| Vandoor AE |
| Date: 16/03/2025 |
Work has been completed | 100% Completed
Work completed-(PIPE LAID- 90 mm PVC 8kg/cm2 -7KM , 80mm GI PIPE -1.5 KM ,FHTC - 1250/1250 NOS) FINAL BILL SUBMITTED ON 15/03/2025
| Vandoor AE |
| Date: 11/03/2025 |
Work in progress | 99% Completed
PIPE LAID - 7KM FHTC - 1250/1480 NOS
| Vandoor AE |
| Date: 20/01/2025 |
Work in progress | 90% Completed
PIPE LAID - 7KM FHTC - 1233/1480 NOS
| Vandoor AE |
| Date: 17/01/2025 |
Work in progress | 90% Completed
PIPE LAID - 7KM FHTC - 1233/1480 NOS
| Vandoor AE |
| Date: 15/01/2025 |
Work in progress | 90% Completed
PIPE LAID - 7KM FHTC - 1233/1480 NOS
| Vandoor AE |
| Date: 09/01/2025 |
Work in progress | 90% Completed
PIPE LAID - 7KM FHTC - 1233/1480 NOS
| Vandoor AE |
| Date: 01/01/2025 |
Work in progress | 75% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed, Floor work completed, plumbing work of office building is completed.
| Vandoor AE |
| Date: 26/12/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed, Floor work and plumbing work of office building is progressing.
| Vandoor AE |
| Date: 24/12/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed, Floor work and plumbing work of office building is progressing.
| Vandoor AE |
| Date: 20/12/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed, Floor work and plumbing work of office building is progressing.
| Vandoor AE |
| Date: 18/12/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed, Floor work and plumbing work of office building is progressing.
| Vandoor AE |
| Date: 13/12/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed, Floor work and plumbing work of office building is progressing.
| Vandoor AE |
| Date: 12/12/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.
| Vandoor AE |
| Date: 09/12/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.
| Vandoor AE |
| Date: 06/12/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.
| Vandoor AE |
| Date: 04/12/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.
| Vandoor AE |
| Date: 02/12/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.
| Vandoor AE |
| Date: 29/11/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.
| Vandoor AE |
| Date: 27/11/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.
| Vandoor AE |
| Date: 25/11/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.
| Vandoor AE |
| Date: 22/11/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.
| Vandoor AE |
| Date: 20/11/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.
| Vandoor AE |
| Date: 18/11/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.
| Vandoor AE |
| Date: 15/11/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.
| Vandoor AE |
| Date: 11/11/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.
| Vandoor AE |
| Date: 07/11/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.
| Vandoor AE |
| Date: 05/11/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building in progress.
| Vandoor AE |
| Date: 02/11/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building in progress.
| Vandoor AE |
| Date: 29/10/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building in progress.
| Vandoor AE |
| Date: 24/10/2024 |
Work in progress | 50% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building in progress.
| Vandoor AE |
| Date: 22/10/2024 |
Work in progress | 1% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building in progress.
| Vandoor AE |
| Date: 18/10/2024 |
Work in progress | 1% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building in progress.
| Vandoor AE |
| Date: 16/10/2024 |
Work in progress | 1% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building in progress.
| Vandoor AE |
| Date: 14/10/2024 |
Work in progress | 1% Completed
1200 connection shifting, Plastering of office building is completed, Road work of office building in progress.
| Malappuram PH Dn EE |
| Date: 10/01/2024 |
Work has started | 0% Completed
TS Issued on 10.01.2024