Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Thaliparamba WS Section
Date: 28/09/2026

Work in progress | 26% Completed

4 Km pipe line laid and 4 valve fixed. Existing connection charged for 4km

Thaliparamba WS Section
Date: 02/07/2026

Work in progress | 26% Completed

4 Km pipe line laid and 4 valve fixed. Existing connection charged for 4km

Thaliparamba WS Section
Date: 25/06/2026

Work in progress | 26% Completed

4 Km pipe line laid and 4 valve fixed. Existing connection charged for 4km

Thaliparamba WS Section
Date: 09/06/2026

Work in progress | 26% Completed

4 Km pipe line laid and 4 valve fixed. Existing connection charged for 4km

Thaliparamba WS Section
Date: 12/05/2026

Work in progress | 26% Completed

4 Km pipe line laid and 4 valve fixed. Existing connection charged for 4km

Thaliparamba WS Section
Date: 24/04/2026

Work in progress | 26% Completed

4 Km pipe line laid and 4 valve fixed. Existing connection charged for 4km

Thaliparamba WS Section
Date: 07/04/2026

Work in progress | 26% Completed

4 Km pipe line laid and 4 valve fixed. Existing connection charged for 4km

Thaliparamba WS Section
Date: 27/03/2026

Work in progress | 26% Completed

4 Km pipe line laid and 4 valve fixed. Existing connection charged for 4km

Thaliparamba WS Section
Date: 13/03/2026

Work in progress | 20% Completed

3 Km pipe line laid and 4 valve fixed. Existing connection charged for 3km

Thaliparamba WS Section
Date: 04/03/2026

Work in progress | 12% Completed

3 Km pipe line laid and 4 valve fixed. Existing connection charged for 3km

Thaliparamba WS Section
Date: 21/02/2026

Work in progress | 12% Completed

3 Km pipe line laid and 4 valve fixed. Existing connection charged for 3km

Thaliparamba WS Section
Date: 16/02/2026

Work in progress | 10% Completed

3 Km pipe line laid and 4 valve fixed. Existing connection charged for 3km

Thaliparamba WS Section
Date: 06/02/2026

Work in progress | 10% Completed

3 Km pipe line laid and 4 valve fixed. Existing connection charged for 3km

Thaliparamba WS Section
Date: 28/01/2026

Work in progress | 10% Completed

3 Km pipe line laid and 4 valve fixed. Existing connection charged for 3km

Thaliparamba WS Section
Date: 23/01/2026

Work in progress | 10% Completed

3 Km pipe line laid and 4 valve fixed.

Thaliparamba WS Section
Date: 17/01/2026

Work in progress | 10% Completed

3 Km pipe line laid and 4 valve fixed.

Thaliparamba WS Dn EE
Date: 12/01/2026

Work in progress | 5% Completed

3 Km pipe line laid.