| Devikulam AE |
| Date: 17/08/2023 |
Work has been completed | 100% Completed
Completed
| Devikulam AE |
| Date: 16/08/2023 |
Work in progress | 95% Completed
Automation work balance
| Devikulam AE |
| Date: 09/08/2023 |
Work in progress | 95% Completed
Automation work balance
| Devikulam AE |
| Date: 05/08/2023 |
Work in progress | 90% Completed
Pump erected, civil work under progress
| Devikulam AE |
| Date: 02/08/2023 |
Work in progress | 90% Completed
Pump erected, civil work started
| Devikulam AE |
| Date: 27/07/2023 |
Work in progress | 90% Completed
Pump erected, civil work balance
| Devikulam AE |
| Date: 19/07/2023 |
Work in progress | 90% Completed
Pump erected, civil work balance
| Devikulam AE |
| Date: 12/07/2023 |
Work in progress | 90% Completed
Pump erected, civil work balance
| Devikulam AE |
| Date: 05/07/2023 |
Work in progress | 90% Completed
Pump erected, civil work balance
| Devikulam AE |
| Date: 29/06/2023 |
Work in progress | 90% Completed
Pump erected, civil work balance
| Devikulam AE |
| Date: 26/06/2023 |
Work in progress | 90% Completed
Pump erected, civil work balance
| Devikulam AE |
| Date: 21/06/2023 |
Work in progress | 90% Completed
Pump erected, civil work balance
| Devikulam AE |
| Date: 15/06/2023 |
Work in progress | 90% Completed
Pump erected, civil work balance
| Devikulam AE |
| Date: 13/06/2023 |
Work in progress | 80% Completed
Pump erected starter connection and remaining work balance
| Devikulam AE |
| Date: 08/06/2023 |
Work in progress | 80% Completed
Pump erected starter connection and remaining work balance
| Devikulam AE |
| Date: 02/06/2023 |
Work in progress | 50% Completed
Pump erection work under progress
| Devikulam AE |
| Date: 30/05/2023 |
Work in progress | 30% Completed
Pump erection work under progress
| Devikulam AE |
| Date: 24/05/2023 |
Work in progress | 25% Completed
Pump erection work under progress
| Devikulam AE |
| Date: 18/05/2023 |
Work in progress | 25% Completed
Pump erection work under progress
| Devikulam AE |
| Date: 16/05/2023 |
Work in progress | 25% Completed
pump erection work started
| Devikulam AE |
| Date: 11/05/2023 |
Work in progress | 20% Completed
Pump supplied. Pump Erection to be completed
| Devikulam AE |
| Date: 09/05/2023 |
Work in progress | 20% Completed
Pump supplied ,erection balance
| Devikulam AE |
| Date: 05/05/2023 |
Work in progress | 20% Completed
Pump supplied ,erection balance
| Devikulam AE |
| Date: 27/04/2023 |
Work in progress | 20% Completed
Pump supplied ,erection will be done on next Tuesday
| Devikulam AE |
| Date: 19/04/2023 |
Work in progress | 10% Completed
Hand rail work started and contractor informed that pump has been delivered from company and it will be erected soon
| Devikulam AE |
| Date: 12/04/2023 |
Work in progress | 10% Completed
Hand rail work started and contractor informed that pump has been delivered from company and it will be erected next week.
