Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kozhikode PH Dn EE
Date: 19/06/2024

Work has been completed | 100% Completed

Completed final bill submitted

Kozhikode PH Dn EE
Date: 20/04/2024

Work in progress | 98% Completed

Work in progress

Kozhikode PH Dn EE
Date: 04/04/2024

Work in progress | 93% Completed

Work in progress

Kozhikode PH Dn EE
Date: 12/03/2024

Work in progress | 89% Completed

Work in progress

Kozhikode PH Dn EE
Date: 01/03/2024

Work in progress | 87% Completed

Work in progress

Kozhikode PH Dn EE
Date: 14/02/2024

Work in progress | 85% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 27/01/2024

Work in progress | 80% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 12/01/2024

Work in progress | 78% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 11/12/2023

Work in progress | 76% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 28/11/2023

Work in progress | 73% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 09/11/2023

Work in progress | 67% Completed

Work Started

Kozhikode PH Dn EE
Date: 27/10/2023

Work in progress | 65% Completed

Work Started

Kozhikode PH Dn EE
Date: 17/10/2023

Work in progress | 60% Completed

Work Started

Kozhikode PH Dn EE
Date: 13/09/2023

Work in progress | 50% Completed

Work Started

Kozhikode PH Dn EE
Date: 05/09/2023

Work in progress | 40% Completed

Work Started

Kozhikode PH Dn EE
Date: 16/08/2023

Work in progress | 25% Completed

Work Started

Kozhikode PH Dn EE
Date: 07/08/2023

Work in progress | 20% Completed

Work Started

Kozhikode PH Dn EE
Date: 02/08/2023

Work in progress | 12% Completed

Work Started

Kozhikode PH Dn EE
Date: 24/07/2023

Work in progress | 10% Completed

Work Started

Kozhikode PH Dn EE
Date: 12/07/2023

Work has started | 0% Completed

Site handovered. Work not yet started.

Kozhikode PH Dn EE
Date: 30/06/2023

Work has started | 0% Completed

Site handovered. Work not yet started.

Kozhikode PH Dn EE
Date: 20/06/2023

Work has started | 0% Completed

Site handovered. Work not yet started.

Kozhikode PH Dn EE
Date: 13/06/2023

Work has started | 0% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 05/06/2023

Work has started | 0% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 01/06/2023

Work has started | 0% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 22/05/2023

Work has started | 0% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 11/05/2023

Work in progress | 0% Completed

Agreement Executed.

Kozhikode PH Dn EE
Date: 27/03/2023

Work has started | 0% Completed

Tendered. Due date 29-03-2023