Kollam Project Dn EE
Date: 25/03/2026

Work has been completed | 100% Completed

work completed on 25/3/2026

Kollam Project Dn EE
Date: 24/03/2026

Work in progress | 95% Completed

Rebar works under progressing

Attached images

img

Kollam Project Dn EE
Date: 11/03/2026

Work in progress | 90% Completed

Earthwork excavation for drain connecting pond to external drain. Anchor block concreting

Attached images

img img img img img img

Kollam Project Dn EE
Date: 07/03/2026

Work in progress | 90% Completed

Earthwork excavation for drain connecting pond to external drain

Attached images

img

Kollam Project Dn EE
Date: 02/03/2026

Work in progress | 90% Completed

1016 mm MS pipe work under progressing. Earthwork excavation for realignment of 500Di pipe under progressing

Attached images

img img img

Kollam Project Dn EE
Date: 27/02/2026

Work in progress | 90% Completed

Concreting of top slab for sokpit work progressing

Attached images

img img img

Kollam Project Dn EE
Date: 25/02/2026

Work in progress | 80% Completed

Electrical works for security cabin under progressing. Shuttering works for foundation (shifting cathodic protection). Pipe connecting Works for pumping out of sludge sump under progressing

Attached images

img img img img img

Kollam Project Dn EE
Date: 19/02/2026

Work in progress | 70% Completed

Yard lighting works under progressing. Compound wall plastering at rear side of WTP. Earthwork excavation for drain under progressing. Inside plastering of security cabin under progressing

Attached images

img img img img img img img img img

Kollam Project Dn EE
Date: 17/02/2026

Work in progress | 70% Completed

GI pipes coating with aluminium paints for yardlighting. Construction of compound wall for gate at backside of WTP

Attached images

img img img img img

Kollam Project Dn EE
Date: 11/02/2026

Work in progress | 65% Completed

Earth filling works under progressing

Attached images

img img img

Kollam Project Dn EE
Date: 05/02/2026

Work in progress | 65% Completed

Rebar works for Rcc slab around pond under progressing

Attached images

img

Kollam Project Dn EE
Date: 03/02/2026

Work in progress | 65% Completed

Pcc for pathway around pond after laying Geotextiles.

Attached images

img img img img img img

Kollam Project Dn EE
Date: 20/01/2026

Work in progress | 65% Completed

Preparing sides for starting pond works. Basement for security cabin under progressing

Attached images

img img img img img img

Kollam Project Dn EE
Date: 16/01/2026

Work in progress | 65% Completed

Bailing out under progressing

Attached images

img

Kollam Project Dn EE
Date: 15/12/2025

Work in progress | 60% Completed

shuttering works for wall concreting 30cm ht.(3rd lift) under progressing. shuttering works for wall concreting 30cm ht.(3rd lift) under progressing

Attached images

img img

Kollam Project Dn EE
Date: 04/12/2025

Work in progress | 60% Completed

shuttering and rebar works for wall concreting

Attached images

img img

Kollam Project Dn EE
Date: 27/11/2025

Work in progress | 51% Completed

Earthwork excavation for drain connecting pond under progressing

Attached images

img

Kollam Project Dn EE
Date: 31/10/2025

Work in progress | 51% Completed

mechanical works under progressing.Earth levelling under progressing.shuttering works for top slab under progressing

Attached images

img img img img img img img img img

Kollam Project Dn EE
Date: 18/10/2025

Work in progress | 50% Completed

Plastering of wall. shuttering works under progressing

Attached images

img img

Kollam Project Dn EE
Date: 20/09/2025

Work in progress | 47% Completed

Rebarwork under progressing. Pcc works under progressing for storm water drain connecting emergency exit to nearest drain.Shuttering works for drain under progressing

Attached images

img img img img img

Kollam Project Dn EE
Date: 15/09/2025

Work in progress | 47% Completed

Plastering works under progressing

Attached images

img img img img

Kollam Project Dn EE
Date: 12/08/2025

Work in progress | 45% Completed

Pcc for footing of compound wall under progressing. Earthwork Excavation for column footing of compound wall at back side of pump house under progressing (gate no. 2). Earthwork Excavation for column footing of compound wall at back side of chemical house under progressing

Attached images

img img img img

Kollam Project Dn EE
Date: 10/06/2025

Work in progress | 40% Completed

shuttering works under progressing.Fixing of polycarbonate sheet on top of raw water channel. casting of precast slab(1.5*0.6*.1) under progressing

Attached images

img img img img img img img

Kollam Project Dn EE
Date: 03/06/2025

Work in progress | 40% Completed

Concreting of cast-in-situ top slab(10thk) b/w cfl1 and areator will be continue after lunch break.

