| Kannur WS Sn AE 2 |
| Date: 25/09/2026 |
Work in progress | 35% Completed
11 Km laying completed. 120 nos. FHTC Given. GSb 8831 m, Wmm 8831 m completed. 90 m Tarring completed.
| Kannur WS Sn AE 2 |
| Date: 14/08/2026 |
Work in progress | 34% Completed
Pipe laying started. 11 Km laying completed. 110 nos. FHTC Given. GSb 8831 m, Wmm 8831 m completed. 71m Tarring completed.
| Kannur WS Sn AE 2 |
| Date: 17/07/2026 |
Work in progress | 9% Completed
Pipe laying started. 11 Km laying completed. 67 nos. FHTC Given. GSb 8831 m completed. 71m Tarring completed.
| Kannur WS Sn AE 2 |
| Date: 07/07/2026 |
Work in progress | 9% Completed
Pipe laying started. 11 Km laying completed. 67 nos. FHTC Given
| Kannur WS Sn AE 2 |
| Date: 18/06/2026 |
Work in progress | 9% Completed
Pipe laying started. 11 Km laying completed. 67 nos. FHTC Given
| Kannur WS Sn AE 2 |
| Date: 04/06/2026 |
Work in progress | 9% Completed
Pipe laying started. 11 Km laying completed. 67 nos. FHTC Given
| Kannur WS Sn AE 2 |
| Date: 29/04/2026 |
Work in progress | 8% Completed
Pipe laying started. 7 Km laying completed. 35 nos. FHTC Given
| Kannur WS Sn AE 2 |
| Date: 17/04/2026 |
Work in progress | 8% Completed
Pipe laying started. 7 Km laying completed. 35 nos. FHTC Given
| Kannur WS Sn AE 2 |
| Date: 08/04/2026 |
Work in progress | 8% Completed
Pipe laying started. 7 Km laying completed. 35 nos. FHTC Given
| Kannur WS Sn AE 2 |
| Date: 24/03/2026 |
Work in progress | 8% Completed
Pipe laying started. 7 Km laying completed. 35 nos. FHTC Given
| Kannur WS Sn AE 2 |
| Date: 06/03/2026 |
Work in progress | 8% Completed
Pipe laying started. 7 Km laying completed. 35 nos. FHTC Given
| Kannur WS Sn AE 2 |
| Date: 25/02/2026 |
Work in progress | 8% Completed
Pipe laying started. 5 Km laying completed.
| Kannur WS Sn AE 2 |
| Date: 16/02/2026 |
Work in progress | 8% Completed
Pipre laying started. 5 Km laying completed.
| Kannur WS Sn AE 2 |
| Date: 11/02/2026 |
Work in progress | 1% Completed
Pipe laying started.
| Kannur WS Sn AE 2 |
| Date: 20/01/2026 |
Work in progress | 1% Completed
pipe laying started
| Kannur PH Dn EE |
| Date: 09/01/2026 |
Work in progress | 1% Completed
Pipe supplied
| Kannur WS Sn AE 2 |
| Date: 05/01/2026 |
Work in progress | 1% Completed
Pipe supplied
| Kannur WS Sn AE 2 |
| Date: 30/12/2025 |
Work in progress | 1% Completed
Pipe supplied.
| Kannur PH Dn EE |
| Date: 15/12/2025 |
Work has started | 0% Completed
Pipe supplied.
| Kannur PH Dn EE |
| Date: 01/12/2025 |
Work has started | 0% Completed
Pipe supplied.
| Kannur PH Dn EE |
| Date: 27/10/2025 |
Work in progress | 0% Completed
Agreement excecuted, Site Handed Overed on 21.07.2025
| Kannur PH Dn EE |
| Date: 07/03/2025 |
Work has started | 0% Completed
TS to be issued
| Kannur PH Dn EE |
| Date: 25/02/2025 |
Work has started | 0% Completed
TS to be issued
| Kannur PH Dn EE |
| Date: 19/02/2025 |
Work has started | 0% Completed
TS to be issued