| Thalassery PH Sn AE |
| Date: 28/09/2026 |
Work in progress | 30% Completed
3rd brace concrete completed
| Thalassery PH Sn AE |
| Date: 08/07/2026 |
| Thalassery PH Sn AE |
| Date: 17/06/2026 |
Work in progress | 15% Completed
plinth beam concrete on progress
| Thalassery PH Sn AE |
| Date: 04/06/2026 |
Work in progress | 15% Completed
steel work for plinth beam on progress
| Kannur PH Dn EE |
| Date: 29/04/2026 |
Work in progress | 15% Completed
Pedestal column concrete completed, back filling first stage on progress
| Thalassery PH Sn AE |
| Date: 18/04/2026 |
| Thalassery PH Sn AE |
| Date: 10/04/2026 |
| Thalassery PH Sn AE |
| Date: 30/03/2026 |
| Thalassery PH Sn AE |
| Date: 23/03/2026 |
| Thalassery PH Sn AE |
| Date: 03/03/2026 |
Work in progress | 1% Completed
Work started site clearing, marking on progress
| Thalassery PH Sn AE |
| Date: 23/02/2026 |
| Thalassery PH Sn AE |
| Date: 18/02/2026 |
Work has started | 0% Completed
Agreement executed
| Thalassery PH Sn AE |
| Date: 09/02/2026 |
Work has started | 0% Completed
Agreement executed
| Thalassery PH Sn AE |
| Date: 29/01/2026 |
Work has started | 0% Completed
Agreement executed
| Thalassery PH Sn AE |
| Date: 19/01/2026 |
Work has started | 0% Completed
Agreement executed
| Thalassery PH Sn AE |
| Date: 08/01/2026 |
Work has started | 0% Completed
Agreement executed
| Thalassery PH Sn AE |
| Date: 05/01/2026 |
Work has started | 0% Completed
Agreement executed
| Thalassery PH Sn AE |
| Date: 24/12/2025 |
Work has started | 0% Completed
Agreement executed
| Thalassery PH Sn AE |
| Date: 17/12/2025 |
Work has started | 0% Completed
Agreement executed
| Thalassery PH Sn AE |
| Date: 12/12/2025 |
Work has started | 0% Completed
Agreement executed
| Thalassery PH Sn AE |
| Date: 01/12/2025 |
Work has started | 0% Completed
Agreement executed
| Thalassery PH Sn AE |
| Date: 20/11/2025 |
Work has started | 0% Completed
Agreement executed
| Thalassery PH Sn AE |
| Date: 07/11/2025 |
Work has started | 0% Completed
LoA issued
| Thalassery PH Sn AE |
| Date: 22/10/2025 |
Work has started | 0% Completed
LoA issued
| Thalassery PH Sn AE |
| Date: 16/10/2025 |
Work has started | 0% Completed
LoA issued
| Thalassery PH Sn AE |
| Date: 29/09/2025 |
Work has started | 0% Completed
LoA issued
| Thalassery PH Sn AE |
| Date: 18/09/2025 |
Work has started | 0% Completed
LoA issued
| Thalassery PH Sn AE |
| Date: 09/09/2025 |
Work has started | 0% Completed
LoA issued
| Thalassery PH Sn AE |
| Date: 30/08/2025 |
Work has started | 0% Completed
LoA issued
| Thalassery PH Sn AE |
| Date: 25/08/2025 |
Work has started | 0% Completed
LoA issued
| Thalassery PH Sn AE |
| Date: 19/08/2025 |
Work has started | 0% Completed
LoA issued
| Thalassery PH Sn AE |
| Date: 09/08/2025 |
Work has started | 0% Completed
LoA issued
| Kannur PH Dn EE |
| Date: 05/08/2025 |
Work has started | 0% Completed
LoA issued
| Thalassery PH Sn AE |
| Date: 30/07/2025 |
Work has started | 0% Completed
T S issued
| Thalassery PH Sn AE |
| Date: 16/07/2025 |
Work has started | 0% Completed
T S issued
| Thalassery PH Sn AE |
| Date: 30/06/2025 |
Work has started | 0% Completed
T S issued
| Thalassery PH Sn AE |
| Date: 27/06/2025 |
Work has started | 0% Completed
T S issued
| Thalassery PH Sn AE |
| Date: 17/06/2025 |
Work has started | 0% Completed
T S issued
| Thalassery PH Sn AE |
| Date: 03/06/2025 |
Work has started | 0% Completed
T S issued
| Thalassery PH Sn AE |
| Date: 19/05/2025 |
Work has started | 0% Completed
T S issued
| Thalassery PH Sn AE |
| Date: 10/05/2025 |
Work has started | 0% Completed
T S issued
| Thalassery PH Sn AE |
| Date: 01/05/2025 |
Work has started | 0% Completed
T S issued
| Thalassery PH Sn AE |
| Date: 15/04/2025 |
Work has started | 0% Completed
T S issued
| Thalassery PH Sn AE |
| Date: 03/04/2025 |
Work has started | 0% Completed
T S issued
| Thalassery PH Sn AE |
| Date: 22/03/2025 |
Work has started | 0% Completed
T S issued
| Thalassery PH Sn AE |
| Date: 17/03/2025 |
Work has started | 0% Completed
T S issued
| Thalassery PH Sn AE |
| Date: 03/03/2025 |
Work has started | 0% Completed
T S issued
| Kannur PH Dn EE |
| Date: 27/02/2025 |
Work has started | 0% Completed
T S issued
| Thalassery PH Sn AE |
| Date: 22/02/2025 |
Work has started | 0% Completed
Estimate Submitted for TS
| Thalassery PH Sn AE |
| Date: 11/02/2025 |
Work has started | 0% Completed
Estimate Submitted for TS
| Thalassery PH Sn AE |
| Date: 01/02/2025 |
Work has started | 0% Completed
Estimate Submitted for TS
| Thalassery PH Sn AE |
| Date: 28/01/2025 |
Work has started | 0% Completed
Estimate Submitted for TS
| Thalassery PH Sn AE |
| Date: 21/01/2025 |
Work has started | 0% Completed
Estimate Submitted for TS
| Thalassery PH Sn AE |
| Date: 13/01/2025 |
Work has started | 0% Completed
Estimate Submitted for TS
| Thalassery PH Sn AE |
| Date: 03/01/2025 |
Work has started | 0% Completed
Estimate Submitted for TS
| Thalassery PH Sn AE |
| Date: 01/01/2025 |
Work has started | 0% Completed
Estimate Submitted for TS
| Thalassery PH Sn AE |
| Date: 18/12/2024 |
Work has started | 0% Completed
Estimate Submitted for TS
| Kannur PH Dn EE |
| Date: 19/11/2024 |
Work has started | 0% Completed
Estimate under scrutiny at Circle office
| Kannur PH Dn EE |
| Date: 04/11/2024 |
Work has started | 0% Completed
AS Accorded on 23-10-2024.