

Work in progress | 30% Completed

3 KM pipe laid 250 nos FHTC given

Kannur PH Sn 3 AE
Date: 27/04/2024

Work in progress | 30% Completed

30 % COMPLETED.

Kannur PH Sn 3 AE
Date: 24/04/2024

Work in progress | 30% Completed

30 % COMPLETED.