| Kozhikode PH Dn EE |
| Date: 31/10/2024 |
Work has been completed | 100% Completed
435 FHTC has been given. 2689.5 m 110 mm PVC pipe 10kg/cm2 laying completed. Restoration work completed.
| Kozhikode PH Dn EE |
| Date: 28/10/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-395 Nos - Pipe (110mm) laying work completed
| Kozhikode PH Dn EE |
| Date: 23/10/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-395 Nos - Pipe (110mm) laying work completed
| Kozhikode PH Dn EE |
| Date: 21/10/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-389 Nos - Pipe (110mm) laying work completed
| Kozhikode PH Dn EE |
| Date: 18/10/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-377 Nos - Pipe (110mm) laying work completed
| Kozhikode PH Dn EE |
| Date: 16/10/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-370 Nos - Pipe (110mm) laying work completed
| Kozhikode PH Dn EE |
| Date: 14/10/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-363 Nos - Pipe (110mm) laying work completed
| Kozhikode PH Dn EE |
| Date: 10/10/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-361 Nos - Pipe (110mm) laying work completed
| Kozhikode PH Dn EE |
| Date: 07/10/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-360 Nos - Pipe (110mm) laying work completed
| Kozhikode PH Dn EE |
| Date: 03/10/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-358 Nos - Pipe (110mm) laying work completed
| Kozhikode PH Dn EE |
| Date: 30/09/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-356 Nos - Pipe (110mm) laying work completed - Requested to Time extension
| Kozhikode PH Dn EE |
| Date: 27/09/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-353Nos - Pipe (110mm) laying work completed - Requested to Time extension
| Kozhikode PH Dn EE |
| Date: 24/09/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-352 Nos - Pipe (110mm) laying work completed - Requested to Time extension
| Kozhikode PH Dn EE |
| Date: 20/09/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-350 Nos - Pipe (110mm) laying work completed - Requested to Time extension
| Kozhikode PH Dn EE |
| Date: 17/09/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-348 Nos - Pipe (110mm) laying work completed - Requested to Time extension
| Kozhikode PH Dn EE |
| Date: 13/09/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-348 Nos - Pipe (110mm) laying work completed - Requested to Time extension
| Kozhikode PH Dn EE |
| Date: 09/09/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-348 Nos - Pipe (110mm) laying work completed - Requested to Time extension
| Kozhikode PH Dn EE |
| Date: 03/09/2024 |
Work in progress | 92% Completed
Restoration work in progress- FHTCs-348 Nos - Pipe (110mm) laying work completed - Requested to Time extension
| Kozhikode PH Dn EE |
| Date: 31/08/2024 |
Work in progress | 92% Completed
Work in progress- FHTCs-348 Nos - Pipe (110mm) laying work completed
| Kozhikode PH Dn EE |
| Date: 29/08/2024 |
Work in progress | 92% Completed
Work in progress- FHTCs-341 Nos - Pipe (110mm) laying work completed
| Kozhikode PH Dn EE |
| Date: 28/08/2024 |
Work in progress | 92% Completed
Work in progress- FHTCs-337 Nos - Pipe (110mm) laying work completed
| Kozhikode PH Dn EE |
| Date: 26/08/2024 |
Work in progress | 92% Completed
Work in progress- FHTCs-330 Nos
| Kozhikode PH Dn EE |
| Date: 21/08/2024 |
Work in progress | 92% Completed
Work in progress. Pipe laying and restoration works completed. Fhtcs Work in progress
| Kozhikode PH Dn EE |
| Date: 19/08/2024 |
Work in progress | 92% Completed
Work in progress. Pipe laying and restoration works completed. Fhtcs Work in progress
| Kozhikode PH Dn EE |
| Date: 16/08/2024 |
Work in progress | 92% Completed
Work in progress. Pipe laying and restoration works completed. Fhtcs Work in progress
| Kozhikode PH Dn EE |
| Date: 25/06/2024 |
Work in progress | 90% Completed
Work in progress-Pipe laid-110mm PVC-2730m, FHTCs-340 nos.
| Kozhikode PH Dn EE |
| Date: 24/06/2024 |
Work in progress | 90% Completed
Work in progress-Pipe laid-110mm PVC-2730m, FHTCs-340 nos.
| Kozhikode PH Dn EE |
| Date: 14/06/2024 |
Work in progress | 85% Completed
Work in progress-Pipe laid-110mm PVC-2730m
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 80% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 78% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 75% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 21/02/2024 |
Work in progress | 73% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 72% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 31/01/2024 |
Work in progress | 69% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 68% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 22/01/2024 |
Work in progress | 67% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 21/01/2024 |
Work in progress | 67% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 20/01/2024 |
Work in progress | 67% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 19/01/2024 |
Work in progress | 67% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 18/01/2024 |
Work in progress | 67% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 17/01/2024 |
Work in progress | 66% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 16/01/2024 |
Work in progress | 66% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 15/01/2024 |
Work in progress | 66% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 14/01/2024 |
Work in progress | 66% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 13/01/2024 |
Work in progress | 66% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 12/01/2024 |
Work in progress | 66% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 11/01/2024 |
Work in progress | 65% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 01/01/2024 |
Work in progress | 58% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 12/12/2023 |
Work in progress | 58% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work in progress | 58% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 28/11/2023 |
Work in progress | 55% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 09/11/2023 |
Work in progress | 53% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 28/10/2023 |
Work in progress | 50% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 17/10/2023 |
Work in progress | 48% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 15/09/2023 |
Work in progress | 40% Completed
40% Work Completed
| Kozhikode PH Dn EE |
| Date: 05/09/2023 |
Work in progress | 35% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 17/08/2023 |
Work in progress | 25% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 08/08/2023 |
Work in progress | 15% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 27/07/2023 |
Work in progress | 5% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 24/07/2023 |
Work has started | 0% Completed
Site Handed Over. Work Not Yet Started
| Kozhikode PH Dn EE |
| Date: 12/07/2023 |
Work has started | 0% Completed
Work Order Issued. Work not yet started.
| Kozhikode PH Dn EE |
| Date: 30/06/2023 |
Work has started | 0% Completed
Work Order Issued. Work not yet started.
| Kozhikode PH Dn EE |
| Date: 20/06/2023 |
Work has started | 0% Completed
Work Order Issued. Work not yet started.
| Kozhikode PH Dn EE |
| Date: 13/06/2023 |
Work has started | 0% Completed
Work Order Issued
| Kozhikode PH Dn EE |
| Date: 08/06/2023 |
Work has started | 0% Completed
Work Order Issued. Not Yet Started
| Kozhikode PH Dn EE |
| Date: 05/06/2023 |
Work in progress | 1% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 01/06/2023 |
Work in progress | 1% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 29/05/2023 |
Work in progress | 1% Completed
Agreement Executed