Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Thodupuzha PH Sub Dn AEE
Date: 30/12/2025

Work has been completed | 100% Completed

Work completed

Thodupuzha PH Sn
Date: 22/12/2025

Work has been completed | 100% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293, RE Submitted

Thodupuzha PH Sn
Date: 29/08/2025

Work has been completed | 100% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293, RE Submitted

Thodupuzha PH Sn
Date: 27/08/2025

Work has been completed | 100% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293, RE Submitted

Thodupuzha PH Sn
Date: 11/08/2025

Work has been completed | 100% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293, RE Submitted

Thodupuzha PH Sn
Date: 02/08/2025

Work has been completed | 100% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293, RE Submitted

Thodupuzha PH Sn
Date: 30/07/2025

Work has been completed | 100% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293, RE Submitted

Thodupuzha PH Sn
Date: 23/07/2025

Work has been completed | 100% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293, RE Submitted

Thodupuzha PH Sn
Date: 21/06/2025

Work has been completed | 100% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293

Thodupuzha PH Sn
Date: 17/06/2025

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293

Thodupuzha PH Sn
Date: 22/04/2025

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 19/04/2025

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 07/04/2025

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 27/03/2025

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 17/03/2025

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 06/03/2025

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 17/02/2025

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 01/02/2025

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 24/01/2025

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 22/01/2025

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 13/01/2025

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 10/01/2025

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 03/01/2025

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 26/12/2024

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 18/12/2024

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 13/12/2024

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 09/12/2024

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 06/12/2024

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 02/12/2024

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 29/11/2024

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 25/11/2024

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 21/11/2024

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 18/11/2024

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 16/11/2024

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 13/11/2024

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 11/11/2024

Work in progress | 60% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290

Thodupuzha PH Sn
Date: 08/11/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 0 Fhts given Total 290

Thodupuzha PH Sn
Date: 06/11/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 0 Fhts given Total 290

Thodupuzha PH Sn
Date: 04/11/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 0 Fhts given Total 290

Thodupuzha PH Sn
Date: 01/11/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 0 Fhts given Total290

Thodupuzha PH Sn
Date: 26/10/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 0 Fhts given Total290

Thodupuzha PH Sn
Date: 21/10/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 0 Fhts given Total290

Thodupuzha PH Sn
Date: 18/10/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 0 Fhts given Total290

Thodupuzha PH Sn
Date: 15/10/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 04/10/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Dn EE
Date: 02/10/2024

Work in progress | 56% Completed

work in progress

Thodupuzha PH Sn
Date: 11/09/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 03/09/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 19/08/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 14/08/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 12/08/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 02/08/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 29/07/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 26/07/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 24/07/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 15/07/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 08/07/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 05/07/2024

Work in progress | 56% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 03/07/2024

Work in progress | 55% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 01/07/2024

Work in progress | 55% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 28/06/2024

Work in progress | 55% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 26/06/2024

Work in progress | 55% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 21/06/2024

Work in progress | 55% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745

Thodupuzha PH Sn
Date: 18/06/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 14/06/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 12/06/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 07/06/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 05/06/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 03/06/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 31/05/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 29/05/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 24/05/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 23/05/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 20/05/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 17/05/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 13/05/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 08/05/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 06/05/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 02/05/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 29/04/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 27/04/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 23/04/2024

Work in progress | 41% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 17/04/2024

Work in progress | 40% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started

Thodupuzha PH Sn
Date: 15/04/2024

Work in progress | 36% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started

Thodupuzha PH Sn
Date: 12/04/2024

Work in progress | 36% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started

Thodupuzha PH Sn
Date: 08/04/2024

Work in progress | 36% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started

Thodupuzha PH Sn
Date: 05/04/2024

Work in progress | 36% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started

Thodupuzha PH Sn
Date: 03/04/2024

Work in progress | 36% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started

Thodupuzha PH Sn
Date: 01/04/2024

Work in progress | 36% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started

Thodupuzha PH Sn
Date: 29/03/2024

Work in progress | 36% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started

Thodupuzha PH Sn
Date: 23/03/2024

Work in progress | 35% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started

Thodupuzha PH Sn
Date: 18/03/2024

Work in progress | 32% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started

Thodupuzha PH Sn
Date: 15/03/2024

Work in progress | 32% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started

Thodupuzha PH Sn
Date: 13/03/2024

Work in progress | 32% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started

Thodupuzha PH Sn
Date: 11/03/2024

Work in progress | 32% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started

Thodupuzha PH Sn
Date: 06/03/2024

Work in progress | 32% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.

Thodupuzha PH Sn
Date: 04/03/2024

Work in progress | 32% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.

Thodupuzha PH Sn
Date: 28/02/2024

Work in progress | 32% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.

Thodupuzha PH Sn
Date: 26/02/2024

Work in progress | 32% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.

Thodupuzha PH Sn
Date: 23/02/2024

Work in progress | 31% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.

Thodupuzha PH Sn
Date: 21/02/2024

Work in progress | 29% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.

Thodupuzha PH Sn
Date: 19/02/2024

Work in progress | 29% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.

Thodupuzha PH Dn EE
Date: 15/02/2024

Work in progress | 29% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.

Thodupuzha PH Dn EE
Date: 07/02/2024

Work in progress | 29% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.

Thodupuzha PH Dn EE
Date: 23/01/2024

Work in progress | 29% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.

Thodupuzha PH Dn EE
Date: 10/01/2024

Work in progress | 27% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed. 90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.

Thodupuzha PH Sn
Date: 01/01/2024

Work in progress | 27% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed. 90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.

Thodupuzha PH Dn EE
Date: 18/12/2023

Work in progress | 27% Completed

0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed. 90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.

Thodupuzha PH Dn EE
Date: 16/12/2023

Work in progress | 25% Completed

0.5LL Capacity at Kanjirampara - RCC Side Wall Completed. RWPH at Karoopara - Roof Slab Completed. PVC Pipe Supplied (75%)

Thodupuzha PH Sn
Date: 15/12/2023

Work in progress | 25% Completed

0.5LL Capacity at Kanjirampara - RCC Side Wall Completed. RWPH at Karoopara - Roof Slab Completed. PVC Pipe Supplied (75%)

Thodupuzha PH Dn EE
Date: 12/12/2023

Work in progress | 25% Completed

0.5LL Capacity at Kanjirampara - RCC Side Wall Completed. RWPH at Karoopara - Roof Slab Completed. PVC Pipe Supplied (75%)