| Chavara AE |
| Date: 06/02/2026 |
Work has been completed | 100% Completed
work completed
| Chavara AE |
| Date: 02/02/2026 |
Work in progress | 85% Completed
Pumpset erection completed.
| Chavara AE |
| Date: 29/01/2026 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway
| Chavara AE |
| Date: 24/01/2026 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway
| Chavara AE |
| Date: 20/01/2026 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway
| Chavara AE |
| Date: 16/01/2026 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway
| Chavara AE |
| Date: 12/01/2026 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway
| Chavara AE |
| Date: 07/01/2026 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway
| Chavara AE |
| Date: 03/01/2026 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway
| Chavara AE |
| Date: 31/12/2025 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway
| Chavara AE |
| Date: 24/12/2025 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway
| Chavara AE |
| Date: 19/12/2025 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway
| Chavara AE |
| Date: 15/12/2025 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway
| Chavara AE |
| Date: 11/12/2025 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.
| Chavara AE |
| Date: 03/12/2025 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.
| Chavara AE |
| Date: 29/11/2025 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.
| Chavara AE |
| Date: 26/11/2025 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.
| Chavara AE |
| Date: 21/11/2025 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.
| Chavara AE |
| Date: 18/11/2025 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.
| Chavara AE |
| Date: 13/11/2025 |
Work in progress | 55% Completed
Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.
| Chavara AE |
| Date: 10/11/2025 |
Work in progress | 55% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.
| Chavara AE |
| Date: 04/11/2025 |
Work in progress | 55% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.
| Chavara AE |
| Date: 30/10/2025 |
Work in progress | 55% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.
| Chavara AE |
| Date: 27/10/2025 |
Work in progress | 55% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.
| Chavara AE |
| Date: 21/10/2025 |
Work in progress | 55% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.
| Chavara AE |
| Date: 16/10/2025 |
Work in progress | 55% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.
| Chavara AE |
| Date: 13/10/2025 |
Work in progress | 55% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.
| Chavara AE |
| Date: 03/10/2025 |
Work in progress | 55% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.
| Chavara AE |
| Date: 29/09/2025 |
Work in progress | 55% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.There is a need for a new pump house and other related works to commission the tubewell at the site where the tubewell construction is currently underway.
| Chavara AE |
| Date: 22/09/2025 |
Work in progress | 55% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.
| Chavara AE |
| Date: 18/09/2025 |
Work in progress | 55% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.
| Chavara AE |
| Date: 15/09/2025 |
Work in progress | 55% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.
| Chavara AE |
| Date: 10/09/2025 |
Work in progress | 55% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.
| Chavara AE |
| Date: 07/09/2025 |
Work in progress | 55% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.
| Chavara AE |
| Date: 01/09/2025 |
Work in progress | 55% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.
| Chavara AE |
| Date: 29/08/2025 |
Work in progress | 55% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Work till tubewell developing completed.
| Chavara AE |
| Date: 19/08/2025 |
Work in progress | 37% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed. Drilling work ongoing.
| Chavara AE |
| Date: 16/08/2025 |
Work in progress | 35% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025. Caisng pipe installation completed.
| Chavara AE |
| Date: 11/08/2025 |
Work in progress | 35% Completed
Drilling of tube well had started in Animal Husbandry Subcentre (Ward 19) on 10.03.2025. Since it failed in the construction phase it has been reported to the Panchayath Authority and Panchayath recommended 1 cent land near Champakkadav for drilling of tubewell. Work statred in new location on 11.08.2025.
| Chavara AE |
| Date: 06/08/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 01/08/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 29/07/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 26/07/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 21/07/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 19/07/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 17/07/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 14/07/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 11/07/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 08/07/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 04/07/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 30/06/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 26/06/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 23/06/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 19/06/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 16/06/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 09/06/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 05/06/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 03/06/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 30/05/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 26/05/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 20/05/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 17/05/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 14/05/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 08/05/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 05/05/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 02/05/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 29/04/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 26/04/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 23/04/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 18/04/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 15/04/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 11/04/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 07/04/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 03/04/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 31/03/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 27/03/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 24/03/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 21/03/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 18/03/2025 |
Work in progress | 35% Completed
Drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed. Plain and slotted uPVC pipe erection completed (41 plain, 9 slotted).
| Chavara AE |
| Date: 15/03/2025 |
Work in progress | 16% Completed
60 m drilling completed. Erection of MS casing pipe (450 mm dia, 18 m length) completed.
| Chavara AE |
| Date: 13/03/2025 |
| Chavara AE |
| Date: 10/03/2025 |
Work has started | 0% Completed
Agreement executed on 11.02.2025
| Chavara AE |
| Date: 05/03/2025 |
Work has started | 0% Completed
Agreement executed on 11.02.2025
| Chavara AE |
| Date: 01/03/2025 |
Work has started | 0% Completed
Agreement executed on 11.02.2025
| Chavara AE |
| Date: 27/02/2025 |
Work has started | 0% Completed
Agreement executed on 11.02.2025
| Chavara AE |
| Date: 23/02/2025 |
Work has started | 0% Completed
Agreement executed on 11.02.2025
| Chavara AE |
| Date: 20/02/2025 |
Work has started | 0% Completed
Agreement executed on 11.02.2025
| Chavara AE |
| Date: 17/02/2025 |
Work has started | 0% Completed
Agreement executed on 11.02.2025
| Chavara AE |
| Date: 14/02/2025 |
Work has started | 0% Completed
Agreement executed on 11.02.2025
| Chavara AE |
| Date: 10/02/2025 |
Work has started | 0% Completed
Tender process ongoing
| Chavara AE |
| Date: 07/02/2025 |
Work has started | 0% Completed
Tender process ongoing
| Chavara AE |
| Date: 04/02/2025 |
Work has started | 0% Completed
Tendering process ongoing
| Chavara AE |
| Date: 02/02/2025 |
Work has started | 0% Completed
Tendering process ongoing
| Chavara AE |
| Date: 30/01/2025 |
Work has started | 0% Completed
Tendering process ongoing
| Chavara AE |
| Date: 27/01/2025 |
Work has started | 0% Completed
Tendering process ongoing
| Chavara AE |
| Date: 24/01/2025 |
Work has started | 0% Completed
Tendering process ongoing
| Chavara AE |
| Date: 21/01/2025 |
Work has started | 0% Completed
Tendering process ongoing
| Chavara AE |
| Date: 18/01/2025 |
Work in progress | 0% Completed
TS approved. Tendering process ongoing
| Chavara AE |
| Date: 15/01/2025 |
Work has started | 0% Completed
TS approved. Tendering process ongoing
| Chavara AE |
| Date: 13/01/2025 |
Work has started | 0% Completed
TS approved. Tendering process ongoing