| Perlasserry Sn 1 |
| Date: 16/10/2025 |
Work has been completed | 100% Completed
work completed.
| Perlasserry Sn 1 |
| Date: 23/09/2024 |
Work has been completed | 100% Completed
work completed and final bill submitted.
| Perlasserry Sn 1 |
| Date: 18/09/2024 |
Work in progress | 99% Completed
Final Bill submitted on 27/08/2024.
| Perlasserry Sn 1 |
| Date: 09/09/2024 |
Work in progress | 99% Completed
Final Bill submitted on 27/08/2024.
| Perlasserry Sn 1 |
| Date: 04/09/2024 |
Work in progress | 99% Completed
Final Bill submitted on 27/08/2024
| Perlasserry Sn 1 |
| Date: 27/08/2024 |
Work in progress | 98% Completed
Final Bill under preparation.
| Perlasserry Sn 1 |
| Date: 21/08/2024 |
Work in progress | 98% Completed
work is ongoing
| Perlasserry Sn 1 |
| Date: 13/08/2024 |
Work in progress | 98% Completed
work is ongoing
| Perlasserry Sn 1 |
| Date: 09/08/2024 |
Work in progress | 98% Completed
work is ongoing
| Perlasserry Sn 1 |
| Date: 05/08/2024 |
Work in progress | 95% Completed
work is ongoing
| Perlasserry Sn 1 |
| Date: 29/07/2024 |
Work in progress | 90% Completed
work is ongoing
| Perlasserry Sn 1 |
| Date: 26/07/2024 |
Work in progress | 90% Completed
work is ongoing
| Perlasserry Sn 1 |
| Date: 23/07/2024 |
Work in progress | 90% Completed
ongoing
| Perlasserry Sn 1 |
| Date: 19/07/2024 |
Work in progress | 90% Completed
work in progress
| Perlasserry Sn 1 |
| Date: 08/07/2024 |
Work in progress | 84% Completed
464 nos of FHTC completed
| Perlasserry Sn 1 |
| Date: 03/07/2024 |
Work in progress | 84% Completed
464 nos of FHTC completed
| Perlasserry Sn 1 |
| Date: 26/06/2024 |
Work in progress | 79% Completed
Fifth part bill submitted.449 nos of FHTC completed .Request for time extension (upto 30/07/2024)sent to division office
| Perlasserry Sn 1 |
| Date: 20/06/2024 |
Work in progress | 79% Completed
Fifth part bill submitted.449 nos of FHTC completed .Request for time extension (upto 30/07/2024)sent to division office
| Perlasserry Sn 1 |
| Date: 12/06/2024 |
Work in progress | 79% Completed
Fifth part bill submitted.449 nos of FHTC completed .Request for time extension (upto 30/07/2024)sent to division office.
| Perlasserry Sn 1 |
| Date: 07/06/2024 |
Work in progress | 79% Completed
Fifth part bill submitted.449 nos of FHTC completed .Request for time extension (upto 30/07/2024)sent to division office.
| Perlasserry Sn 1 |
| Date: 29/05/2024 |
Work in progress | 79% Completed
Fifth part bill submitted.449 nos of FHTC completed and 35 nos of application pending. Request for time extension sent to division office.
| Perlasserry Sn 1 |
| Date: 21/05/2024 |
Work in progress | 77% Completed
449 nos of FHTC completed and 35 nos of application pending. Request for time extension sent to division office.
| Perlasserry Sn 1 |
| Date: 14/05/2024 |
Work in progress | 77% Completed
449 nos of FHTC completed and 35 nos of application pending. Request for time extension sent to division office.
| Perlasserry Sn 1 |
| Date: 09/05/2024 |
Work in progress | 77% Completed
449 nos of FHTC completed and 35 nos of application pending. Request for time extension sent to division office.
| Perlasserry Sn 1 |
| Date: 04/05/2024 |
Work in progress | 77% Completed
449 nos of FHTC completed and 35 nos of application pending. Request for time extension sent to division office.
| Perlasserry Sn 1 |
| Date: 23/04/2024 |
Work in progress | 68% Completed
Out of 490 nos of applications recieved , 443 nos of FHTC completed yet.
| Perlasserry Sn 1 |
| Date: 16/04/2024 |
Work in progress | 59% Completed
Out of 45nos of applications recieved in January 2024, 42 nos of FHTC & 3 nos of HTC completed yet.
| Perlasserry Sn 1 |
| Date: 06/04/2024 |
Work in progress | 59% Completed
Out of 45nos of applications recieved in January 2024, 42 nos of FHTC & 3 nos of HTC completed yet.
| Perlasserry Sn 1 |
| Date: 01/04/2024 |
Work in progress | 59% Completed
Out of 44nos of applications recieved in January 2024, 32nos of FHTC & 12 nos of HTC completed yet.
| Perlasserry Sn 1 |
| Date: 25/03/2024 |
Work in progress | 59% Completed
Out of 44nos of applications recieved in January 2024, 14nos of FHTC & 30 nos of HTC completed yet.
| Perlasserry Sn 1 |
| Date: 20/03/2024 |
Work in progress | 59% Completed
Out of 44nos of applications recieved in January 2024, 14nos of FHTC & 30 nos of HTC completed yet.
| Perlasserry Sn 1 |
| Date: 13/03/2024 |
Work in progress | 59% Completed
Out of 44nos of applications recieved in January 2024, 14nos of FHTC & 20nos of HTC completed yet.
| Perlasserry Sn 1 |
| Date: 27/02/2024 |
Work in progress | 58% Completed
44nos of applications recieved after Jan-31st -2024 and awaiting for 20mm upvc pipe supply .
