Painavu PH Section AE
Date: 17/10/2023

Work has been completed | 100% Completed

Work Completed

Painavu PH Section AE
Date: 10/10/2023

Work in progress | 73% Completed

KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath

Painavu PH Section AE
Date: 03/10/2023

Work in progress | 73% Completed

KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath

Painavu PH Section AE
Date: 27/09/2023

Work in progress | 73% Completed

KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath

Painavu PH Section AE
Date: 20/09/2023

Work in progress | 73% Completed

KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath

Painavu PH Section AE
Date: 18/09/2023

Work in progress | 73% Completed

KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath

Painavu PH Section AE
Date: 11/09/2023

Work in progress | 73% Completed

KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath

Painavu PH Section AE
Date: 05/09/2023

Work in progress | 73% Completed

KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath

Painavu PH Section AE
Date: 01/09/2023

Work in progress | 73% Completed

KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath

Painavu PH Section AE
Date: 21/08/2023

Work in progress | 73% Completed

Since the permission of road cutting from KSTP is having an indefinite delay, Concerned ward member has requested to lay the pipes in an alternate route. Had a joint inspection with Panchayath officials on 12/07/23 in the alternate route

Painavu PH Section AE
Date: 16/08/2023

Work in progress | 73% Completed

Since the permission of road cutting from KSTP is having an indefinite delay, Concerned ward member has requested to lay the pipes in an alternate route. Had a joint inspection with Panchayath officials on 12/07/23 in the alternate route

Painavu PH Section AE
Date: 09/08/2023

Work in progress | 73% Completed

Since the permission of road cutting from KSTP is having an indefinite delay, Concerned ward member has requested to lay the pipes in an alternate route. Had a joint inspection with Panchayath officials on 12/07/23 in the alternate route

Painavu PH Section AE
Date: 04/08/2023

Work in progress | 73% Completed

Since the permission of road cutting from KSTP is having an indefinite delay, Concerned ward member has requested to lay the pipes in an alternate route. Had a joint inspection with Panchayath officials on 12/07/23 in the alternate route

Painavu PH Section AE
Date: 31/07/2023

Work in progress | 73% Completed

Since the permission of road cutting from KSTP is having an indefinite delay, Concerned ward member has requested to lay the pipes in an alternate route. Had a joint inspection with Panchayath officials on 12/07/23 in the alternate route

Painavu PH Section AE
Date: 25/07/2023

Work in progress | 73% Completed

Since the permission of road cutting from KSTP is having an indefinite delay, Concerned ward member has requested to lay the pipes in an alternate route. Had a joint inspection with Panchayath officials on 12/07/23 in the alternate route

Painavu PH Section AE
Date: 19/07/2023

Work in progress | 73% Completed

Since the permission of road cutting from KSTP is having an indefinite delay, Concerned ward member has requested to lay the pipes in an alternate route. Had a joint inspection with Panchayath officials on 12/07/23 in the alternate route

Painavu PH Section AE
Date: 13/07/2023

Work in progress | 73% Completed

Since the permission of road cutting from KSTP is having an indefinite delay, Concerned ward member has requested to lay the pipes in an alternate route. Had a joint inspection with Panchayath officials on 12/07/23 in the alternate route

Painavu PH Section AE
Date: 04/07/2023

Work in progress | 73% Completed

Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work.

Painavu PH Section AE
Date: 29/06/2023

Work in progress | 73% Completed

Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work.

Painavu PH Section AE
Date: 24/06/2023

Work in progress | 73% Completed

Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work.

Painavu PH Section AE
Date: 20/06/2023

Work in progress | 73% Completed

Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work.

Painavu PH Section AE
Date: 15/06/2023

Work in progress | 73% Completed

Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work.

Painavu PH Section AE
Date: 12/06/2023

Work in progress | 73% Completed

Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work.

Painavu PH Section AE
Date: 07/06/2023

Work in progress | 73% Completed

Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work.

