Perlassery Sn 2 AE |
Date: 25/06/2024 |
Work in progress | 95% Completed
Work in progress | 95% Completed
Perlassery Sn 2 AE |
Date: 20/06/2024 |
Work in progress | 95% Completed
Work in progress | 95% Completed
Perlassery Sn 2 AE |
Date: 10/06/2024 |
Work in progress | 95% Completed
Work in progress | 95% Completed
Perlassery Sn 2 AE |
Date: 01/06/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61nos. FHTC provided
Perlassery Sn 2 AE |
Date: 22/05/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61nos. FHTC provided
Perlassery Sn 2 AE |
Date: 17/05/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61nos. FHTC provided.Part bill submitted
Perlassery Sn 2 AE |
Date: 10/05/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61nos. FHTC provided
Perlassery Sn 2 AE |
Date: 25/04/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61nos. FHTC provided
Perlassery Sn 2 AE |
Date: 18/04/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.44nos. FHTC provided
Perlassery Sn 2 AE |
Date: 06/04/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.44nos. FHTC provided
Perlassery Sn 2 AE |
Date: 27/03/2024 |
Work in progress | 15% Completed
work in progress
Perlassery Sn 2 AE |
Date: 18/03/2024 |
Work in progress | 5% Completed
work in progress
Perlassery Sn 2 AE |
Date: 11/03/2024 |
Work in progress | 3% Completed
work in progress
Perlassery Sn 2 AE |
Date: 28/02/2024 |
Work has started | 0% Completed
AGREEMENT EXECUTED ON 19.01.2024,Pipe have been supplied
Perlassery Sn 2 AE |
Date: 14/02/2024 |
Work has started | 0% Completed
AGREEMENT EXECUTED ON 19.01.2024
Perlassery Sn 2 AE |
Date: 06/02/2024 |
Work has started | 0% Completed
AGREEMENT EXECUTED ON 19.01.2024
Perlassery Sn 2 AE |
Date: 29/01/2024 |
Work has started | 0% Completed
AGREEMENT EXECUTED ON 19.01.2024
Kannur PH Dn EE |
Date: 19/01/2024 |
Work has started | 0% Completed
AGREEMENT EXECUTED ON 19.01.2024
Kannur PH Dn EE |
Date: 08/01/2024 |
Work has started | 0% Completed
WORK ORDER ISSUED ON 08.01.2024
Kannur PH Dn EE |
Date: 21/12/2023 |
Work has started | 0% Completed
WORK TENDERED
Kannur PH Dn EE |
Date: 20/12/2023 |
Work has started | 0% Completed
TS ISSUED