Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kannur WS Sn AE 2
Date: 25/09/2026

Work in progress | 35% Completed

11 Km laying completed. 120 nos. FHTC Given. GSb 8831 m, Wmm 8831 m completed. 90 m Tarring completed.

Kannur WS Sn AE 2
Date: 14/08/2026

Work in progress | 34% Completed

Pipe laying started. 11 Km laying completed. 110 nos. FHTC Given. GSb 8831 m, Wmm 8831 m completed. 71m Tarring completed.

Kannur WS Sn AE 2
Date: 17/07/2026

Work in progress | 9% Completed

Pipe laying started. 11 Km laying completed. 67 nos. FHTC Given. GSb 8831 m completed. 71m Tarring completed.

Kannur WS Sn AE 2
Date: 07/07/2026

Work in progress | 9% Completed

Pipe laying started. 11 Km laying completed. 67 nos. FHTC Given

Kannur WS Sn AE 2
Date: 18/06/2026

Work in progress | 9% Completed

Pipe laying started. 11 Km laying completed. 67 nos. FHTC Given

Kannur WS Sn AE 2
Date: 04/06/2026

Work in progress | 9% Completed

Pipe laying started. 11 Km laying completed. 67 nos. FHTC Given

Kannur WS Sn AE 2
Date: 29/04/2026

Work in progress | 8% Completed

Pipe laying started. 7 Km laying completed. 35 nos. FHTC Given

Kannur WS Sn AE 2
Date: 17/04/2026

Work in progress | 8% Completed

Pipe laying started. 7 Km laying completed. 35 nos. FHTC Given

Kannur WS Sn AE 2
Date: 08/04/2026

Work in progress | 8% Completed

Pipe laying started. 7 Km laying completed. 35 nos. FHTC Given

Kannur WS Sn AE 2
Date: 24/03/2026

Work in progress | 8% Completed

Pipe laying started. 7 Km laying completed. 35 nos. FHTC Given

Kannur WS Sn AE 2
Date: 06/03/2026

Work in progress | 8% Completed

Pipe laying started. 7 Km laying completed. 35 nos. FHTC Given

Kannur WS Sn AE 2
Date: 25/02/2026

Work in progress | 8% Completed

Pipe laying started. 5 Km laying completed.

Kannur WS Sn AE 2
Date: 16/02/2026

Work in progress | 8% Completed

Pipre laying started. 5 Km laying completed.

Kannur WS Sn AE 2
Date: 11/02/2026

Work in progress | 1% Completed

Pipe laying started.

Kannur WS Sn AE 2
Date: 20/01/2026

Work in progress | 1% Completed

pipe laying started

Kannur PH Dn EE
Date: 09/01/2026

Work in progress | 1% Completed

Pipe supplied

Kannur WS Sn AE 2
Date: 05/01/2026

Work in progress | 1% Completed

Pipe supplied

Kannur WS Sn AE 2
Date: 30/12/2025

Work in progress | 1% Completed

Pipe supplied.

Kannur PH Dn EE
Date: 15/12/2025

Work has started | 0% Completed

Pipe supplied.

Kannur PH Dn EE
Date: 01/12/2025

Work has started | 0% Completed

Pipe supplied.

Kannur PH Dn EE
Date: 27/10/2025

Work in progress | 0% Completed

Agreement excecuted, Site Handed Overed on 21.07.2025

Kannur PH Dn EE
Date: 07/03/2025

Work has started | 0% Completed

TS to be issued

Kannur PH Dn EE
Date: 25/02/2025

Work has started | 0% Completed

TS to be issued

Kannur PH Dn EE
Date: 19/02/2025

Work has started | 0% Completed

TS to be issued