| Kannur PH Sn 3 AE |
| Date: 25/03/2026 |
Work has been completed | 100% Completed
Work completed
| Kannur PH Sn 3 AE |
| Date: 12/03/2026 |
Work in progress | 90% Completed
90% work completed
| Kannur PH Sn 3 AE |
| Date: 02/03/2026 |
Work in progress | 90% Completed
90% work completed
| Kannur PH Sn 3 AE |
| Date: 17/02/2026 |
Work in progress | 90% Completed
90% work completed
| Kannur PH Sn 3 AE |
| Date: 04/02/2026 |
Work in progress | 90% Completed
90% work completed
| Kannur PH Sn 3 AE |
| Date: 21/01/2026 |
Work in progress | 90% Completed
90% work completed
| Kannur PH Sn 3 AE |
| Date: 15/01/2026 |
Work in progress | 90% Completed
90% work completed
| Kannur PH Sn 3 AE |
| Date: 06/01/2026 |
Work in progress | 90% Completed
90% work completed
| Kannur PH Sn 3 AE |
| Date: 27/12/2025 |
Work in progress | 90% Completed
90% work completed
| Kannur PH Sn 3 AE |
| Date: 15/12/2025 |
Work in progress | 90% Completed
90% work completed
| Kannur PH Sn 3 AE |
| Date: 04/12/2025 |
Work in progress | 90% Completed
90% work completed
| Kannur PH Sn 3 AE |
| Date: 24/11/2025 |
Work in progress | 90% Completed
90% work completed
| Kannur PH Sn 3 AE |
| Date: 12/11/2025 |
Work in progress | 80% Completed
340 m pipe laid
| Kannur PH Sn 3 AE |
| Date: 03/11/2025 |
Work in progress | 50% Completed
300 m pipe laid
| Kannur PH Sn 3 AE |
| Date: 22/10/2025 |
Work in progress | 50% Completed
300 m pipe laid
| Kannur PH Sn 3 AE |
| Date: 04/10/2025 |
Work in progress | 50% Completed
300 m pipe laid
| Kannur PH Sn 3 AE |
| Date: 10/09/2025 |
Work in progress | 50% Completed
300 m pipe laid
| Kannur PH Sn 3 AE |
| Date: 30/08/2025 |
Work in progress | 50% Completed
300 m pipe laid
| Kannur PH Sn 3 AE |
| Date: 08/08/2025 |
Work in progress | 50% Completed
300 m pipe laid
| Kannur PH Sn 3 AE |
| Date: 31/07/2025 |
Work in progress | 50% Completed
300 m pipe laid
| Kannur PH Sn 3 AE |
| Date: 19/07/2025 |
Work in progress | 50% Completed
300 m pipe laid
| Kannur PH Sn 3 AE |
| Date: 14/07/2025 |
Work in progress | 50% Completed
300 m pipe laid
| Kannur PH Sn 3 AE |
| Date: 30/06/2025 |
Work in progress | 50% Completed
300 m pipe laid
| Kannur PH Sn 3 AE |
| Date: 27/06/2025 |
Work in progress | 45% Completed
300m pipe laid
| Kannur PH Sn 3 AE |
| Date: 17/06/2025 |
Work in progress | 45% Completed
300m pipe laid
| Kannur PH Sn 3 AE |
| Date: 29/05/2025 |
Work in progress | 45% Completed
300m pipe laid
| Kannur PH Sn 3 AE |
| Date: 19/05/2025 |
Work in progress | 45% Completed
300m pipe laid
| Kannur PH Sn 3 AE |
| Date: 03/05/2025 |
Work in progress | 45% Completed
300m pipe laid
| Kannur PH Sn 3 AE |
| Date: 05/04/2025 |
Work in progress | 45% Completed
300m pipe laid
| Kannur PH Sn 3 AE |
| Date: 29/03/2025 |
Work in progress | 45% Completed
300m pipe laid
| Kannur PH Sn 3 AE |
| Date: 27/03/2025 |
Work in progress | 45% Completed
300m pipe laid
| Kannur PH Sn 3 AE |
| Date: 03/03/2025 |
Work in progress | 15% Completed
15% Completed,100 M PIPE LAID
| Kannur PH Sn 3 AE |
| Date: 22/02/2025 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 12/02/2025 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 01/02/2025 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 29/01/2025 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 24/01/2025 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 22/01/2025 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 18/01/2025 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 10/01/2025 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 04/01/2025 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 31/12/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 24/12/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 21/12/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 20/12/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 17/12/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 16/12/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 10/12/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 07/12/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 05/12/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 02/12/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 29/11/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 26/11/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted
| Kannur PH Sn 3 AE |
| Date: 22/11/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted.
| Kannur PH Sn 3 AE |
| Date: 19/11/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted.
| Kannur PH Sn 3 AE |
| Date: 16/11/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted.
| Kannur PH Sn 3 AE |
| Date: 12/11/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted.
| Kannur PH Sn 3 AE |
| Date: 08/11/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted.
| Kannur PH Sn 3 AE |
| Date: 07/11/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted.
| Kannur PH Sn 3 AE |
| Date: 04/11/2024 |
Work in progress | 10% Completed
CC 1st and part bill submitted.
| Kannur PH Sn 3 AE |
| Date: 02/11/2024 |
Work in progress | 5% Completed
Pipe supplied
| Kannur PH Sn 3 AE |
| Date: 30/10/2024 |
Work in progress | 5% Completed
Pipe supplied
| Kannur PH Sn 3 AE |
| Date: 28/10/2024 |
Work in progress | 5% Completed
Pipe supplied
| Kannur PH Sn 3 AE |
| Date: 26/10/2024 |
Work in progress | 5% Completed
Pipe supplied
| Kannur PH Sn 3 AE |
| Date: 24/10/2024 |
Work in progress | 5% Completed
Pipe supplied
| Kannur PH Sn 3 AE |
| Date: 21/10/2024 |
Work in progress | 5% Completed
Pipe supplied
| Kannur PH Sn 3 AE |
| Date: 18/10/2024 |
Work in progress | 5% Completed
Pipe supplied
| Kannur PH Sn 3 AE |
| Date: 17/10/2024 |
Work in progress | 5% Completed
Pipe supplied