Perlassery Sn 2 AE
Date: 25/06/2024

Work in progress | 70% Completed

Work in progress | 70% Completed 921 Nos FHTCS provided. Physical progress 70%. 4.300Km pipe laying and 811 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 20/06/2024

Work in progress | 70% Completed

Work in progress | 70% Completed

Perlassery Sn 2 AE
Date: 10/06/2024

Work in progress | 70% Completed

Work in progress | 70% Completed

Perlassery Sn 2 AE
Date: 01/06/2024

Work in progress | 70% Completed

892 Nos FHTCS provided. Physical progress 70%. 4.300Km pipe laying and 811 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 22/05/2024

Work in progress | 70% Completed

890 Nos FHTCS provided. Physical progress 70%. 4.300Km pipe laying and 811 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 17/05/2024

Work in progress | 70% Completed

890 Nos FHTCS provided. Physical progress 70%. 4.300Km pipe laying and 811 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 10/05/2024

Work in progress | 70% Completed

890 Nos FHTCS provided. Physical progress 70%. 4.300Km pipe laying and 811 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 25/04/2024

Work in progress | 70% Completed

872 Nos FHTCS provided. Physical progress 70%. Pipe supplied,4.300Km laying and 811 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 18/04/2024

Work in progress | 70% Completed

835 Nos FHTCS provided. Physical progress 70%. Pipe supplied,4.300Km laying and 811 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 06/04/2024

Work in progress | 70% Completed

835 Nos FHTCS provided. Physical progress 70%. Pipe supplied,4.300Km laying and 811 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 27/03/2024

Work in progress | 70% Completed

835 Nos FHTCS provided. Physical progress 70%. Pipe supplied,4.300Km laying and 811 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 18/03/2024

Work in progress | 70% Completed

835 Nos FHTCS provided. Physical progress 70%. Pipe supplied,4.300Km laying and 811 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 11/03/2024

Work in progress | 70% Completed

835 Nos FHTCS provided. Physical progress 70%. Pipe supplied,4.300Km laying and 811 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 28/02/2024

Work in progress | 70% Completed

821 Nos FHTCS provided. Physical progress 70%. Pipe supplied,4.300Km laying and 811 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 14/02/2024

Work in progress | 70% Completed

739Nos FHTCS provided. Physical progress 70%. Pipe supplied,4.300Km laying and 555Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 06/02/2024

Work in progress | 70% Completed

739Nos FHTCS provided. Physical progress 70%. Pipe supplied,4.300Km laying and 555Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 29/01/2024

Work in progress | 70% Completed

706Nos FHTCS provided. Physical progress 70%. Pipe supplied,4.300Km laying and 555Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 11/01/2024

Work in progress | 70% Completed

706Nos FHTCS provided. Physical progress 70%. Pipe supplied,4.300Km laying and 555Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 20/12/2023

Work in progress | 70% Completed

706Nos FHTCS provided. Physical progress 70%. Pipe supplied,4.300Km laying and 555Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 07/12/2023

Work in progress | 70% Completed

706Nos FHTCS provided. Physical progress 70%. Pipe supplied,4.300Km laying and 555Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 25/11/2023

Work in progress | 70% Completed

706Nos FHTCS provided. Physical progress 70%. Pipe supplied,4.300Km laying and 555Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 18/11/2023

Work in progress | 70% Completed

706Nos FHTCS provided. Physical progress 70%. Pipe supplied,4.300Km laying and 555Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 09/11/2023

Work in progress | 60% Completed

662Nos FHTCS provided. Physical progress 51%. Pipe supplied,4.200Km laying and 324 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 02/11/2023

Work in progress | 51% Completed

626Nos FHTCS provided. Physical progress 51%. Pipe supplied,4.200Km laying and 324 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 27/10/2023

Work in progress | 51% Completed

558Nos FHTCS provided. Physical progress 51%. Pipe supplied,4.100Km laying and 324 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 21/10/2023

Work in progress | 51% Completed

558Nos FHTCS provided. Physical progress 51%. Pipe supplied,4.100Km laying and 324 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 12/10/2023

Work in progress | 50% Completed

558Nos FHTCS provided. Physical progress 50%. Pipe supplied,3.830Km laying and 324 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 03/10/2023

Work in progress | 48% Completed

526Nos FHTCS provided. Physical progress 48%. Pipe supplied,3.520Km laying and 324 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 27/09/2023

Work in progress | 48% Completed

526Nos FHTCS provided. Physical progress 48%. Pipe supplied,3.520Km laying and 324 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 20/09/2023

Work in progress | 48% Completed

507Nos FHTCS provided. Physical progress 48%. Pipe supplied,3.405Km laying and 324 Nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 13/09/2023

Work in progress | 48% Completed

502Nos FHTCS provided. Physical progress 48%. Pipe supplied, 3.310 Km laying and 324 Nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 01/09/2023

Work in progress | 48% Completed

477Nos FHTCS provided. Physical progress 48%. Pipe supplied, 3.310 Km laying and 324 Nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 24/08/2023

Work in progress | 48% Completed

470 Nos FHTCS provided. Physical progress 48%. Pipe supplied, 3.310 Km laying and 324 Nos FHTCS bill submitted.

Attached images

img

Kannur PH Dn EE
Date: 17/08/2023

Work in progress | 46% Completed

456 Nos FHTCS provided. Physical progress 46%. Pipe supplied, 3.075 Km laying and 324 Nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 09/08/2023

