Pullad PH Sn - AE
Date: 26/06/2024

Work in progress | 45% Completed

30000M PVC Pipes Laid. 320 FHTCs Provided

Pullad PH Sn - AE
Date: 21/06/2024

Work in progress | 45% Completed

30000M PVC Pipes Laid. 320 FHTCs Provided

Pullad PH Sn - AE
Date: 18/06/2024

Work in progress | 45% Completed

30000M PVC Pipes Laid. 320 FHTCs Provided, 301 geotagged

Pullad PH Sn - AE
Date: 13/06/2024

Work in progress | 45% Completed

30000M PVC Pipes Laid. 320 FHTCs Provided, 301 geotagged

Pullad PH Sn - AE
Date: 11/06/2024

Work in progress | 45% Completed

30000M PVC Pipes Laid. 320 FHTCs Provided, 301 geotagged

Pullad PH Sn - AE
Date: 07/06/2024

Work in progress | 45% Completed

30000M PVC Pipes Laid. 320 FHTCs Provided, 301 geotagged

Pullad PH Sn - AE
Date: 30/05/2024

Work in progress | 43% Completed

30000M PVC Pipes Laid. 250 FHTCs Provided, 193 geotagged

Pullad PH Sn - AE
Date: 25/05/2024

Work in progress | 43% Completed

30000M PVC Pipes Laid. 250 FHTCs Provided, 193 geotagged

Pullad PH Sn - AE
Date: 21/05/2024

Work in progress | 43% Completed

30000M PVC Pipes Laid. 250 FHTCs Provided, 193 geotagged

Pullad PH Sn - AE
Date: 17/05/2024

Work in progress | 40% Completed

30000M PVC Pipes Laid. 155 FHTCs Provided, 93 geotagged

Pullad PH Sn - AE
Date: 13/05/2024

Work in progress | 40% Completed

30000M PVC Pipes Laid. 155 FHTCs Provided, 93 geotagged

Pullad PH Sn - AE
Date: 06/05/2024

Work in progress | 37% Completed

30000M PVC Pipes Laid. 140 FHTCs Provided, 86 geotagged

Pullad PH Sn - AE
Date: 02/05/2024

Work in progress | 37% Completed

30000M PVC Pipes Laid. 140 FHTCs Provided, 86 geotagged

Pullad PH Sn - AE
Date: 27/04/2024

Work in progress | 37% Completed

30000M PVC Pipes Laid. 140 FHTCs Provided, 86 geotagged

Pullad PH Sn - AE
Date: 23/04/2024

Work in progress | 35% Completed

26000M PVC Pipes Laid 50 FHTCs Provided

Pullad PH Sn - AE
Date: 19/04/2024

Work in progress | 35% Completed

26000M PVC Pipes Laid 50 FHTCs Provided

Pullad PH Sn - AE
Date: 16/04/2024

Work in progress | 32% Completed

25654M PVC Pipes Laid 36 FHTCs Provided

Pullad PH Sn - AE
Date: 11/04/2024

Work in progress | 32% Completed

25654M PVC Pipes Laid 36 FHTCs Provided

Pullad PH Sn - AE
Date: 06/04/2024

Work in progress | 32% Completed

25654M PVC Pipes Laid 36 FHTCs Provided

Pullad PH Sn - AE
Date: 01/04/2024

Work in progress | 32% Completed

25654M PVC Pipes Laid 36 FHTCs Provided

Pullad PH Sn - AE
Date: 27/03/2024

Work in progress | 32% Completed

25654M PVC Pipes Laid 36 FHTCs Provided

Pullad PH Sn - AE
Date: 23/03/2024

Work in progress | 30% Completed

25000M PVC Pipes Laid 36 FHTCs Provided

Pullad PH Sn - AE
Date: 19/03/2024

Work in progress | 30% Completed

25000M PVC Pipes Laid 36 FHTCs Provided

Pullad PH Sn - AE
Date: 15/03/2024

Work in progress | 30% Completed

25000M PVC Pipes Laid 36 FHTCs Provided

Pullad PH Sn - AE
Date: 11/03/2024

Work in progress | 24% Completed

12000M PVC Pipes Laid 25 FHTCs Provided.

Pullad PH Sn - AE
Date: 04/03/2024

Work in progress | 24% Completed

12000M PVC Pipes Laid 25 FHTCs Provided.

Pullad PH Sn - AE
Date: 26/02/2024

Work in progress | 24% Completed

12000M PVC Pipes Laid 25 FHTCs Provided.

Pullad PH Sn - AE
Date: 21/02/2024

Work in progress | 24% Completed

12000M PVC Pipes Laid 25 FHTCs Provided.

Pullad PH Sn - AE
Date: 17/02/2024

Work in progress | 24% Completed

12000M PVC Pipes Laid 25 FHTCs Provided.

Pullad PH Sn - AE
Date: 09/02/2024

Work in progress | 24% Completed

12000M PVC Pipes Laid 25 FHTCs Provided.

Pullad PH Sn - AE
Date: 05/02/2024

Work in progress | 24% Completed

12000M PVC Pipes Laid 25 FHTCs Provided.

Pullad PH Sn - AE
Date: 02/02/2024

Work in progress | 24% Completed

12000M PVC Pipes Laid 25 FHTCs Provided.

Pullad PH Sn - AE
Date: 31/01/2024

Work in progress | 20% Completed

Pipes fully supplied by the Contractor & work ongoing. 07 FHTCs Provided.

Pullad PH Sn - AE
Date: 22/01/2024

Work in progress | 20% Completed

Pipes fully supplied by the Contractor & work ongoing. 07 FHTCs Provided.

Pullad PH Sn - AE
Date: 16/01/2024

Work in progress | 20% Completed

Pipes fully supplied by the Contractor & work ongoing. 07 FHTCs Provided.

Pullad PH Sn - AE
Date: 09/01/2024

Work in progress | 15% Completed

Pipes fully supplied by the Contractor & work ongoing. 07 FHTCs Provided.

Pullad PH Sn - AE
Date: 01/01/2024

Work in progress | 15% Completed

Pipes fully supplied by the Contractor. 07 FHTCs Provided.

Pullad PH Sn - AE
Date: 27/12/2023

Work in progress | 15% Completed

Pipes fully supplied by the Contractor. 07 FHTCs Provided.

Pullad PH Sn - AE
Date: 23/12/2023

Work in progress | 15% Completed

PVC Pipes & GI Pipes fully supplied by the Contractor. 07FHTCs Provided.

Pullad PH Sn - AE
Date: 19/12/2023

Work in progress | 15% Completed

PVC Pipes & GI Pipes fully supplied by the Contractor. 07FHTCs Provided.

Pullad PH Sn - AE
Date: 15/12/2023

Work in progress | 15% Completed

PVC Pipes & GI Pipes fully supplied by the Contractor. 07FHTCs Provided.

Pullad PH Sn - AE
Date: 11/12/2023

Work in progress | 15% Completed

PVC Pipes & GI Pipes fully supplied by the Contractor. 07FHTCs Provided.

Pullad PH Sn - AE
Date: 07/12/2023

Work in progress | 15% Completed

PVC Pipes & GI Pipes fully supplied by the Contractor. 07FHTCs Provided.