| Thaliparamba WS Section |
| Date: 28/09/2026 |
Work in progress | 26% Completed
4 Km pipe line laid and 4 valve fixed. Existing connection charged for 4km
| Thaliparamba WS Section |
| Date: 02/07/2026 |
Work in progress | 26% Completed
4 Km pipe line laid and 4 valve fixed. Existing connection charged for 4km
| Thaliparamba WS Section |
| Date: 25/06/2026 |
Work in progress | 26% Completed
4 Km pipe line laid and 4 valve fixed. Existing connection charged for 4km
| Thaliparamba WS Section |
| Date: 09/06/2026 |
Work in progress | 26% Completed
4 Km pipe line laid and 4 valve fixed. Existing connection charged for 4km
| Thaliparamba WS Section |
| Date: 12/05/2026 |
Work in progress | 26% Completed
4 Km pipe line laid and 4 valve fixed. Existing connection charged for 4km
| Thaliparamba WS Section |
| Date: 24/04/2026 |
Work in progress | 26% Completed
4 Km pipe line laid and 4 valve fixed. Existing connection charged for 4km
| Thaliparamba WS Section |
| Date: 07/04/2026 |
Work in progress | 26% Completed
4 Km pipe line laid and 4 valve fixed. Existing connection charged for 4km
| Thaliparamba WS Section |
| Date: 27/03/2026 |
Work in progress | 26% Completed
4 Km pipe line laid and 4 valve fixed. Existing connection charged for 4km
| Thaliparamba WS Section |
| Date: 13/03/2026 |
Work in progress | 20% Completed
3 Km pipe line laid and 4 valve fixed. Existing connection charged for 3km
| Thaliparamba WS Section |
| Date: 04/03/2026 |
Work in progress | 12% Completed
3 Km pipe line laid and 4 valve fixed. Existing connection charged for 3km
| Thaliparamba WS Section |
| Date: 21/02/2026 |
Work in progress | 12% Completed
3 Km pipe line laid and 4 valve fixed. Existing connection charged for 3km
| Thaliparamba WS Section |
| Date: 16/02/2026 |
Work in progress | 10% Completed
3 Km pipe line laid and 4 valve fixed. Existing connection charged for 3km
| Thaliparamba WS Section |
| Date: 06/02/2026 |
Work in progress | 10% Completed
3 Km pipe line laid and 4 valve fixed. Existing connection charged for 3km
| Thaliparamba WS Section |
| Date: 28/01/2026 |
Work in progress | 10% Completed
3 Km pipe line laid and 4 valve fixed. Existing connection charged for 3km
| Thaliparamba WS Section |
| Date: 23/01/2026 |
Work in progress | 10% Completed
3 Km pipe line laid and 4 valve fixed.
| Thaliparamba WS Section |
| Date: 17/01/2026 |
Work in progress | 10% Completed
3 Km pipe line laid and 4 valve fixed.
| Thaliparamba WS Dn EE |
| Date: 12/01/2026 |
Work in progress | 5% Completed
3 Km pipe line laid.