Kollam WS Sn 1 - AE
Date: 31/08/2024

Work has been completed | 100% Completed

100 % COMPLETED, Final Bill submitted.

Kollam WS Sn 1 - AE
Date: 19/08/2024

Work has been completed | 100% Completed

100 % COMPLETED, Final Bill submitted.

Kollam WS Sn 1 - AE
Date: 16/08/2024

Work has been completed | 100% Completed

100 % COMPLETED, Final Bill submitted.

Kollam WS Sn 1 - AE
Date: 12/08/2024

Work in progress | 79% Completed

79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 09/08/2024

Work in progress | 79% Completed

79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 07/08/2024

Work in progress | 79% Completed

79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 05/08/2024

Work in progress | 79% Completed

79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 01/08/2024

Work in progress | 79% Completed

79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 29/07/2024

Work in progress | 79% Completed

79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 25/07/2024

Work in progress | 79% Completed

79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 22/07/2024

Work in progress | 79% Completed

79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 15/07/2024

Work in progress | 60% Completed

60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 09/07/2024

Work in progress | 60% Completed

60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 06/07/2024

Work in progress | 60% Completed

60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 02/07/2024

Work in progress | 60% Completed

60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 27/06/2024

Work in progress | 60% Completed

60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 24/06/2024

Work in progress | 60% Completed

60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 21/06/2024

Work in progress | 60% Completed

60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 18/06/2024

Work in progress | 60% Completed

60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 13/06/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 10/06/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 07/06/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 04/06/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 31/05/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 27/05/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 24/05/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 20/05/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 16/05/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 13/05/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 10/05/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 06/05/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 03/05/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 29/04/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 25/04/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 22/04/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 19/04/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 15/04/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 11/04/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 08/04/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 05/04/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 02/04/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 30/03/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 27/03/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 25/03/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 21/03/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 18/03/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 15/03/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 11/03/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 07/03/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 04/03/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 01/03/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 27/02/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED

Kollam WS Sn 1 - AE
Date: 24/02/2024

Work in progress | 40% Completed

40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED.

Kollam WS Sn 1 - AE
Date: 20/02/2024

Work in progress | 30% Completed

30 % COMPLETED, 140 NOS. OF TAP DISCONNECTED.

Kollam WS Sn 1 - AE
Date: 17/02/2024

Work in progress | 30% Completed

30 % COMPLETED, 140 NOS. OF TAP DISCONNECTED.

Kollam WS Sub Dn - AEE
Date: 15/02/2024

Work in progress | 25% Completed

25 % COMPLETED, 130 NOS. OF TAP DISCONNECTED.