| Kozhikode PH Dn EE |
| Date: 30/06/2024 |
Work has been completed | 100% Completed
Completed
| Kozhikode PH Dn EE |
| Date: 24/06/2024 |
Work in progress | 99% Completed
Almost completed. FHTCs-432 nos.
| Kozhikode PH Dn EE |
| Date: 14/06/2024 |
Work in progress | 98% Completed
Almost Completed. Pipe laid-90mm PVC-2.70km, 63mm pvc-0.60km, FHTCs-404 nos.
| Kozhikode PH Dn EE |
| Date: 21/04/2024 |
Work in progress | 92% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 89% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 85% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 05/03/2024 |
Work in progress | 82% Completed
Pipe laid-2.70km, FHTCs-215 nos.
| Kozhikode PH Dn EE |
| Date: 04/03/2024 |
Work in progress | 81% Completed
Pipe laid-2.70km, FHTCs-215 nos.
| Kozhikode PH Dn EE |
| Date: 03/03/2024 |
Work in progress | 81% Completed
Pipe laid-2.70km, FHTCs-215 nos.
| Kozhikode PH Dn EE |
| Date: 02/03/2024 |
Work in progress | 81% Completed
Pipe laid-2.70km, FHTCs-215 nos.
| Kozhikode PH Dn EE |
| Date: 01/03/2024 |
Work in progress | 81% Completed
Pipe laid-2.70km, FHTCs-215 nos.
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 80% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 30/01/2024 |
Work in progress | 76% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 29/01/2024 |
Work in progress | 76% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 75% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 08/01/2024 |
Work in progress | 70% Completed
Pipe laid-2673m. FHTC-100
| Kozhikode PH Dn EE |
| Date: 07/01/2024 |
Work in progress | 70% Completed
Pipe laid-2673m. FHTC-100
| Kozhikode PH Dn EE |
| Date: 06/01/2024 |
Work in progress | 69% Completed
Pipe laid-2673m. FHTC-100
| Kozhikode PH Dn EE |
| Date: 05/01/2024 |
Work in progress | 69% Completed
Pipe laid-2673m. FHTC-100
| Kozhikode PH Dn EE |
| Date: 04/01/2024 |
Work in progress | 68% Completed
Pipe laid-2673m. FHTC-100
| Kozhikode PH Dn EE |
| Date: 03/01/2024 |
Work in progress | 68% Completed
Pipe laid-2673m. FHTC-100
| Kozhikode PH Dn EE |
| Date: 02/01/2024 |
Work in progress | 68% Completed
Pipe laid-2673m. FHTC-100
| Kozhikode PH Dn EE |
| Date: 01/01/2024 |
Work in progress | 68% Completed
Pipe laid-2673m. FHTC-100
| Kozhikode PH Dn EE |
| Date: 12/12/2023 |
Work in progress | 65% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 29/11/2023 |
Work in progress | 63% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 20/11/2023 |
Work in progress | 61% Completed
Work in progress-Pipe laid-2350 m, HTC-34 nos.
| Kozhikode PH Dn EE |
| Date: 19/11/2023 |
Work in progress | 60% Completed
Work in progress-Pipe laid-2350 m, HTC-34 nos.
| Kozhikode PH Dn EE |
| Date: 18/11/2023 |
Work in progress | 60% Completed
Work in progress-Pipe laid-2350 m, HTC-34 nos.
| Kozhikode PH Dn EE |
| Date: 17/11/2023 |
Work in progress | 60% Completed
Work in progress-Pipe laid-2350 m, HTC-34 nos.
| Kozhikode PH Dn EE |
| Date: 16/11/2023 |
Work in progress | 60% Completed
Work in progress-Pipe laid-2350 m, HTC-34 nos.
| Kozhikode PH Dn EE |
| Date: 15/11/2023 |
Work in progress | 52% Completed
Work in progress-Pipe laid-2050 m, HTC-34 nos.
| Kozhikode PH Dn EE |
| Date: 02/11/2023 |
Work in progress | 43% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 31/10/2023 |
Work in progress | 14% Completed
wORK IN PROGRESS
| Kozhikode PH Dn EE |
| Date: 30/10/2023 |
Work in progress | 10% Completed
Pipelaying Started