| Kollam Project Dn EE |
| Date: 25/03/2026 |
Work has been completed | 100% Completed
work completed on 25/3/2026
| Kollam Project Dn EE |
| Date: 24/03/2026 |
| Kollam Project Dn EE |
| Date: 11/03/2026 |
| Kollam Project Dn EE |
| Date: 07/03/2026 |
| Kollam Project Dn EE |
| Date: 02/03/2026 |
| Kollam Project Dn EE |
| Date: 27/02/2026 |
| Kollam Project Dn EE |
| Date: 25/02/2026 |
| Kollam Project Dn EE |
| Date: 19/02/2026 |
| Kollam Project Dn EE |
| Date: 17/02/2026 |
| Kollam Project Dn EE |
| Date: 11/02/2026 |
| Kollam Project Dn EE |
| Date: 05/02/2026 |
| Kollam Project Dn EE |
| Date: 03/02/2026 |
| Kollam Project Dn EE |
| Date: 20/01/2026 |
| Kollam Project Dn EE |
| Date: 16/01/2026 |
| Kollam Project Dn EE |
| Date: 15/12/2025 |
| Kollam Project Dn EE |
| Date: 04/12/2025 |
| Kollam Project Dn EE |
| Date: 27/11/2025 |
| Kollam Project Dn EE |
| Date: 31/10/2025 |
| Kollam Project Dn EE |
| Date: 18/10/2025 |
| Kollam Project Dn EE |
| Date: 20/09/2025 |
| Kollam Project Dn EE |
| Date: 15/09/2025 |
| Kollam Project Dn EE |
| Date: 12/08/2025 |
Work in progress | 45% Completed
Pcc for footing of compound wall under progressing. Earthwork Excavation for column footing of compound wall at back side of pump house under progressing (gate no. 2). Earthwork Excavation for column footing of compound wall at back side of chemical house under progressing
Attached images
| Kollam Project Dn EE |
| Date: 10/06/2025 |
| Kollam Project Dn EE |
| Date: 03/06/2025 |
| Kollam Project Dn EE |
| Date: 22/05/2025 |
Work in progress | 40% Completed
Roof covering work for CFL Bridge progressing. Shuttering for cast insitu top slab of drain near aerator progressing.Rebar works for top slab of drain progressing at ch:403m.Earthwork excavation for storm water drain from ch:330 to detention pond.Rebar works for top slab of drain progressing at ch:403m.CFL bridge cover fabrication progressing
Attached images
| Kollam Project Dn EE |
| Date: 22/04/2025 |
| Kollam Project Dn EE |
| Date: 17/04/2025 |
| Kollam Project Dn EE |
| Date: 10/04/2025 |
| Kollam Project Dn EE |
| Date: 02/04/2025 |
| Kollam Project Dn EE |
| Date: 25/03/2025 |
| Kollam Project Dn EE |
| Date: 17/03/2025 |
| Kollam Project Dn EE |
| Date: 11/03/2025 |
| Kollam Project Dn EE |
| Date: 05/03/2025 |
Work in progress | 35% Completed
Rebar work for storm water drain near north east side of aerator. RR masonry for compound wall near entrance progressing. Earthwork excavation for detention pond progressing. Concreting of rcc wall(1st lift) near east side of admin building (from ch:32m)
Attached images
| Kollam Project Dn EE |
| Date: 01/03/2025 |
| Kollam Project Dn EE |
| Date: 26/02/2025 |
| Kollam Project Dn EE |
| Date: 20/02/2025 |
| Kollam Project Dn EE |
| Date: 14/02/2025 |
Work in progress | 30% Completed
Solid block work construction for compound wall near pump house. Compound wall plastering progressing near north east of chemical house progressing. Concreting of rcc wall 2nd lift near aerator progressing. Shuttering work of rcc wall (2nd lift) for drain near aerator from ch:365.515m progressing. Compound wall plastering progressing near north east of chemical house
Attached images
| Kollam Project Dn EE |
| Date: 07/02/2025 |
Work in progress | 25% Completed
Concreting of cast insitu top slab of drain near chlorine building from ch:190m. Concreting of rcc wall first lift (1.2m)near north east side of aerator. Earthwork excavation for drain near chlorine building. Concreting of rcc wall first lift (1.2m)near north east side of aerator progressing. Excavation for rcc drain near (kwa office) at ch:230m
Attached images
| Kollam Project Dn EE |
| Date: 02/02/2025 |
| Kollam Project Dn EE |
| Date: 25/01/2025 |
| Kollam Project Dn EE |
| Date: 23/01/2025 |
| Kollam Project Dn EE |
| Date: 18/01/2025 |
Work in progress | 20% Completed
Concreting of rcc stem from ch. 355.515 under progressing. Backfilling of temporary pit at backside of admin building. Rebar works at back side of chemical house. Shuttering works for haunch at back side of areator under progressing. Concreting of rcc stem,2nd lift from ch. 355.515 to ch. 365.515 under progressing. Curing and Pcc for storm water drain (1.7 m width started from back side of chemical house.
Attached images
| Kollam Project Dn EE |
| Date: 13/01/2025 |
| Kollam Project Dn EE |
| Date: 03/01/2025 |
| Kollam Project Dn EE |
| Date: 31/12/2024 |
| Kollam Project Dn EE |
| Date: 19/12/2024 |
| Kollam Project Dn EE |
| Date: 12/12/2024 |
Work in progress | 12% Completed
Casting of Precast rcc top slab for drain(no:79 ) progressing.Shuttering work for wall of RCC drain near admin building ( from ch: 45m to 60m). RCC for base slab of storm water drain near chlorine building ( from ch:150 m). Concreting of haunch for base slab of drain near pump house ( at ch 140m). Rebar work for storm water drain ( from ch:150 m)
Attached images
| Kollam Project Dn EE |
| Date: 10/12/2024 |
| Kollam Project Dn EE |
| Date: 04/12/2024 |
Work in progress | 7% Completed
Rebar works progressing. Ch. 110 ( near pumphouse). Restarted Concreting after lunch break: Rcc walls for storm water drain.. Ch:60- Ch :80.Concreting rcc wall for strom water drain. Ch:60 to ch :80 (back side of admin building).Rebar works at ch: 90(back side of pumphouse)
Attached images
| Kollam Project Dn EE |
| Date: 18/11/2024 |
| Kollam Project Dn EE |
| Date: 16/11/2024 |
| Kollam Project Dn EE |
| Date: 14/11/2024 |
Work in progress | 5% Completed
Rebar work (cutting and bending) for drain. Shuttering work for wall of drain
| Kollam Project Dn EE |
| Date: 11/11/2024 |
Work in progress | 5% Completed
RCC base slab haunch portion concreting progressing (near pump house)
| Kollam Project Dn EE |
| Date: 05/11/2024 |
Work in progress | 5% Completed
Concreting of precast RCC top slab of storm water drain work progressing.
| Kollam Project Dn EE |
| Date: 04/11/2024 |
| Kollam Project Dn EE |
| Date: 27/10/2024 |