Perlassery Sn 2 AE
Date: 25/06/2024

Work in progress | 95% Completed

Work in progress | 95% Completed

Perlassery Sn 2 AE
Date: 20/06/2024

Work in progress | 95% Completed

Work in progress | 95% Completed

Perlassery Sn 2 AE
Date: 10/06/2024

Work in progress | 95% Completed

Work in progress | 95% Completed

Perlassery Sn 2 AE
Date: 01/06/2024

Work in progress | 95% Completed

95% work completed.5165m pipe laid.61nos. FHTC provided

Perlassery Sn 2 AE
Date: 22/05/2024

Work in progress | 95% Completed

95% work completed.5165m pipe laid.61nos. FHTC provided

Perlassery Sn 2 AE
Date: 17/05/2024

Work in progress | 95% Completed

95% work completed.5165m pipe laid.61nos. FHTC provided.Part bill submitted

Perlassery Sn 2 AE
Date: 10/05/2024

Work in progress | 95% Completed

95% work completed.5165m pipe laid.61nos. FHTC provided

Perlassery Sn 2 AE
Date: 25/04/2024

Work in progress | 95% Completed

95% work completed.5165m pipe laid.61nos. FHTC provided

Perlassery Sn 2 AE
Date: 18/04/2024

Work in progress | 95% Completed

95% work completed.5165m pipe laid.44nos. FHTC provided

Perlassery Sn 2 AE
Date: 06/04/2024

Work in progress | 95% Completed

95% work completed.5165m pipe laid.44nos. FHTC provided

Perlassery Sn 2 AE
Date: 27/03/2024

Work in progress | 15% Completed

work in progress

Perlassery Sn 2 AE
Date: 18/03/2024

Work in progress | 5% Completed

work in progress

Perlassery Sn 2 AE
Date: 11/03/2024

Work in progress | 3% Completed

work in progress

Perlassery Sn 2 AE
Date: 28/02/2024

Work has started | 0% Completed

AGREEMENT EXECUTED ON 19.01.2024,Pipe have been supplied

Perlassery Sn 2 AE
Date: 14/02/2024

Work has started | 0% Completed

AGREEMENT EXECUTED ON 19.01.2024

Perlassery Sn 2 AE
Date: 06/02/2024

Work has started | 0% Completed

AGREEMENT EXECUTED ON 19.01.2024

Perlassery Sn 2 AE
Date: 29/01/2024

Work has started | 0% Completed

AGREEMENT EXECUTED ON 19.01.2024

Kannur PH Dn EE
Date: 19/01/2024

Work has started | 0% Completed

AGREEMENT EXECUTED ON 19.01.2024

Kannur PH Dn EE
Date: 08/01/2024

Work has started | 0% Completed

WORK ORDER ISSUED ON 08.01.2024

Kannur PH Dn EE
Date: 21/12/2023

Work has started | 0% Completed

WORK TENDERED

Kannur PH Dn EE
Date: 20/12/2023

Work has started | 0% Completed

TS ISSUED