| Thalassery PH Sn AE |
| Date: 13/07/2022 |
Work has been completed | 100% Completed
Work completed & Final bill submited
| Thalassery PH Sn AE |
| Date: 06/05/2022 |
Work in progress | 88% Completed
3720 FHTC GIVEN &28.3 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 10/03/2022 |
Work in progress | 84% Completed
3579 FHTC GIVEN &27 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 02/03/2022 |
Work in progress | 84% Completed
3579 FHTC GIVEN &27 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 03/02/2022 |
Work in progress | 84% Completed
3579 FHTC GIVEN &27 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 29/01/2022 |
Work in progress | 84% Completed
3537 FHTC GIVEN &27 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 27/01/2022 |
Work in progress | 84% Completed
3537 FHTC GIVEN &27 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 21/01/2022 |
Work in progress | 70% Completed
3433 FHTC GIVEN & 27 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 13/01/2022 |
Work in progress | 70% Completed
3433 FHTC GIVEN & 27 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 04/01/2022 |
Work in progress | 70% Completed
3433 FHTC GIVEN & 27 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 29/12/2021 |
Work in progress | 70% Completed
3390 FHTC GIVEN & 27 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 25/12/2021 |
Work in progress | 70% Completed
3390 FHTC GIVEN & 27 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 15/12/2021 |
Work in progress | 70% Completed
3390 FHTC GIVEN & 27 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 07/12/2021 |
Work in progress | 70% Completed
3390 FHTC GIVEN & 27 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 29/11/2021 |
Work in progress | 70% Completed
3390 FHTC GIVEN & 27 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 23/11/2021 |
Work in progress | 70% Completed
3390 FHTC GIVEN & 27 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 18/11/2021 |
Work in progress | 70% Completed
3390 FHTC GIVEN & 27 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 10/11/2021 |
Work in progress | 70% Completed
3265 FHTC GIVEN &26 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 02/11/2021 |
Work in progress | 70% Completed
3265 FHTC GIVEN &26 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 27/10/2021 |
Work in progress | 70% Completed
3265 FHTC GIVEN &26 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 18/10/2021 |
Work in progress | 70% Completed
3218 FHTC GIVEN &26 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 13/10/2021 |
Work in progress | 70% Completed
3218 FHTC GIVEN &26 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 06/10/2021 |
Work in progress | 70% Completed
3218 FHTC GIVEN &26 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 29/09/2021 |
Work in progress | 70% Completed
3218 FHTC GIVEN &26 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 21/09/2021 |
Work in progress | 70% Completed
3079 FHTC GIVEN &26 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 14/09/2021 |
Work in progress | 70% Completed
3079 FHTC GIVEN &26 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 07/09/2021 |
Work in progress | 70% Completed
3067 FHTC GIVEN &25 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 01/09/2021 |
Work in progress | 70% Completed
2928 FHTC GIVEN &25 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 24/08/2021 |
Work in progress | 70% Completed
2928 FHTC GIVEN &25 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 17/08/2021 |
Work in progress | 70% Completed
2770 FHTC GIVEN &25 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 11/08/2021 |
Work in progress | 70% Completed
2770 FHTC GIVEN &25 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 06/08/2021 |
Work in progress | 70% Completed
2770 FHTC GIVEN &25 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 02/08/2021 |
Work in progress | 70% Completed
2670 FHTC GIVEN &25 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 26/07/2021 |
Work in progress | 70% Completed
2670 FHTC GIVEN & 25 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 20/07/2021 |
Work in progress | 67% Completed
2588 FHTC GIVEN & 25 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 15/07/2021 |
Work in progress | 67% Completed
2588 FHTC GIVEN & 25 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 11/07/2021 |
Work in progress | 67% Completed
2588 FHTC GIVEN & 25 km PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 06/07/2021 |
Work in progress | 65% Completed
65 % completed. 2583 FHTC GIVEN & 24 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 02/07/2021 |
Work in progress | 64% Completed
2568 FHTC provided and 24 km pipe line laid
| Thalassery PH Sn AE |
| Date: 01/07/2021 |
Work in progress | 64% Completed
2544 FHTC GIVEN AND 24 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 15/06/2021 |
Work in progress | 60% Completed
2467 FHTCS GIVEN AND 24 KM PIPE LINE LAID .
| Thalassery PH Sn AE |
| Date: 22/04/2021 |
Work in progress | 46% Completed
2065 FHTCS GIVEN AND 21 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 31/03/2021 |
Work in progress | 40% Completed
1829 fhtcs given and 20 KM pipe line laid
| Thalassery PH Sn AE |
| Date: 10/03/2021 |
Work in progress | 38% Completed
1580 FHTCS GIVEN & 17 KM PIPE LINE LAID
| Thalassery PH Sn AE |
| Date: 24/02/2021 |
Work in progress | 35% Completed
1524 connections completed and 15 KM pipe line laid
| Thalassery PH Sn AE |
| Date: 13/02/2021 |
Work in progress | 33% Completed
33% Completed. 1508 connections given. 10 km pipe line extension completed
| Thalassery PH Sn AE |
| Date: 02/02/2021 |
Work in progress | 30% Completed
1380 connections given . 8 Km pipe line extension completed
| Thalassery PH Sn AE |
| Date: 26/01/2021 |
Work in progress | 25% Completed
1280 connections given
| Thalassery PH Sn AE |
| Date: 27/11/2020 |
Work in progress | 10% Completed
435 connections given