Kollam WS Sn 3 - AE
Date: 16/08/2023

Work has been completed | 100% Completed

Work completed.

Kollam WS Sn 3 - AE
Date: 14/08/2023

Work in progress | 90% Completed

Pipe laying completed.

Kollam WS Sn 3 - AE
Date: 09/08/2023

Work in progress | 90% Completed

Pipe laying completed.

Kollam WS Sn 3 - AE
Date: 05/08/2023

Work in progress | 90% Completed

Pipe laying completed.

Kollam WS Sn 3 - AE
Date: 31/07/2023

Work in progress | 90% Completed

Pipe laying completed.

Kollam WS Sn 3 - AE
Date: 25/07/2023

Work in progress | 90% Completed

Pipe laying completed.

Kollam WS Sn 3 - AE
Date: 22/07/2023

Work in progress | 90% Completed

Pipe laying completed.

Kollam WS Sn 3 - AE
Date: 18/07/2023

Work in progress | 90% Completed

Pipe laying completed.

Kollam WS Sn 3 - AE
Date: 13/07/2023

Work in progress | 90% Completed

Pipe laying completed.

Kollam WS Sn 3 - AE
Date: 10/07/2023

Work in progress | 90% Completed

Pipe laying completed.

Kollam WS Sn 3 - AE
Date: 06/07/2023

Work in progress | 90% Completed

Pipe laying completed.

Kollam WS Sn 3 - AE
Date: 01/07/2023

Work in progress | 90% Completed

Pipe laying completed.

Kollam WS Sn 3 - AE
Date: 24/06/2023

Work in progress | 85% Completed

Pipe laying in progress.

Kollam WS Sn 3 - AE
Date: 17/06/2023

Work in progress | 60% Completed

pipe laying in progress.

Kollam WS Sn 3 - AE
Date: 12/06/2023

Work in progress | 5% Completed

Pipe supplied, and pipe laying started.

Kollam WS Sn 3 - AE
Date: 06/06/2023

Work has started | 0% Completed

waiting for pipe testing and supply.

Kollam WS Sn 3 - AE
Date: 01/06/2023

Work has started | 0% Completed

waiting for pipe testing and supply.

Kollam WS Sn 3 - AE
Date: 29/05/2023

Work has started | 0% Completed

waiting for pipe testing and supply.

Kollam WS Sn 3 - AE
Date: 25/05/2023

Work in progress | 0% Completed

waiting for pipe testing and supply.

Kollam WS Sn 3 - AE
Date: 18/05/2023

Work has started | 0% Completed

LoA sent to contractor

Kollam WS Sn 3 - AE
Date: 15/05/2023

Work has started | 0% Completed

LoA sent to contractor

Kollam WS Sn 3 - AE
Date: 10/05/2023

Work has started | 0% Completed

LoA sent to contractor