Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Cheruvathur AE
Date: 08/08/2022

Work has been completed | 100% Completed

Work has been completed 100FHTCs completed and final bill submitted

Cheruvathur AE
Date: 04/08/2022

Work has been completed | 100% Completed

Work has been completed 100FHTCs completed and final bill submitted

Cheruvathur AE
Date: 02/08/2022

Work has been completed | 100% Completed

Work has been completed 100FHTCs completed and final bill submitted

Cheruvathur AE
Date: 19/07/2022

Work has been completed | 100% Completed

Work has been completed 100FHTCs completed and final bill submitted

Cheruvathur AE
Date: 13/07/2022

Work has been completed | 100% Completed

Work has been completed 100FHTCs completed and final bill submitted

Cheruvathur AE
Date: 17/06/2022

Work has been completed | 100% Completed

Work has been completed 100FHTCs completed and final bill submitted

Cheruvathur AE
Date: 07/06/2022

Work has been completed | 100% Completed

Work has been completed 100FHTCs completed

Cheruvathur AE
Date: 31/05/2022

Work has been completed | 100% Completed

Work has been completed 100FHTCs completed

Cheruvathur AE
Date: 29/05/2022

Work has been completed | 100% Completed

completed

Cheruvathur AE
Date: 27/05/2022

Work in progress | 80% Completed

100 FHTC is physcically given, geo tagging is pending due to irregular water supply in connection with road widening work. 36 FHTC billed

Cheruvathur AE
Date: 22/05/2022

Work in progress | 80% Completed

100 FHTC is physcically given, geo tagging is pending due to irregular water supply in connection with road widening work. 36 FHTC billed

Cheruvathur AE
Date: 18/05/2022

Work in progress | 71% Completed

83 nos physically given out of 100 Fhtc

Cheruvathur AE
Date: 10/05/2022

Work in progress | 71% Completed

83 nos physically given out of 100 Fhtc

Cheruvathur AE
Date: 04/05/2022

Work in progress | 71% Completed

83 nos physically given out of 100 Fhtc

Cheruvathur AE
Date: 30/04/2022

Work in progress | 70% Completed

77 nos physically given out of 100 Fhtc

Cheruvathur AE
Date: 22/04/2022

Work in progress | 58% Completed

58%completed,36 nos Fhtc completed and 1st part bill submitted

Attached images

img img

Cheruvathur AE
Date: 20/04/2022

Work in progress | 58% Completed

58% completed.36 FHTC completed and Ist part bill submitted.

Cheruvathur AE
Date: 12/04/2022

Work in progress | 58% Completed

58% completed.36 FHTC completed and Ist part bill submitted.

Cheruvathur AE
Date: 04/04/2022

Work in progress | 58% Completed

58% completed.36 FHTC completed and Ist part bill submitted.

Cheruvathur AE
Date: 01/04/2022

Work in progress | 58% Completed

58% completed.36 FHTC completed and Ist part bill submitted.

Cheruvathur AE
Date: 28/03/2022

Work in progress | 57% Completed

57% completed. Ist part bill submitted.

Cheruvathur AE
Date: 22/03/2022

Work in progress | 55% Completed

PIPE SUPPLIED BY THE CONTRACTOR, LAYING OF 75MM PVC AND 90MM PVC ARE ONGOING.60m 75mm PVC laid for interconnection work and 1000m -90mm PVCand 160m -110mm pvc pipe for interconnection- pipe laid . 55% COMPLETED.road cutting application submitted to PWD row portal.

Cheruvathur AE
Date: 16/03/2022

Work in progress | 35% Completed

PIPE SUPPLIED BY THE CONTRACTOR, LAYING OF 75MM PVC AND 90MM PVC ARE ONGOING.60m 75mm PVC laid for interconnection work and 100m out of 1 km -90mm PVC pipe laid . 35% COMPLETED

Attached images

img img

Cheruvathur AE
Date: 14/03/2022

Work in progress | 35% Completed

PIPE SUPPLIED BY THE CONTRACTOR, LAYING OF 75MM PVC AND 90MM PVC ARE ONGOING. 35% COMPLETED.

Cheruvathur AE
Date: 13/03/2022

Work in progress | 30% Completed

pipe laying progressing on

Cheruvathur AE
Date: 11/03/2022

Work in progress | 10% Completed

Pipe supplied by the contractor

Cheruvathur AE
Date: 08/03/2022

Work has started | 0% Completed

PVC Pipe is not supplied due to work not started

Cheruvathur AE
Date: 04/03/2022

Work has started | 0% Completed

PVC Pipe is not supplied due to work not started

Cheruvathur AE
Date: 28/02/2022

Work has started | 0% Completed

PVC Pipe is not supplied due to work not started

Cheruvathur AE
Date: 21/02/2022

Work has started | 0% Completed

PVC Pipe is not supplied due to work not started

Cheruvathur AE
Date: 15/02/2022

Work has started | 0% Completed

PVC Pipe is not supplied due to work not started

Cheruvathur AE
Date: 14/02/2022

Work has started | 0% Completed

PVC Pipe is not supplied due to work not started

Cheruvathur AE
Date: 10/02/2022

Work has started | 0% Completed

PVC Pipe is not supplied due to work not started

Cheruvathur AE
Date: 03/02/2022

Work has started | 0% Completed

PVC Pipe is not supplied due to work not started

Cheruvathur AE
Date: 01/02/2022

Work has started | 0% Completed

Pipe is not supplied due to work not started