| Painavu PH Sub Dn AEE |
| Date: 15/10/2022 |
Work has been completed | 100% Completed
completed
| Painavu PH Sub Dn AEE |
| Date: 02/10/2022 |
Work has been completed | 100% Completed
completed
| Painavu PH Sub Dn AEE |
| Date: 20/09/2022 |
Work has been completed | 100% Completed
Completed
| Painavu PH Section AE |
| Date: 06/09/2022 |
Work has been completed | 100% Completed
completed
| Painavu PH Section AE |
| Date: 01/09/2022 |
Work in progress | 98% Completed
road crossing started
| Painavu PH Sub Dn AEE |
| Date: 28/08/2022 |
Work in progress | 95% Completed
road crossing pending
| Painavu PH Section AE |
| Date: 25/08/2022 |
Work in progress | 78% Completed
road crossing pending
| Painavu PH Section AE |
| Date: 22/08/2022 |
Work in progress | 78% Completed
road crossing pending
| Painavu PH Section AE |
| Date: 19/08/2022 |
Work in progress | 78% Completed
road crossing pending
| Painavu PH Section AE |
| Date: 16/08/2022 |
Work in progress | 78% Completed
road crossing pending
| Painavu PH Section AE |
| Date: 10/08/2022 |
Work in progress | 77% Completed
road crossing pending
| Painavu PH Sub Dn AEE |
| Date: 04/08/2022 |
Work in progress | 76% Completed
KSTP new road crossing pending. They said there is a duct near by and that will be located soon
| Painavu PH Section AE |
| Date: 03/08/2022 |
Work in progress | 76% Completed
KSTP new road crossing pending. They said there is a duct near by and that will be located soon
| Painavu PH Sub Dn AEE |
| Date: 01/08/2022 |
Work in progress | 75% Completed
KSTP new road crossing pending. They said there is a duct near by and that will be located soon
| Painavu PH Section AE |
| Date: 27/07/2022 |
Work in progress | 75% Completed
KSTP new road crossing pending. They said there is a duct near by and that will be located soon
| Painavu PH Section AE |
| Date: 22/07/2022 |
Work in progress | 63% Completed
ongoing
| Painavu PH Section AE |
| Date: 19/07/2022 |
Work in progress | 62% Completed
ongoing
| Painavu PH Section AE |
| Date: 15/07/2022 |
Work in progress | 61% Completed
ongoing
| Painavu PH Section AE |
| Date: 12/07/2022 |
Work in progress | 60% Completed
ongoing
| Painavu PH Section AE |
| Date: 08/07/2022 |
Work in progress | 55% Completed
ongoing
| Painavu PH Section AE |
| Date: 05/07/2022 |
Work in progress | 40% Completed
ongoing
| Painavu PH Section AE |
| Date: 02/07/2022 |
Work in progress | 25% Completed
ongoing
| Painavu PH Section AE |
| Date: 28/06/2022 |
Work in progress | 15% Completed
ongoing
| Painavu PH Section AE |
| Date: 23/06/2022 |
Work has started | 0% Completed
pipe supplied
| Painavu PH Section AE |
| Date: 20/06/2022 |
Work has started | 0% Completed
Agreement executed on pipe test procedures
| Painavu PH Section AE |
| Date: 16/06/2022 |
Work has started | 0% Completed
Agreement executed on pipe test procedures
| Painavu PH Section AE |
| Date: 13/06/2022 |
Work has started | 0% Completed
Agreement executed on pipe test procedures
| Painavu PH Section AE |
| Date: 07/06/2022 |
Work has started | 0% Completed
Agreement executed on pipe test procedures
| Painavu PH Section AE |
| Date: 04/06/2022 |
Work has started | 0% Completed
Agreement executed on pipe test procedures
| Thodupuzha PH Dn EE |
| Date: 31/05/2022 |
Work has started | 0% Completed
Agreement executed on pipe test procedures
| Painavu PH Section AE |
| Date: 28/05/2022 |
Work has started | 0% Completed
Agreement execute
| Thodupuzha PH Dn EE |
| Date: 23/05/2022 |
Work has started | 0% Completed
Agreement executed
| Painavu PH Section AE |
| Date: 19/05/2022 |
Work has started | 0% Completed
Agreement executed
| Painavu PH Section AE |
| Date: 16/05/2022 |
Work has started | 0% Completed
Agreement executed
| Painavu PH Section AE |
| Date: 11/05/2022 |
Work has started | 0% Completed
Agreement executed
| Painavu PH Section AE |
| Date: 05/05/2022 |
Work has started | 0% Completed
Agreement executed
| Painavu PH Section AE |
| Date: 30/04/2022 |
Work has started | 0% Completed
Agreement executed
| Painavu PH Section AE |
| Date: 26/04/2022 |
Work has started | 0% Completed
Agreement executed
| Painavu PH Section AE |
| Date: 22/04/2022 |
Work has started | 0% Completed
agreement executed Agreement No-01/22-23/AEE/KWA/PHSDN/PNV dtd.12/04/2022
| Painavu PH Section AE |
| Date: 18/04/2022 |
Work has started | 0% Completed
work order issued
| Painavu PH Section AE |
| Date: 12/04/2022 |
Work has started | 0% Completed
work order issued
| Painavu PH Section AE |
| Date: 08/04/2022 |
Work has started | 0% Completed
work order issued
| Painavu PH Section AE |
| Date: 04/04/2022 |
| Painavu PH Sub Dn AEE |
| Date: 28/03/2022 |
Work has started | 0% Completed
Not started. Work tendered.
| Painavu PH Section AE |
| Date: 26/03/2022 |
Work has started | 0% Completed
work tendered
| Thodupuzha PH Dn EE |
| Date: 25/03/2022 |
Work has started | 0% Completed
work handed over to PH sub division Painavu to Tender and arrange the work