| Devikulam AE |
| Date: 09/04/2023 |
Work in progress | 10% Completed
Hand rail work started and contractor informed that order placed for pump and it will be erected soon
| Devikulam AE |
| Date: 30/03/2023 |
Work in progress | 10% Completed
Hand rail work started and contractor informed that order placed for pump and it will be erected soon
| Devikulam AE |
| Date: 23/03/2023 |
Work in progress | 10% Completed
Hand rail work started and contractor informed that order placed for pump and it will be erected soon
| Devikulam AE |
| Date: 17/03/2023 |
Work in progress | 10% Completed
Hand rail work started and contractor informed that order placed for pump and it will be erected soon
| Devikulam AE |
| Date: 09/03/2023 |
Work in progress | 10% Completed
Hand rail work started and contractor informed that order placed for pump and it will be erected soon
| Devikulam AE |
| Date: 02/03/2023 |
Work in progress | 10% Completed
Hand rail work started
| Devikulam AE |
| Date: 15/02/2023 |
Work in progress | 10% Completed
Handrail work started
| Devikulam AE |
| Date: 24/01/2023 |
Work has started | 0% Completed
Directed the contractor to start the work immediately .Contractor informed that the order for the pump were placed and handrail work will be started with in one week
| Devikulam AE |
| Date: 10/01/2023 |
Work in progress | 0% Completed
Contractor visited the site and informed that the fixing of handrail will be started within one week
| Devikulam AE |
| Date: 28/12/2022 |
Work has started | 0% Completed
Work not Started yet. Directed the Contractor to start the work as soon as possible
| Devikulam AE |
| Date: 13/12/2022 |
Work has started | 0% Completed
Work not Started yet. Directed the Contractor to start the work as soon as possible
| Devikulam AE |
| Date: 07/12/2022 |
Work has started | 0% Completed
Contractor informed that he will start the work immediately
| Devikulam AE |
| Date: 03/12/2022 |
Work has started | 0% Completed
Contractor informed that he will start the work immediately
| Devikulam AE |
| Date: 24/11/2022 |
Work has started | 0% Completed
Agreement Executed
| Devikulam AE |
| Date: 16/11/2022 |
Work has started | 0% Completed
One Contractor quoted the work. Work order issued. But Agreement not executed yet
| Painavu PH Sub Dn AEE |
| Date: 11/11/2022 |
Work has started | 0% Completed
Work order issued
| Painavu PH Sub Dn AEE |
| Date: 06/11/2022 |
Work has started | 0% Completed
Work order issued
| Painavu PH Sub Dn AEE |
| Date: 21/10/2022 |
Work has started | 0% Completed
Work order issued
| Painavu PH Sub Dn AEE |
| Date: 15/10/2022 |
Work has started | 0% Completed
Work order issued
| Devikulam AE |
| Date: 01/10/2022 |
Work has started | 0% Completed
One Contractor quoted the work. Agreement not executed yet
| Devikulam AE |
| Date: 22/09/2022 |
Work has started | 0% Completed
One Contractor has quoted the work. Agreement not executed yet
| Painavu PH Sub Dn AEE |
| Date: 20/09/2022 |
Work has started | 0% Completed
One Contractor quoted the work. Agreement not executed yet
| Devikulam AE |
| Date: 13/09/2022 |
Work has started | 0% Completed
One Contractor quoted the work. Agreement not executed yet
| Devikulam AE |
| Date: 01/09/2022 |
Work has started | 0% Completed
two bids received ,work order to issued
| Painavu PH Sub Dn AEE |
| Date: 28/08/2022 |
Work has started | 0% Completed
two bids received ,work order to be issued
| Thodupuzha PH Dn EE |
| Date: 24/08/2022 |
Work has started | 0% Completed
two bids received ,work order to issued
| Devikulam AE |
| Date: 16/08/2022 |
Work has started | 0% Completed
Work Tendered. Non participation
| Painavu PH Sub Dn AEE |
| Date: 13/08/2022 |
Work has started | 0% Completed
tendered
| Thodupuzha PH Dn EE |
| Date: 05/08/2022 |
Work has started | 0% Completed
Work tendered
| Painavu PH Sub Dn AEE |
| Date: 04/08/2022 |
Work has started | 0% Completed
Tendered
| Painavu PH Sub Dn AEE |
| Date: 01/08/2022 |
Work has started | 0% Completed
Tendered
| Devikulam AE |
| Date: 26/07/2022 |
Work has started | 0% Completed
The estimate is under scrutiny at Divisional Office
| Devikulam AE |
| Date: 20/07/2022 |
Work has started | 0% Completed
The estimate is under scrutiny at Divisional Office
| Devikulam AE |
| Date: 13/07/2022 |
Work has started | 0% Completed
The estimate is under scrutiny at Divisional Office
| Thodupuzha PH Dn EE |
| Date: 08/07/2022 |
Work has started | 0% Completed
The estimate is under scrutiny