Oachira AE
Date: 08/09/2026

Work has been completed | 100% Completed

Work completed

Oachira AE
Date: 31/08/2026

Work in progress | 50% Completed

Work ongoing

Oachira AE
Date: 26/08/2026

Work in progress | 20% Completed

Work ongoing

Oachira AE
Date: 21/08/2026

Work in progress | 10% Completed

Work started

Oachira AE
Date: 17/08/2026

Work in progress | 10% Completed

75 mm PVC (6 kg/cm2) pipe 120 m supplied.

Oachira AE
Date: 13/08/2026

Work in progress | 10% Completed

75 mm PVC (6 kg/cm2) pipe 120 m supplied.

Oachira AE
Date: 10/08/2026

Work in progress | 10% Completed

75 mm PVC (6 kg/cm2) pipe 120 m supplied.

Oachira AE
Date: 17/07/2026

Work in progress | 10% Completed

75 mm PVC (6 kg/cm2) pipe 120 m supplied.

Oachira AE
Date: 13/07/2026

Work in progress | 10% Completed

75 mm PVC (6 kg/cm2) pipe 120 m supplied.

Oachira AE
Date: 10/07/2026

Work in progress | 10% Completed

75 mm PVC (6 kg/cm2) pipe 120 m supplied.

Oachira AE
Date: 06/07/2026

Work in progress | 10% Completed

75 mm PVC (6 kg/cm2) pipe 120 m supplied.

Attached images

img img

Oachira AE
Date: 01/07/2026

Work in progress | 1% Completed

Agreement executed. Supply order issued for pipe testing

Oachira AE
Date: 30/06/2026

Work in progress | 1% Completed

Agreement executed. Supply order issued for pipe testing