| Thalassery PH Sn AE |
| Date: 28/09/2026 |
Work has been completed | 100% Completed
Final bill submitted
| Thalassery PH Sn AE |
| Date: 08/07/2026 |
Work has been completed | 100% Completed
Work completed & final bill under preparation
| Thalassery PH Sn AE |
| Date: 17/06/2026 |
Work in progress | 80% Completed
91no. public tap disconnected
| Thalassery PH Sn AE |
| Date: 04/06/2026 |
Work in progress | 80% Completed
91no. public tap disconnected
| Thalassery PH Sn AE |
| Date: 29/04/2026 |
Work in progress | 80% Completed
91no. public tap disconnected
| Thalassery PH Sn AE |
| Date: 18/04/2026 |
Work in progress | 80% Completed
91no. public tap disconnected
| Thalassery PH Sn AE |
| Date: 10/04/2026 |
Work in progress | 80% Completed
91no. public tap disconnected
| Thalassery PH Sn AE |
| Date: 30/03/2026 |
Work in progress | 80% Completed
91no. public tap disconnected
| Thalassery PH Sn AE |
| Date: 23/03/2026 |
Work in progress | 80% Completed
91no. public tap disconnected
| Thalassery PH Sn AE |
| Date: 11/03/2026 |
Work in progress | 80% Completed
91no. public tap disconnected
| Thalassery PH Sn AE |
| Date: 03/03/2026 |
Work in progress | 35% Completed
40nos. public tap disconnected
| Kannur PH Dn EE |
| Date: 23/02/2026 |
Work in progress | 2% Completed
Work started