| Perlasserry Sn 1 |
| Date: 22/02/2024 |
Work in progress | 58% Completed
44nos of applications recieved after Jan-31st -2024 and awaiting for 20mm upvc pipe supply .
| Perlasserry Sn 1 |
| Date: 14/02/2024 |
Work in progress | 58% Completed
44nos of applications recieved after Jan-31st -2024 and awaiting for 20mm upvc pipe supply .
| Perlasserry Sn 1 |
| Date: 06/02/2024 |
Work in progress | 58% Completed
Final bill is under preparation
| Perlasserry Sn 1 |
| Date: 29/01/2024 |
Work in progress | 58% Completed
Final bill is under preparation
| Perlasserry Sn 1 |
| Date: 24/01/2024 |
Work in progress | 58% Completed
Final bill is under preparation
| Perlasserry Sn 1 |
| Date: 10/01/2024 |
Work in progress | 58% Completed
Final bill is under preparation
| Perlasserry Sn 1 |
| Date: 01/01/2024 |
Work in progress | 58% Completed
Final bill is under preparation
| Perlasserry Sn 1 |
| Date: 21/12/2023 |
Work in progress | 57% Completed
pwd road cutting permission awaiting and cop submitted
| Perlasserry Sn 1 |
| Date: 14/12/2023 |
Work in progress | 57% Completed
pwd road cutting permission awaiting and cop submitted
| Perlasserry Sn 1 |
| Date: 08/12/2023 |
Work in progress | 57% Completed
pwd road cutting permission awaiting and cop submitted
| Perlasserry Sn 1 |
| Date: 06/12/2023 |
Work in progress | 55% Completed
pwd road cutting permission awaiting and cop submitted
| Perlasserry Sn 1 |
| Date: 30/11/2023 |
Work in progress | 54% Completed
pwd road cutting permission awaiting and cop submitted
| Perlasserry Sn 1 |
| Date: 27/11/2023 |
Work in progress | 54% Completed
pwd road cutting permission awaiting and cop submitted
| Perlasserry Sn 1 |
| Date: 24/11/2023 |
Work in progress | 54% Completed
pwd road cutting permission awaiting and cop submitted
| Perlasserry Sn 1 |
| Date: 15/11/2023 |
Work in progress | 53% Completed
work in progress
| Perlasserry Sn 1 |
| Date: 04/11/2023 |
Work in progress | 52% Completed
work in progress
| Perlasserry Sn 1 |
| Date: 31/10/2023 |
Work in progress | 52% Completed
work in progress
| Perlasserry Sn 1 |
| Date: 25/10/2023 |
Work in progress | 45% Completed
work in progress
| Perlasserry Sn 1 |
| Date: 19/10/2023 |
Work in progress | 45% Completed
work in progress
| Perlasserry Sn 1 |
| Date: 16/10/2023 |
Work in progress | 45% Completed
work in progress
| Perlasserry Sn 1 |
| Date: 07/10/2023 |
Work in progress | 45% Completed
work in progress
| Perlasserry Sn 1 |
| Date: 03/10/2023 |
Work in progress | 44% Completed
work in progress
| Perlasserry Sn 1 |
| Date: 29/09/2023 |
Work in progress | 44% Completed
work in progress
| Perlasserry Sn 1 |
| Date: 19/09/2023 |
Work in progress | 44% Completed
300 out of 681 FHTC Completed
| Perlasserry Sn 1 |
| Date: 13/09/2023 |
Work in progress | 44% Completed
TARGET 681nos FHTC 300nos GEO TAG 288nos IMIS 278nos BILLED 180nos 75mm pvc pipe-8kg 4084m/5060m 50mm pvc pipe-8kg 197m/200m 40mm pvc pipe-10kg 100m/100m
| Perlasserry Sn 1 |
| Date: 05/09/2023 |
Work in progress | 44% Completed
work in progress
| Perlasserry Sn 1 |
| Date: 18/05/2023 |
Work in progress | 35% Completed
Work in progress
| Perlasserry Sn 1 |
| Date: 04/05/2023 |
Work in progress | 3% Completed
Work in Progress
| Perlasserry Sn 1 |
| Date: 28/04/2023 |
Work in progress | 3% Completed
Work in Progress
| Perlasserry Sn 1 |
| Date: 25/04/2023 |
Work in progress | 2% Completed
Work in Progress
| Perlasserry Sn 1 |
| Date: 22/04/2023 |
Work in progress | 2% Completed
Work in Progress
| Perlasserry Sn 1 |
| Date: 19/04/2023 |
Work in progress | 2% Completed
Work in Progress
| Perlasserry Sn 1 |
| Date: 16/04/2023 |
Work in progress | 2% Completed
Work in Progress
| Perlasserry Sn 1 |
| Date: 13/04/2023 |
Work in progress | 2% Completed
Work in Progress
| Perlasserry Sn 1 |
| Date: 10/04/2023 |
Work in progress | 1% Completed
Work in Progress
| Perlasserry Sn 1 |
| Date: 04/04/2023 |
Work in progress | 1% Completed
Work in Progress
| Perlasserry Sn 1 |
| Date: 26/03/2023 |
Work has started | 0% Completed
AGREEMENT EXECUTED ON 02.03.2023
| Kannur PH Dn EE |
| Date: 02/03/2023 |
Work has started | 0% Completed
AGREEMENT EXECUTED ON 02.03.2023
| Kannur PH Dn EE |
| Date: 06/02/2023 |
Work has started | 0% Completed
WORK ORDER ISSUED ON 06.02.2023
| Kannur PH Dn EE |
| Date: 31/01/2023 |
Work has started | 0% Completed
TENDER APPROVED BY SE
| Kannur PH Dn EE |
| Date: 26/12/2022 |
Work has started | 0% Completed
TS ISSUED