Chavara AE
Date: 06/02/2026

Work has been completed | 100% Completed

work completed

Chavara AE
Date: 02/02/2026

Work in progress | 85% Completed

Pumpset erection completed.

Chavara AE
Date: 29/01/2026

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway

Chavara AE
Date: 24/01/2026

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway

Chavara AE
Date: 20/01/2026

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway

Chavara AE
Date: 16/01/2026

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway

Chavara AE
Date: 12/01/2026

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway

Chavara AE
Date: 07/01/2026

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway

Chavara AE
Date: 03/01/2026

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway

Chavara AE
Date: 31/12/2025

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway

Chavara AE
Date: 24/12/2025

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway

Chavara AE
Date: 19/12/2025

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway

Chavara AE
Date: 15/12/2025

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway

Chavara AE
Date: 11/12/2025

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.

Chavara AE
Date: 03/12/2025

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.

Chavara AE
Date: 29/11/2025

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.

Chavara AE
Date: 26/11/2025

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.

Chavara AE
Date: 21/11/2025

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.

Chavara AE
Date: 18/11/2025

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.

Chavara AE
Date: 13/11/2025

Work in progress | 55% Completed

Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.

Chavara AE
Date: 10/11/2025

Work in progress | 55% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.

Chavara AE
Date: 04/11/2025

Work in progress | 55% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.

Chavara AE
Date: 30/10/2025

Work in progress | 55% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.

Chavara AE
Date: 27/10/2025

Work in progress | 55% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.

Chavara AE
Date: 21/10/2025

Work in progress | 55% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.

Chavara AE
Date: 16/10/2025

Work in progress | 55% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.

Chavara AE
Date: 13/10/2025

Work in progress | 55% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.

Chavara AE
Date: 03/10/2025

Work in progress | 55% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.

Chavara AE
Date: 29/09/2025

Work in progress | 55% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.

Chavara AE
Date: 22/09/2025

Work in progress | 55% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.

Chavara AE
Date: 18/09/2025

Work in progress | 55% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.

Chavara AE
Date: 15/09/2025

Work in progress | 55% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.

Chavara AE
Date: 10/09/2025

Work in progress | 55% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.

Chavara AE
Date: 07/09/2025

Work in progress | 55% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.

Chavara AE
Date: 01/09/2025

Work in progress | 55% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.

Chavara AE
Date: 29/08/2025

Work in progress | 55% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.

Chavara AE
Date: 19/08/2025

Work in progress | 37% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Drilling work ongoing.

Chavara AE
Date: 16/08/2025

Work in progress | 35% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed.

Chavara AE
Date: 11/08/2025

Work in progress | 35% Completed

Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025.

Chavara AE
Date: 06/08/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 01/08/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 29/07/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 26/07/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 21/07/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 19/07/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 17/07/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 14/07/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 11/07/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 08/07/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 04/07/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 30/06/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 26/06/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 23/06/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 19/06/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 16/06/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 09/06/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 05/06/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 03/06/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 30/05/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 26/05/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 20/05/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 17/05/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 14/05/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 08/05/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 05/05/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 02/05/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 29/04/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 26/04/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 23/04/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 18/04/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 15/04/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 11/04/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 07/04/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 03/04/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 31/03/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 27/03/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 24/03/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 21/03/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 18/03/2025

Work in progress | 35% Completed

Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).

Chavara AE
Date: 15/03/2025

Work in progress | 16% Completed

60 m drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed.

Chavara AE
Date: 13/03/2025

Work in progress | 15% Completed

45 m drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed.

Attached images

img

Chavara AE
Date: 10/03/2025

Work has started | 0% Completed

Agreement executed on 11.02.2025

Chavara AE
Date: 05/03/2025

Work has started | 0% Completed

Agreement executed on 11.02.2025

Chavara AE
Date: 01/03/2025

Work has started | 0% Completed

Agreement executed on 11.02.2025

Chavara AE
Date: 27/02/2025

Work has started | 0% Completed

Agreement executed on 11.02.2025

Chavara AE
Date: 23/02/2025

Work has started | 0% Completed

Agreement executed on 11.02.2025

Chavara AE
Date: 20/02/2025

Work has started | 0% Completed

Agreement executed on 11.02.2025

Chavara AE
Date: 17/02/2025

Work has started | 0% Completed

Agreement executed on 11.02.2025

Chavara AE
Date: 14/02/2025

Work has started | 0% Completed

Agreement executed on 11.02.2025

Chavara AE
Date: 10/02/2025

Work has started | 0% Completed

Tender process ongoing

Chavara AE
Date: 07/02/2025

Work has started | 0% Completed

Tender process ongoing

Chavara AE
Date: 04/02/2025

Work has started | 0% Completed

Tendering process ongoing

Chavara AE
Date: 02/02/2025

Work has started | 0% Completed

Tendering process ongoing

Chavara AE
Date: 30/01/2025

Work has started | 0% Completed

Tendering process ongoing

Chavara AE
Date: 27/01/2025

Work has started | 0% Completed

Tendering process ongoing

Chavara AE
Date: 24/01/2025

Work has started | 0% Completed

Tendering process ongoing

Chavara AE
Date: 21/01/2025

Work has started | 0% Completed

Tendering process ongoing

Chavara AE
Date: 18/01/2025

Work in progress | 0% Completed

TS approved. Tendering process ongoing

Chavara AE
Date: 15/01/2025

Work has started | 0% Completed

TS approved. Tendering process ongoing

Chavara AE
Date: 13/01/2025

Work has started | 0% Completed

TS approved. Tendering process ongoing