Attached images

img img img img

Kollam Project Dn EE
Date: 22/05/2025

Work in progress | 40% Completed

Roof covering work for CFL Bridge progressing. Shuttering for cast insitu top slab of drain near aerator progressing.Rebar works for top slab of drain progressing at ch:403m.Earthwork excavation for storm water drain from ch:330 to detention pond.Rebar works for top slab of drain progressing at ch:403m.CFL bridge cover fabrication progressing

Attached images

img img img img img img

Kollam Project Dn EE
Date: 22/04/2025

Work in progress | 35% Completed

Solid block work construction for compound wall near eastside of areator

Attached images

img img

Kollam Project Dn EE
Date: 17/04/2025

Work in progress | 35% Completed

Solid block work construction for compound wall near eastside of CFL1 progressing. 200 cft coarse aggregate reached on site. Shuttering work for (20cm thick) precast rcc top slab of drain

Attached images

img img img img

Kollam Project Dn EE
Date: 10/04/2025

Work in progress | 35% Completed

Solid block work construction for compound wall near backside of chemical house progressing

Attached images

img

Kollam Project Dn EE
Date: 02/04/2025

Work in progress | 35% Completed

Shuttering for top slab of drain from ch:90m. RR masonry for compound wall near aerator. Earthwork excavation for detention pond

Attached images

img img img img

Kollam Project Dn EE
Date: 25/03/2025

Work in progress | 35% Completed

Backfilling and Site clearance work progressing. Shuttering for top slab of drain at ch:200m

Attached images

img img img

Kollam Project Dn EE
Date: 17/03/2025

Work in progress | 35% Completed

RR masonry for compound wall near CFL1 progressing. Rebar work for top slab of drain. Shuttering for cast in situ top slab of drain at ch :60m near pump house (northside). Solid block work construction for compound wall near CFL3 progressing

Attached images

img img img img

Kollam Project Dn EE
Date: 11/03/2025

Work in progress | 35% Completed

RR masonary under progressing. RR masonry for compound wall under progressing @ back side of areator. Concreting of RCC wall (2nd lift) b/w CFL1 and areator.Construction of Brick work for compound wall @ entrance

Attached images

img img img img

Kollam Project Dn EE
Date: 05/03/2025

Work in progress | 35% Completed

Rebar work for storm water drain near north east side of aerator. RR masonry for compound wall near entrance progressing. Earthwork excavation for detention pond progressing. Concreting of rcc wall(1st lift) near east side of admin building (from ch:32m)

Attached images

img img img img

Kollam Project Dn EE
Date: 01/03/2025

Work in progress | 30% Completed

Concreting of RCC wall 2nd lift. From ch. 140. Rebar works under progressing from ch. 201. Earthwork excavation under progressing. Shuttering for haunch under progressing b/w areator and cfl1

Attached images

img img img img

Kollam Project Dn EE
Date: 26/02/2025

Work in progress | 30% Completed

Earthwork excavation for detention pond. Rebar work for storm water drain near north west side of aerator progressing

Attached images

img img

Kollam Project Dn EE
Date: 20/02/2025

Work in progress | 30% Completed

Concreting of rcc wall 2nd lift near aerator(from ch:376.515m).Shuttering work for catch basin near pump house. Compound wall plastering near pump house.Excavation for detention pond

Attached images

img img img img img img

Kollam Project Dn EE
Date: 14/02/2025

Work in progress | 30% Completed

Solid block work construction for compound wall near pump house. Compound wall plastering progressing near north east of chemical house progressing. Concreting of rcc wall 2nd lift near aerator progressing. Shuttering work of rcc wall (2nd lift) for drain near aerator from ch:365.515m progressing. Compound wall plastering progressing near north east of chemical house

Attached images

img img img img img img

Kollam Project Dn EE
Date: 07/02/2025

Work in progress | 25% Completed

Concreting of cast insitu top slab of drain near chlorine building from ch:190m. Concreting of rcc wall first lift (1.2m)near north east side of aerator. Earthwork excavation for drain near chlorine building. Concreting of rcc wall first lift (1.2m)near north east side of aerator progressing. Excavation for rcc drain near (kwa office) at ch:230m

