Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Devikulam AE
Date: 17/08/2023

Work has been completed | 100% Completed

Completed

Devikulam AE
Date: 16/08/2023

Work in progress | 95% Completed

Automation work balance

Devikulam AE
Date: 09/08/2023

Work in progress | 95% Completed

Automation work balance

Devikulam AE
Date: 05/08/2023

Work in progress | 90% Completed

Pump erected, civil work under progress

Devikulam AE
Date: 02/08/2023

Work in progress | 90% Completed

Pump erected, civil work started

Devikulam AE
Date: 27/07/2023

Work in progress | 90% Completed

Pump erected, civil work balance

Devikulam AE
Date: 19/07/2023

Work in progress | 90% Completed

Pump erected, civil work balance

Devikulam AE
Date: 12/07/2023

Work in progress | 90% Completed

Pump erected, civil work balance

Devikulam AE
Date: 05/07/2023

Work in progress | 90% Completed

Pump erected, civil work balance

Devikulam AE
Date: 29/06/2023

Work in progress | 90% Completed

Pump erected, civil work balance

Devikulam AE
Date: 26/06/2023

Work in progress | 90% Completed

Pump erected, civil work balance

Devikulam AE
Date: 21/06/2023

Work in progress | 90% Completed

Pump erected, civil work balance

Devikulam AE
Date: 15/06/2023

Work in progress | 90% Completed

Pump erected, civil work balance

Devikulam AE
Date: 13/06/2023

Work in progress | 80% Completed

Pump erected starter connection and remaining work balance

Devikulam AE
Date: 08/06/2023

Work in progress | 80% Completed

Pump erected starter connection and remaining work balance

Devikulam AE
Date: 02/06/2023

Work in progress | 50% Completed

Pump erection work under progress

Devikulam AE
Date: 30/05/2023

Work in progress | 30% Completed

Pump erection work under progress

Devikulam AE
Date: 24/05/2023

Work in progress | 25% Completed

Pump erection work under progress

Devikulam AE
Date: 18/05/2023

Work in progress | 25% Completed

Pump erection work under progress

Devikulam AE
Date: 16/05/2023

Work in progress | 25% Completed

pump erection work started

Devikulam AE
Date: 11/05/2023

Work in progress | 20% Completed

Pump supplied. Pump Erection to be completed

Devikulam AE
Date: 09/05/2023

Work in progress | 20% Completed

Pump supplied ,erection balance

Devikulam AE
Date: 05/05/2023

Work in progress | 20% Completed

Pump supplied ,erection balance

Devikulam AE
Date: 27/04/2023

Work in progress | 20% Completed

Pump supplied ,erection will be done on next Tuesday

Devikulam AE
Date: 19/04/2023

Work in progress | 10% Completed

Hand rail work started and contractor informed that pump has been delivered from company and it will be erected soon

Devikulam AE
Date: 12/04/2023

Work in progress | 10% Completed

Hand rail work started and contractor informed that pump has been delivered from company and it will be erected next week.

Devikulam AE
Date: 09/04/2023

Work in progress | 10% Completed

Hand rail work started and contractor informed that order placed for pump and it will be erected soon

Devikulam AE
Date: 30/03/2023

Work in progress | 10% Completed

Hand rail work started and contractor informed that order placed for pump and it will be erected soon

Devikulam AE
Date: 23/03/2023

Work in progress | 10% Completed

Hand rail work started and contractor informed that order placed for pump and it will be erected soon

Devikulam AE
Date: 17/03/2023

Work in progress | 10% Completed

Hand rail work started and contractor informed that order placed for pump and it will be erected soon

Devikulam AE
Date: 09/03/2023

Work in progress | 10% Completed

Hand rail work started and contractor informed that order placed for pump and it will be erected soon

Devikulam AE
Date: 02/03/2023

Work in progress | 10% Completed

Hand rail work started

Devikulam AE
Date: 15/02/2023

Work in progress | 10% Completed

Handrail work started

Devikulam AE
Date: 24/01/2023

Work has started | 0% Completed

Directed the contractor to start the work immediately .Contractor informed that the order for the pump were placed and handrail work will be started with in one week

Devikulam AE
Date: 10/01/2023

Work in progress | 0% Completed

Contractor visited the site and informed that the fixing of handrail will be started within one week

Devikulam AE
Date: 28/12/2022

Work has started | 0% Completed

Work not Started yet. Directed the Contractor to start the work as soon as possible

Devikulam AE
Date: 13/12/2022

Work has started | 0% Completed

Work not Started yet. Directed the Contractor to start the work as soon as possible

Devikulam AE
Date: 07/12/2022

Work has started | 0% Completed

Contractor informed that he will start the work immediately

Devikulam AE
Date: 03/12/2022

Work has started | 0% Completed

Contractor informed that he will start the work immediately

Devikulam AE
Date: 24/11/2022

Work has started | 0% Completed

Agreement Executed

Devikulam AE
Date: 16/11/2022

Work has started | 0% Completed

One Contractor quoted the work. Work order issued. But Agreement not executed yet

Painavu PH Sub Dn AEE
Date: 11/11/2022

Work has started | 0% Completed

Work order issued

Painavu PH Sub Dn AEE
Date: 06/11/2022

Work has started | 0% Completed

Work order issued

Painavu PH Sub Dn AEE
Date: 21/10/2022

Work has started | 0% Completed

Work order issued

Painavu PH Sub Dn AEE
Date: 15/10/2022

Work has started | 0% Completed

Work order issued

Devikulam AE
Date: 01/10/2022

Work has started | 0% Completed

One Contractor quoted the work. Agreement not executed yet

Devikulam AE
Date: 22/09/2022

Work has started | 0% Completed

One Contractor has quoted the work. Agreement not executed yet

Painavu PH Sub Dn AEE
Date: 20/09/2022

Work has started | 0% Completed

One Contractor quoted the work. Agreement not executed yet

Devikulam AE
Date: 13/09/2022

Work has started | 0% Completed

One Contractor quoted the work. Agreement not executed yet

Devikulam AE
Date: 01/09/2022

Work has started | 0% Completed

two bids received ,work order to issued

Painavu PH Sub Dn AEE
Date: 28/08/2022

Work has started | 0% Completed

two bids received ,work order to be issued

Thodupuzha PH Dn EE
Date: 24/08/2022

Work has started | 0% Completed

two bids received ,work order to issued

Devikulam AE
Date: 16/08/2022

Work has started | 0% Completed

Work Tendered. Non participation

Painavu PH Sub Dn AEE
Date: 13/08/2022

Work has started | 0% Completed

tendered

Thodupuzha PH Dn EE
Date: 05/08/2022

Work has started | 0% Completed

Work tendered

Painavu PH Sub Dn AEE
Date: 04/08/2022

Work has started | 0% Completed

Tendered

Painavu PH Sub Dn AEE
Date: 01/08/2022

Work has started | 0% Completed

Tendered

Devikulam AE
Date: 26/07/2022

Work has started | 0% Completed

The estimate is under scrutiny at Divisional Office

Devikulam AE
Date: 20/07/2022

Work has started | 0% Completed

The estimate is under scrutiny at Divisional Office

Devikulam AE
Date: 13/07/2022

Work has started | 0% Completed

The estimate is under scrutiny at Divisional Office

Thodupuzha PH Dn EE
Date: 08/07/2022

Work has started | 0% Completed

The estimate is under scrutiny