| Kattapana AE 1 |
| Date: 13/05/2022 |
Work has been completed | 100% Completed
Work Is Completed.
| Kattapana AE 1 |
| Date: 11/05/2022 |
Work in progress | 99% Completed
Charging Work In Progress
| Kattapana AE 1 |
| Date: 09/05/2022 |
Work in progress | 90% Completed
40m of 50mm GI Pipes laid.
| Kattapana AE 1 |
| Date: 07/05/2022 |
| Kattapana AE 1 |
| Date: 06/05/2022 |
Work in progress | 61% Completed
60m of 50mm GI Pipes laid.
| Kattapana AE 1 |
| Date: 05/05/2022 |
Work in progress | 43% Completed
54m of 50mm GI Pipes laid.
| Kattapana AE 1 |
| Date: 04/05/2022 |
| Kattapana AE 1 |
| Date: 03/05/2022 |
Work in progress | 15% Completed
Material Supply at Site