Attached images

img img img img img

Kollam Project Dn EE
Date: 02/02/2025

Work in progress | 25% Completed

Concreting of RCC wall under progressing at back side of CFL1

Attached images

img

Kollam Project Dn EE
Date: 25/01/2025

Work in progress | 25% Completed

Concreting of rcc base slab at backside of chemical house. Rebar works under progressing infront of areator

Attached images

img img

Kollam Project Dn EE
Date: 23/01/2025

Work in progress | 25% Completed

Shuttering work for rcc drain near south east side of aerator

Attached images

img

Kollam Project Dn EE
Date: 18/01/2025

Work in progress | 20% Completed

Concreting of rcc stem from ch. 355.515 under progressing. Backfilling of temporary pit at backside of admin building. Rebar works at back side of chemical house. Shuttering works for haunch at back side of areator under progressing. Concreting of rcc stem,2nd lift from ch. 355.515 to ch. 365.515 under progressing. Curing and Pcc for storm water drain (1.7 m width started from back side of chemical house.

Attached images

img img img img img img img img

Kollam Project Dn EE
Date: 13/01/2025

Work in progress | 15% Completed

Shuttering work for haunch portion of drain near chlorine building (from ch:185m). Placing of precast slab on top of drain from ch. 54.5

Attached images

img img

Kollam Project Dn EE
Date: 03/01/2025

Work in progress | 15% Completed

Concreting of rcc base slab for drain from ch. 330 progressing. Fixing of precast slab on top of drain at ch. 260

Attached images

img img img

Kollam Project Dn EE
Date: 31/12/2024

Work in progress | 15% Completed

Concreting for rcc wall, 2nd lift from ch. 154 to ch. 181. Progressing.

Attached images

img img

Kollam Project Dn EE
Date: 19/12/2024

Work in progress | 12% Completed

Shuttering work for wall of drain 2 nd lift near KWA office. Rebar work for wall of drain near chlorine building. casting of precast RCC slab for drain progressing. Concreting of RCC wall near pump house.

Attached images

img

Kollam Project Dn EE
Date: 12/12/2024

Work in progress | 12% Completed

Casting of Precast rcc top slab for drain(no:79 ) progressing.Shuttering work for wall of RCC drain near admin building ( from ch: 45m to 60m). RCC for base slab of storm water drain near chlorine building ( from ch:150 m). Concreting of haunch for base slab of drain near pump house ( at ch 140m). Rebar work for storm water drain ( from ch:150 m)

Attached images

img img img img img

Kollam Project Dn EE
Date: 10/12/2024

Work in progress | 10% Completed

Curing work progressing

Attached images

img

Kollam Project Dn EE
Date: 04/12/2024

Work in progress | 7% Completed

Rebar works progressing. Ch. 110 ( near pumphouse). Restarted Concreting after lunch break: Rcc walls for storm water drain.. Ch:60- Ch :80.Concreting rcc wall for strom water drain. Ch:60 to ch :80 (back side of admin building).Rebar works at ch: 90(back side of pumphouse)

Attached images

img img img img img

Kollam Project Dn EE
Date: 18/11/2024

Work in progress | 7% Completed

Rebar work PCC drain progressing near pump house.

Attached images

img

Kollam Project Dn EE
Date: 16/11/2024

Work in progress | 5% Completed

Pcc for storm water drain progressing. (Additional 0.15 m depth provided from existing level)

Attached images

img

Kollam Project Dn EE
Date: 14/11/2024

Work in progress | 5% Completed

Rebar work (cutting and bending) for drain. Shuttering work for wall of drain

Kollam Project Dn EE
Date: 11/11/2024

Work in progress | 5% Completed

RCC base slab haunch portion concreting progressing (near pump house)

Kollam Project Dn EE
Date: 05/11/2024

Work in progress | 5% Completed

Concreting of precast RCC top slab of storm water drain work progressing.

Kollam Project Dn EE
Date: 04/11/2024

Work in progress | 2% Completed

PCC work progressing

Attached images

img

Kollam Project Dn EE
Date: 27/10/2024

Work in progress | 1% Completed

Excavation Leveling work progressing.

Attached images

img img img img

Kollam Project Dn EE
Date: 25/10/2024

Work in progress | 1% Completed

Excavation Leveling work progressing

Attached images

img