| Kozhikode Dist 1 Sn 2 - AE |
| Date: 23/10/2024 |
Work has been completed | 100% Completed
Corrected RE submitted and Final bill to be submitted.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 22/10/2024 |
Work has been completed | 100% Completed
Corrected RE to be send and Final Bill to be submitted
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 11/09/2024 |
Work has been completed | 100% Completed
Work completed.RE send and approvaL pending.Final bill to be submitted.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 21/08/2024 |
Work in progress | 99% Completed
RE preparation started
| Kozhikode PH Dn EE |
| Date: 21/04/2024 |
Work in progress | 20% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 5% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work has started | 0% Completed
Agreement executed
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work has started | 0% Completed
agreement executed
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work has started | 0% Completed
Work Order Issued
| Kozhikode PH Dn EE |
| Date: 12/01/2024 |
Work has started | 0% Completed
Work Order Issued