Painavu PH Section AE
Date: 04/06/2023

Work in progress | 73% Completed

Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work

Painavu PH Section AE
Date: 29/05/2023

Work in progress | 73% Completed

Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work

Painavu PH Section AE
Date: 24/05/2023

Work in progress | 73% Completed

RoW Application for laying of Pipes in Progress

Painavu PH Section AE
Date: 17/05/2023

Work in progress | 73% Completed

Row Application for laying of Pipes in Progress

Painavu PH Section AE
Date: 10/05/2023

Work in progress | 73% Completed

KSTP Officials informed that they could not give permission for concrete cutting since the road is under DLP Period

Painavu PH Section AE
Date: 05/05/2023

Work in progress | 73% Completed

KSTP Officials informed that they could not give permission for concrete cutting since the road is under DLP Period

Painavu PH Section AE
Date: 28/04/2023

Work in progress | 73% Completed

KSTP Officials informed that they could not give permission for concrete cutting since the road is under DLP Period

Painavu PH Section AE
Date: 18/04/2023

Work in progress | 73% Completed

KSTP Officials informed that they could not give permission for concrete cutting since the road is under DLP Period

Painavu PH Section AE
Date: 10/04/2023

Work in progress | 73% Completed

KSTP Officials informed that they could not give permission for concrete cutting since the road is under DLP Period

Painavu PH Section AE
Date: 28/03/2023

Work in progress | 73% Completed

Had a joint inspection with KSTP Officials on 22/03/23. They informed that, sanction details will be intimated after discussing with their higher officials

Painavu PH Section AE
Date: 23/03/2023

Work in progress | 73% Completed

Had a joint inspection with KSTP Officials on 22/03/23. They informed that, sanction details will be intimated after discussing with their higher officials

Painavu PH Section AE
Date: 16/03/2023

Work in progress | 73% Completed

KSTP Road Irish cutting sanction needed. Sanction availing procedures are going on

Painavu PH Section AE
Date: 08/03/2023

Work in progress | 73% Completed

KSTP Road Irish cutting sanction needed. Sanction availing procedures are going on

Painavu PH Section AE
Date: 27/02/2023

Work in progress | 73% Completed

KSTP Road Irish cutting sanction needed. Sanction availing procedures are going on

Painavu PH Section AE
Date: 21/02/2023

Work in progress | 73% Completed

KSTP Road Irish cutting sanction needed. Sanction availing procedures are going on

Painavu PH Section AE
Date: 14/02/2023

Work in progress | 73% Completed

KSTP Road Irish cutting sanction needed. Sanction availing procedures are going on

Painavu PH Section AE
Date: 06/02/2023

Work in progress | 73% Completed

KSTP Road Irish cutting sanction needed. Sanction availing procedures are going on

Painavu PH Section AE
Date: 27/01/2023

Work in progress | 73% Completed

Pipe Laying work is going on

Painavu PH Section AE
Date: 20/01/2023

Work in progress | 69% Completed

Pipe Laying works in progress

Painavu PH Section AE
Date: 10/01/2023

Work in progress | 66% Completed

Pipe laying work is going on

Painavu PH Section AE
Date: 04/01/2023

Work in progress | 64% Completed

Pipe laying work is going on

Painavu PH Section AE
Date: 26/12/2022

Work in progress | 61% Completed

Pipe Laying Works in Progress

Painavu PH Section AE
Date: 19/12/2022

Work in progress | 57% Completed

Pipe Laying in Progress

Painavu PH Section AE
Date: 13/12/2022

Work in progress | 55% Completed

Pipe Laying in Progress

Painavu PH Section AE
Date: 08/12/2022

Work in progress | 53% Completed

Work in progress

Painavu PH Section AE
Date: 03/12/2022

Work in progress | 48% Completed

Work in progress

Painavu PH Section AE
Date: 29/11/2022

Work in progress | 45% Completed

Work on going

Painavu PH Section AE
Date: 24/11/2022

Work in progress | 30% Completed

Work on going

Painavu PH Section AE
Date: 16/11/2022

Work in progress | 20% Completed

Pipe supply done, work started

Painavu PH Sub Dn AEE
Date: 06/11/2022

Work has started | 0% Completed

pipe supplied ,not started

Painavu PH Sub Dn AEE
Date: 15/10/2022

Work has started | 0% Completed

pipe tested

Painavu PH Section AE
Date: 03/10/2022

Work in progress | 0% Completed

pipe supply order placed in the firm

Painavu PH Sub Dn AEE
Date: 02/10/2022

Work has started | 0% Completed

pipe supply order placed in the firm

Painavu PH Sub Dn AEE
Date: 20/09/2022

Work has started | 0% Completed

Agreement executed

Painavu PH Section AE
Date: 17/09/2022

Work has started | 0% Completed

work order issued

Painavu PH Section AE
Date: 13/09/2022

Work has started | 0% Completed

work order issued

Painavu PH Section AE
Date: 01/09/2022

Work has started | 0% Completed

work order issued

Thodupuzha PH Dn EE
Date: 27/08/2022

Work has started | 0% Completed

Work Order Issued