Kattapana AE 1
Date: 28/12/2021

Work has been completed | 100% Completed

Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021

Kattapana AE 1
Date: 22/12/2021

Work has been completed | 100% Completed

Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021

Kattapana AE 1
Date: 16/12/2021

Work has been completed | 100% Completed

Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021

Kattapana AE 1
Date: 13/12/2021

Work has been completed | 100% Completed

Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021

Kattapana AE 1
Date: 06/12/2021

Work has been completed | 100% Completed

Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021

Kattapana AE 1
Date: 01/12/2021

Work has been completed | 100% Completed

Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021

Kattapana AE 1
Date: 24/11/2021

Work has been completed | 100% Completed

Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021

Kattapana AE 1
Date: 20/11/2021

Work has been completed | 100% Completed

Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021

Kattapana AE 1
Date: 11/11/2021

Work has been completed | 100% Completed

Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021

Kattapana AE 1
Date: 26/10/2021

Work has been completed | 100% Completed

Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021

Kattapana AE 1
Date: 21/10/2021

Work has been completed | 100% Completed

Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021

Kattappana AEE 1
Date: 07/10/2021

Work has been completed | 100% Completed

Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021

Kattappana AEE 1
Date: 30/09/2021

Work has been completed | 100% Completed

Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021

Kattappana AEE 1
Date: 23/01/2021

Work has been completed | 100% Completed

Out of 500 Nos FHTC, 514 Nos provided. Work completed on 19-01-2021

Kattappana AEE 1
Date: 04/01/2021

Work in progress | 88% Completed

Out of 500 Nos FHTC, 440 Nos provided till 03-01-2021

Kattappana AEE 1
Date: 24/12/2020

Work in progress | 87% Completed

Out of 500 Nos FHTC, 435 Nos provided till 23-12-2020

Kattappana AEE 1
Date: 12/12/2020

Work in progress | 69% Completed

Out of 500 Nos FHTC, 349 Nos provided.

Kattappana AEE 1
Date: 03/12/2020

Work in progress | 57% Completed

Out of 500 Nos FHTC, 286 Nos provided.

Kattappana AEE 1
Date: 25/11/2020

Work in progress | 44% Completed

Out of 500 Nos FHTC, 223 Nos provided.

Kattappana AEE 1
Date: 22/11/2020

Work in progress | 40% Completed

Out of 500 FHTC, 200 FHTC Provided till 22-11-2020.

Attached images

img img

Kattappana AEE 1
Date: 21/11/2020

Work in progress | 38% Completed

Out of 500 FHTC, 194 Nos FHTC provided up to 21/11/2020.

Kattappana AEE 1
Date: 17/11/2020

Work in progress | 32% Completed

Out of 500 Nos FHTC, 164 Nos provided

Kattappana AEE 1
Date: 11/11/2020

Work in progress | 24% Completed

124 Nos FHTC provided. 79 Nos approved by AE. 78 Nos entered in IMIS.

Kattappana AEE 1
Date: 06/11/2020

Work in progress | 15% Completed

82 Nos FHTC provided

Kattappana AEE 1
Date: 30/10/2020

Work in progress | 10% Completed

52 Nos FHTC provided

Kattappana AEE 1
Date: 16/10/2020

Work in progress | 1% Completed

Work awarded to contractor. Beneficiary list obtained.