| Thodupuzha PH Sub Dn AEE |
| Date: 30/12/2025 |
Work has been completed | 100% Completed
Work completed
| Thodupuzha PH Sn |
| Date: 22/12/2025 |
Work has been completed | 100% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293, RE Submitted
| Thodupuzha PH Sn |
| Date: 29/08/2025 |
Work has been completed | 100% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293, RE Submitted
| Thodupuzha PH Sn |
| Date: 27/08/2025 |
Work has been completed | 100% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293, RE Submitted
| Thodupuzha PH Sn |
| Date: 11/08/2025 |
Work has been completed | 100% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293, RE Submitted
| Thodupuzha PH Sn |
| Date: 02/08/2025 |
Work has been completed | 100% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293, RE Submitted
| Thodupuzha PH Sn |
| Date: 30/07/2025 |
Work has been completed | 100% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293, RE Submitted
| Thodupuzha PH Sn |
| Date: 23/07/2025 |
Work has been completed | 100% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293, RE Submitted
| Thodupuzha PH Sn |
| Date: 21/06/2025 |
Work has been completed | 100% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293
| Thodupuzha PH Sn |
| Date: 17/06/2025 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 293
| Thodupuzha PH Sn |
| Date: 22/04/2025 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 19/04/2025 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 07/04/2025 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 27/03/2025 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 17/03/2025 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 06/03/2025 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 17/02/2025 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 01/02/2025 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 24/01/2025 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 22/01/2025 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 13/01/2025 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 10/01/2025 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 03/01/2025 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 26/12/2024 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 18/12/2024 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 13/12/2024 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 09/12/2024 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 06/12/2024 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 02/12/2024 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 29/11/2024 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 25/11/2024 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 21/11/2024 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 18/11/2024 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 16/11/2024 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 13/11/2024 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 11/11/2024 |
Work in progress | 60% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 100 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 08/11/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 0 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 06/11/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 0 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 04/11/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 0 Fhts given Total 290
| Thodupuzha PH Sn |
| Date: 01/11/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 0 Fhts given Total290
| Thodupuzha PH Sn |
| Date: 26/10/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 0 Fhts given Total290
| Thodupuzha PH Sn |
| Date: 21/10/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 0 Fhts given Total290
| Thodupuzha PH Sn |
| Date: 18/10/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 2000 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started, 110mm PVC pipe 1180.4m laid, 100mm GI pipe 3000m laid, 90mm PVC pipe 483m laid,80mm GI pipe 903m laid, 0 Fhts given Total290
| Thodupuzha PH Sn |
| Date: 15/10/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 04/10/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Dn EE |
| Date: 02/10/2024 |
Work in progress | 56% Completed
work in progress
| Thodupuzha PH Sn |
| Date: 11/09/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 03/09/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 19/08/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 14/08/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 12/08/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 02/08/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 29/07/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 26/07/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 24/07/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 15/07/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 08/07/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 05/07/2024 |
Work in progress | 56% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 03/07/2024 |
Work in progress | 55% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 01/07/2024 |
Work in progress | 55% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 28/06/2024 |
Work in progress | 55% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 26/06/2024 |
Work in progress | 55% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 21/06/2024 |
Work in progress | 55% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started Fhts given :745
| Thodupuzha PH Sn |
| Date: 18/06/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 14/06/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 12/06/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 07/06/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 05/06/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 03/06/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 31/05/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 29/05/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 24/05/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 23/05/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 20/05/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 17/05/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 13/05/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 08/05/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 06/05/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 02/05/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 29/04/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 27/04/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 23/04/2024 |
Work in progress | 41% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 17/04/2024 |
Work in progress | 40% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.100 MM GI PIpe 3000mtr supplied ,80MM GI PIpe 1000mtr Supplied,Pumbing line work started
| Thodupuzha PH Sn |
| Date: 15/04/2024 |
Work in progress | 36% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started
| Thodupuzha PH Sn |
| Date: 12/04/2024 |
Work in progress | 36% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started
| Thodupuzha PH Sn |
| Date: 08/04/2024 |
Work in progress | 36% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started
| Thodupuzha PH Sn |
| Date: 05/04/2024 |
Work in progress | 36% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started
| Thodupuzha PH Sn |
| Date: 03/04/2024 |
Work in progress | 36% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started
| Thodupuzha PH Sn |
| Date: 01/04/2024 |
Work in progress | 36% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started
| Thodupuzha PH Sn |
| Date: 29/03/2024 |
Work in progress | 36% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started
| Thodupuzha PH Sn |
| Date: 23/03/2024 |
Work in progress | 35% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed ,Plastering and painting completed.Tank Plastering and painting completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started
| Thodupuzha PH Sn |
| Date: 18/03/2024 |
Work in progress | 32% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started
| Thodupuzha PH Sn |
| Date: 15/03/2024 |
Work in progress | 32% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started
| Thodupuzha PH Sn |
| Date: 13/03/2024 |
Work in progress | 32% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started
| Thodupuzha PH Sn |
| Date: 11/03/2024 |
Work in progress | 32% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.Pumbing line work started
| Thodupuzha PH Sn |
| Date: 06/03/2024 |
Work in progress | 32% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.
| Thodupuzha PH Sn |
| Date: 04/03/2024 |
Work in progress | 32% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.
| Thodupuzha PH Sn |
| Date: 28/02/2024 |
Work in progress | 32% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.
| Thodupuzha PH Sn |
| Date: 26/02/2024 |
Work in progress | 32% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.
| Thodupuzha PH Sn |
| Date: 23/02/2024 |
Work in progress | 31% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.
| Thodupuzha PH Sn |
| Date: 21/02/2024 |
Work in progress | 29% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.
| Thodupuzha PH Sn |
| Date: 19/02/2024 |
Work in progress | 29% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.
| Thodupuzha PH Dn EE |
| Date: 15/02/2024 |
Work in progress | 29% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.
| Thodupuzha PH Dn EE |
| Date: 07/02/2024 |
Work in progress | 29% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.
| Thodupuzha PH Dn EE |
| Date: 23/01/2024 |
Work in progress | 29% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed.Tank Plastering work completed.90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.
| Thodupuzha PH Dn EE |
| Date: 10/01/2024 |
Work in progress | 27% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed. 90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.
| Thodupuzha PH Sn |
| Date: 01/01/2024 |
Work in progress | 27% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed. 90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.
| Thodupuzha PH Dn EE |
| Date: 18/12/2023 |
Work in progress | 27% Completed
0.5LL Capacity at Kanjirampara - RCC top slab Completed. RWPH at Karoopara - Roof Slab Completed. 90 mm PVC Pipe- 3500 m Supplied. 110 mm PVC Pipe- 1200 m Supplied.
| Thodupuzha PH Dn EE |
| Date: 16/12/2023 |
Work in progress | 25% Completed
0.5LL Capacity at Kanjirampara - RCC Side Wall Completed. RWPH at Karoopara - Roof Slab Completed. PVC Pipe Supplied (75%)
| Thodupuzha PH Sn |
| Date: 15/12/2023 |
Work in progress | 25% Completed
0.5LL Capacity at Kanjirampara - RCC Side Wall Completed. RWPH at Karoopara - Roof Slab Completed. PVC Pipe Supplied (75%)
| Thodupuzha PH Dn EE |
| Date: 12/12/2023 |
Work in progress | 25% Completed
0.5LL Capacity at Kanjirampara - RCC Side Wall Completed. RWPH at Karoopara - Roof Slab Completed. PVC Pipe Supplied (75%)