| Kannur PH Dn EE |
| Date: 23/12/2025 |
Work has been completed | 100% Completed
work completed.bill under preperation
| Kannur WS Sn AE 2 |
| Date: 16/12/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation
| Kannur WS Sn AE 2 |
| Date: 13/12/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation
| Kannur WS Sn AE 2 |
| Date: 09/12/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation
| Kannur WS Sn AE 2 |
| Date: 05/12/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation
| Kannur WS Sn AE 2 |
| Date: 02/12/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation
| Kannur WS Sn AE 2 |
| Date: 28/11/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation
| Kannur WS Sn AE 2 |
| Date: 24/11/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation
| Kannur WS Sn AE 2 |
| Date: 20/11/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation
| Kannur WS Sn AE 2 |
| Date: 17/11/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation
| Kannur WS Sn AE 2 |
| Date: 13/11/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation
| Kannur WS Sn AE 2 |
| Date: 10/11/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation
| Kannur WS Sn AE 2 |
| Date: 07/11/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation
| Kannur WS Sn AE 2 |
| Date: 03/11/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 30/10/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 25/10/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 21/10/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 15/10/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 09/10/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 06/10/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 03/10/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 29/09/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 25/09/2025 |
Work in progress | 99% Completed
50 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 22/09/2025 |
Work in progress | 99% Completed
46 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 18/09/2025 |
Work in progress | 98% Completed
46 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 15/09/2025 |
Work in progress | 98% Completed
46 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 11/09/2025 |
Work in progress | 98% Completed
46 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 08/09/2025 |
Work in progress | 98% Completed
46 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 04/09/2025 |
Work in progress | 98% Completed
46 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 01/09/2025 |
Work in progress | 98% Completed
46 Nos public tap disconnected out of 46 Nos.CC 1st and final bill under preparation.
| Kannur WS Sn AE 2 |
| Date: 29/08/2025 |
Work in progress | 98% Completed
46 Nos public tap disconnected out of 46 Nos.
| Kannur WS Sn AE 2 |
| Date: 25/08/2025 |
Work in progress | 98% Completed
46 Nos public tap disconnected out of 46 Nos.
| Kannur WS Sn AE 2 |
| Date: 21/08/2025 |
Work in progress | 98% Completed
46 Nos public tap disconnected out of 46 Nos.
| Kannur WS Sn AE 2 |
| Date: 18/08/2025 |
Work in progress | 98% Completed
46 Nos public tap disconnected out of 46 Nos.
| Kannur WS Sn AE 2 |
| Date: 14/08/2025 |
Work in progress | 98% Completed
46 Nos public tap disconnected out of 46 Nos.
| Kannur WS Sn AE 2 |
| Date: 11/08/2025 |
Work in progress | 91% Completed
42 Nos public tap disconnected out of 46 Nos.
| Kannur WS Sn AE 2 |
| Date: 06/08/2025 |
Work in progress | 91% Completed
42 Nos public tap disconnected out of 46 Nos.
| Kannur WS Sn AE 2 |
| Date: 04/08/2025 |
Work in progress | 91% Completed
42 Nos public tap disconnected out of 46 Nos.
| Kannur WS Sn AE 2 |
| Date: 31/07/2025 |
Work in progress | 86% Completed
42 Nos public tap disconnected out of 46 Nos.
| Kannur WS Sn AE 2 |
| Date: 28/07/2025 |
Work in progress | 86% Completed
40 Nos public tap disconnected out of 46 Nos.
| Kannur WS Sn AE 2 |
| Date: 25/07/2025 |
Work in progress | 76% Completed
35 Nos public tap disconnected out of 46 Nos.
| Kannur WS Sn AE 2 |
| Date: 21/07/2025 |
Work in progress | 60% Completed
28 Nos public tap disconnected out of 46 Nos.
| Kannur WS Sn AE 2 |
| Date: 18/07/2025 |
Work in progress | 43% Completed
20 Nos public tap disconnected out of 46 Nos.
| Kannur WS Sn AE 2 |
| Date: 14/07/2025 |
Work in progress | 1% Completed
No response received
| Kannur WS Sn AE 2 |
| Date: 11/07/2025 |
Work in progress | 1% Completed
No response received
| Kannur WS Sn AE 2 |
| Date: 08/07/2025 |
Work in progress | 1% Completed
No response received
| Kannur WS Sn AE 2 |
| Date: 05/07/2025 |
Work in progress | 1% Completed
no response recived
| Kannur WS Sub-Dn - AEE |
| Date: 30/06/2025 |
Work in progress | 1% Completed
ONGOING