Chittur Project Dn - AE 3
Date: 27/06/2024

Work in progress | 48% Completed

DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m

Chittur Project Dn - AE 3
Date: 20/06/2024

Work in progress | 48% Completed

DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m

Chittur Project Dn - AE 3
Date: 12/06/2024

Work in progress | 48% Completed

DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m

Chittur Project Dn - AE 3
Date: 06/06/2024

Work in progress | 48% Completed

DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m

Chittur Project Dn - AE 3
Date: 01/06/2024

Work in progress | 48% Completed

DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m

Chittur Project Dn - AE 3
Date: 23/05/2024

Work in progress | 48% Completed

DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m

Chittur Project Dn - AE 3
Date: 16/05/2024

Work in progress | 48% Completed

DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m

Chittur Project Dn - AE 3
Date: 09/05/2024

Work in progress | 48% Completed

DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m

Chittur Project Dn - AE 3
Date: 02/05/2024

Work in progress | 48% Completed

DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m

Chittur Project Dn - AE 3
Date: 25/04/2024

Work in progress | 48% Completed

DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m

Chittur Project Dn - AE 3
Date: 19/04/2024

Work in progress | 48% Completed

DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m

Chittur Project Dn - AE 3
Date: 11/04/2024

Work in progress | 48% Completed

DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m

Chittur Project Dn - AE 3
Date: 04/04/2024

Work in progress | 48% Completed

DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m

Chittur Project Dn - AE 3
Date: 21/03/2024

Work in progress | 48% Completed

DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m

Chittur Project Dn - AE 3
Date: 14/03/2024

Work in progress | 48% Completed

DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m

Chittur Project Dn - AE 3
Date: 28/02/2024

Work in progress | 48% Completed

DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m

Chittur Project Dn - AE 3
Date: 22/02/2024

Work in progress | 46% Completed

DI and PVC work started, 58.517km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m

Chittur Project Dn - AE 3
Date: 14/02/2024

Work in progress | 46% Completed

DI and PVC work started, 58.517km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m

Chittur Project Dn - AE 1
Date: 24/01/2024

Work in progress | 46% Completed

DI and PVC work started, 58.517km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m

Chittur Project Dn - AE 3
Date: 01/12/2023

Work in progress | 46% Completed

DI and PVC work started, 57.701km pipe line laid /126km HTC 595 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49504.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 1830 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M

Chittur Project Dn - AE 3
Date: 29/11/2023

Work in progress | 45% Completed

DI and PVC work started, 57.701km pipe line laid /126km HTC 595 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49504.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 1830 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M

Chittur Project Dn - AE 3
Date: 09/11/2023

Work in progress | 40% Completed

DI and PVC work started, 53381.50 m pipe line laid /126km HTC 595 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-45636.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 1398 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1542 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M

Chittur Project Dn - AE 3
Date: 03/11/2023

Work in progress | 40% Completed

DI and PVC work started, 51713.50 m pipe line laid /126km HTC 348/4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-44004.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 1362 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1542 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M

Chittur Project Dn - AE 3
Date: 12/10/2023

Work in progress | 28% Completed

DI and PVC work started,36107.50 m pipe line laid /126km HTC 348/4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-30090.00m 3)500 mm DI-957.00 4)100 mm GI – 24M 5)80mm GI- 648 M 6)110mm 8kg pvc-34 m 7)110 mm 6kg-pvc-990 8)160MM PVC 6Kg-1068M 9)160MM 8 KG-492M

Chittur Project Dn - AE 3
Date: 30/09/2023

Work in progress | 15% Completed

DI and PVC work started,23.639 km pipe line laid /126km FHTC 281/PROVIDED 1)600 mm DI-1738.50m 2)90MM PVC-18600.00m 3)500 mm DI-957.00 4)90mm pvc 6kg- 5)80mm GI-210M 6)110mm 8kg pvc-34 m 7)110 mm 6kg-pvc-990 8)160MM PVC 6KG-900M 9)160MM 8 KG-210M

Chittur Project Dn - AE 3
Date: 07/09/2023

Work in progress | 11% Completed

DI and PVC work started,16.673km pipe line laid /126km 1)600 mm DI-1639.50m 2)90MM PVC-7986.00m 3)500 mm DI-599.50 4)90mm pvc 6kg-5952 m 5)80mm GI-6M 6)110mm 8kg pvc-34 m 7)110 mm 6kg-pvc-456m

Chittur Project Dn - AE 3
Date: 26/08/2023

Work in progress | 7% Completed

DI and PVC work started,9.609km pipe line laid /126km 1)600 mm DI-1623.00m 2)90MM PVC-7986.00m

Chittur Project Dn - AE 3
Date: 15/08/2023

Work in progress | 4% Completed

DI and PVC work started,6.726km pipe line laid /126km 1)600 mm DI-1458.00m 2)90MM PVC-5268.00m

Chittur Project Dn - AE 3
Date: 03/08/2023

Work in progress | 1% Completed

DI and PVC work started,3618.50m pipe line laid 1)600 mm DI-1254.50m 2)90MM PVC-2364.00m

Chittur Project Dn - AE 3
Date: 20/07/2023

Work in progress | 1% Completed

DI and PVC work started,492 m pipe line laid at site, 600 mm DI-270M,90MM PVC-222M

Chittur Project Dn - AE 3
Date: 13/07/2023

Work in progress | 1% Completed

AGREEMENT EXECUTED,work not started

Chittur Project Dn - AE 3
Date: 04/07/2023

Work in progress | 1% Completed

AGREEMENT EXECUTED