Work in progress | 46% Completed

456Nos FHTCS provided. Physical progress 46%. Pipe supplied, 3.075 Km laying and 324 Nos FHTCS bill submitted

Attached images

img

Perlassery Sn 2 AE
Date: 04/08/2023

Work in progress | 45% Completed

445Nos FHTCS provided. Physical progress 45%. Pipe supplied, 3.075 Km laying and 324 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 31/07/2023

Work in progress | 45% Completed

435Nos FHTCS provided. Physical progress 45%. Pipe supplied, 3.075 Km laying and 324 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 27/07/2023

Work in progress | 45% Completed

435Nos FHTCS provided. Physical progress 45%. Pipe supplied, 3.075 Km laying and 324 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 19/07/2023

Work in progress | 45% Completed

414Nos FHTCS provided. Physical progress 45%. Pipe supplied, 3.075 Km laying and 324 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 14/07/2023

Work in progress | 45% Completed

409Nos FHTCS provided. Physical progress 45%. Pipe supplied, 3.075 Km laying and 324 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 10/07/2023

Work in progress | 40% Completed

392Nos FHTCS provided. Physical progress 45%. Pipe supplied, 3.075 Km laying and 324 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 04/07/2023

Work in progress | 40% Completed

364Nos FHTCS provided. Physical progress 45%. Pipe supplied, 3.075 Km laying and 324 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 30/06/2023

Work in progress | 40% Completed

348Nos FHTCS provided. Physical progress 45%. Pipe supplied, 3.075 Km laying and 324 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 24/06/2023

Work in progress | 40% Completed

340 Nos FHTCS provided. Physical progress 40%. Pipe supplied, 3.075 Km laying and 109 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 19/06/2023

Work in progress | 40% Completed

308 Nos FHTCS provided. Physical progress 40%. Pipe supplied, 3.075 Km laying and 109 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 16/06/2023

Work in progress | 40% Completed

270- Nos FHTCS provided. Physical progress 40%. Pipe supplied, 3.075 Km laying and 109 Nos FHTCS bill submitted

Perlassery Sn 2 AE
Date: 13/06/2023

Work in progress | 37% Completed

221Nos FHTC provided. 303Nos HTC provided. Pipe supplied

Perlassery Sn 2 AE
Date: 08/06/2023

Work in progress | 37% Completed

221Nos FHTC provided. 303Nos HTC provided. Pipe supplied

Perlassery Sn 2 AE
Date: 01/06/2023

Work in progress | 36% Completed

199Nos FHTC provided. 325Nos HTC provided. Pipe supplied

Attached images

img

Perlassery Sn 2 AE
Date: 24/05/2023

Work in progress | 33% Completed

176Nos FHTC provided. 319Nos HTC provided. Pipe supplied

Perlassery Sn 2 AE
Date: 18/05/2023

Work in progress | 33% Completed

137 Nos FHTC provided. 220Nos HTC provided. Pipe supplied

Perlassery Sn 2 AE
Date: 15/05/2023

Work in progress | 33% Completed

137 Nos FHTC provided. 220Nos HTC provided. Pipe supplied

Perlassery Sn 2 AE
Date: 10/05/2023

Work in progress | 32% Completed

124 Nos FHTC provided. 216Nos HTC provided. Pipe supplied

Perlassery Sn 2 AE
Date: 02/05/2023

Work in progress | 31% Completed

124 Nos FHTC provided. 216Nos HTC provided. Pipe supplied

Perlassery Sn 2 AE
Date: 26/04/2023

Work in progress | 31% Completed

97 Nos FHTC provided. 218 Nos HTC provided. Pipe supplied

Perlassery Sn 2 AE
Date: 19/04/2023

Work in progress | 30% Completed

77 Nos FHTC provided. 270 Nos HTC provided. Pipe supplied

Perlassery Sn 2 AE
Date: 13/04/2023

Work in progress | 30% Completed

75 Nos FHTC provided. 270 Nos HTC provided. Pipe supplied

Perlassery Sn 2 AE
Date: 09/04/2023

Work in progress | 30% Completed

66 Nos FHTC provided. 199 Nos HTC provided. Pipe supplied

Perlassery Sn 2 AE
Date: 03/04/2023

Work in progress | 30% Completed

40 Nos FHTC provided. 225 Nos HTC provided. Pipe supplied

Perlassery Sn 2 AE
Date: 29/03/2023

Work in progress | 20% Completed

27 Nos FHTC provided. 190 Nos HTC provided. Pipe supplied

Perlassery Sn 2 AE
Date: 22/03/2023

Work in progress | 18% Completed

180 Nos HTC provided. Pipe supplied

Perlassery Sn 2 AE
Date: 18/03/2023

Work in progress | 15% Completed

160 Nos HTC provided. Pipe supplied

Kannur PH Dn EE
Date: 28/01/2023

Work has started | 0% Completed

WORK ORDER ISSUED ON 28.01.2023 BY SE

Kannur PH Dn EE
Date: 04/01/2023

Work has started | 0% Completed

TS ISSUED