Kattapana AE 1 |
Date: 28/12/2021 |
Work has been completed | 100% Completed
Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021
Kattapana AE 1 |
Date: 22/12/2021 |
Work has been completed | 100% Completed
Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021
Kattapana AE 1 |
Date: 16/12/2021 |
Work has been completed | 100% Completed
Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021
Kattapana AE 1 |
Date: 13/12/2021 |
Work has been completed | 100% Completed
Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021
Kattapana AE 1 |
Date: 06/12/2021 |
Work has been completed | 100% Completed
Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021
Kattapana AE 1 |
Date: 01/12/2021 |
Work has been completed | 100% Completed
Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021
Kattapana AE 1 |
Date: 24/11/2021 |
Work has been completed | 100% Completed
Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021
Kattapana AE 1 |
Date: 20/11/2021 |
Work has been completed | 100% Completed
Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021
Kattapana AE 1 |
Date: 11/11/2021 |
Work has been completed | 100% Completed
Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021
Kattapana AE 1 |
Date: 26/10/2021 |
Work has been completed | 100% Completed
Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021
Kattapana AE 1 |
Date: 21/10/2021 |
Work has been completed | 100% Completed
Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021
Kattappana AEE 1 |
Date: 07/10/2021 |
Work has been completed | 100% Completed
Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021
Kattappana AEE 1 |
Date: 30/09/2021 |
Work has been completed | 100% Completed
Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021
Kattappana AEE 1 |
Date: 23/01/2021 |
Work has been completed | 100% Completed
Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021
Kattappana AEE 1 |
Date: 04/01/2021 |
Work in progress | 88% Completed
Out of 500 Nos FHTC, 440 Nos provided till 03-01-2021
Kattappana AEE 1 |
Date: 24/12/2020 |
Work in progress | 87% Completed
Out of 500 Nos FHTC, 435 Nos provided till 23-12-2020
Kattappana AEE 1 |
Date: 12/12/2020 |
Work in progress | 69% Completed
Out of 500 Nos FHTC, 349 Nos provided.
Kattappana AEE 1 |
Date: 03/12/2020 |
Work in progress | 57% Completed
Out of 500 Nos FHTC, 286 Nos provided.
Kattappana AEE 1 |
Date: 25/11/2020 |
Work in progress | 44% Completed
Out of 500 Nos FHTC, 223 Nos provided.
Kattappana AEE 1 |
Date: 22/11/2020 |
Kattappana AEE 1 |
Date: 21/11/2020 |
Work in progress | 38% Completed
Out of 500 FHTC, 194 Nos FHTC provided up to 21/11/2020.
Kattappana AEE 1 |
Date: 17/11/2020 |
Work in progress | 32% Completed
Out of 500 Nos FHTC, 164 Nos provided
Kattappana AEE 1 |
Date: 11/11/2020 |
Work in progress | 24% Completed
124 Nos FHTC provided. 79 Nos approved by AE. 78 Nos entered in IMIS.
Kattappana AEE 1 |
Date: 06/11/2020 |
Work in progress | 15% Completed
82 Nos FHTC provided
Kattappana AEE 1 |
Date: 30/10/2020 |
Work in progress | 10% Completed
52 Nos FHTC provided
Kattappana AEE 1 |
Date: 16/10/2020 |
Work in progress | 1% Completed
Work awarded to contractor. Beneficiary list obtained.