| Painavu PH Section AE |
| Date: 17/10/2023 |
Work has been completed | 100% Completed
Work Completed
| Painavu PH Section AE |
| Date: 10/10/2023 |
Work in progress | 73% Completed
KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath
| Painavu PH Section AE |
| Date: 03/10/2023 |
Work in progress | 73% Completed
KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath
| Painavu PH Section AE |
| Date: 27/09/2023 |
Work in progress | 73% Completed
KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath
| Painavu PH Section AE |
| Date: 20/09/2023 |
Work in progress | 73% Completed
KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath
| Painavu PH Section AE |
| Date: 18/09/2023 |
Work in progress | 73% Completed
KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath
| Painavu PH Section AE |
| Date: 11/09/2023 |
Work in progress | 73% Completed
KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath
| Painavu PH Section AE |
| Date: 05/09/2023 |
Work in progress | 73% Completed
KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath
| Painavu PH Section AE |
| Date: 01/09/2023 |
Work in progress | 73% Completed
KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath
| Painavu PH Section AE |
| Date: 21/08/2023 |
Work in progress | 73% Completed
Since the permission of road cutting from KSTP is having an indefinite delay, Concerned ward member has requested to lay the pipes in an alternate route. Had a joint inspection with Panchayath officials on 12/07/23 in the alternate route
| Painavu PH Section AE |
| Date: 16/08/2023 |
Work in progress | 73% Completed
Since the permission of road cutting from KSTP is having an indefinite delay, Concerned ward member has requested to lay the pipes in an alternate route. Had a joint inspection with Panchayath officials on 12/07/23 in the alternate route
| Painavu PH Section AE |
| Date: 09/08/2023 |
Work in progress | 73% Completed
Since the permission of road cutting from KSTP is having an indefinite delay, Concerned ward member has requested to lay the pipes in an alternate route. Had a joint inspection with Panchayath officials on 12/07/23 in the alternate route
| Painavu PH Section AE |
| Date: 04/08/2023 |
Work in progress | 73% Completed
Since the permission of road cutting from KSTP is having an indefinite delay, Concerned ward member has requested to lay the pipes in an alternate route. Had a joint inspection with Panchayath officials on 12/07/23 in the alternate route
| Painavu PH Section AE |
| Date: 31/07/2023 |
Work in progress | 73% Completed
Since the permission of road cutting from KSTP is having an indefinite delay, Concerned ward member has requested to lay the pipes in an alternate route. Had a joint inspection with Panchayath officials on 12/07/23 in the alternate route
| Painavu PH Section AE |
| Date: 25/07/2023 |
Work in progress | 73% Completed
Since the permission of road cutting from KSTP is having an indefinite delay, Concerned ward member has requested to lay the pipes in an alternate route. Had a joint inspection with Panchayath officials on 12/07/23 in the alternate route
| Painavu PH Section AE |
| Date: 19/07/2023 |
Work in progress | 73% Completed
Since the permission of road cutting from KSTP is having an indefinite delay, Concerned ward member has requested to lay the pipes in an alternate route. Had a joint inspection with Panchayath officials on 12/07/23 in the alternate route
| Painavu PH Section AE |
| Date: 13/07/2023 |
Work in progress | 73% Completed
Since the permission of road cutting from KSTP is having an indefinite delay, Concerned ward member has requested to lay the pipes in an alternate route. Had a joint inspection with Panchayath officials on 12/07/23 in the alternate route
| Painavu PH Section AE |
| Date: 04/07/2023 |
Work in progress | 73% Completed
Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work.
| Painavu PH Section AE |
| Date: 29/06/2023 |
Work in progress | 73% Completed
Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work.
| Painavu PH Section AE |
| Date: 24/06/2023 |
Work in progress | 73% Completed
Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work.
| Painavu PH Section AE |
| Date: 20/06/2023 |
Work in progress | 73% Completed
Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work.
| Painavu PH Section AE |
| Date: 15/06/2023 |
Work in progress | 73% Completed
Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work.
| Painavu PH Section AE |
| Date: 12/06/2023 |
Work in progress | 73% Completed
Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work.
| Painavu PH Section AE |
| Date: 07/06/2023 |
Work in progress | 73% Completed
Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work.
| Painavu PH Section AE |
| Date: 04/06/2023 |
Work in progress | 73% Completed
Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work
| Painavu PH Section AE |
| Date: 29/05/2023 |
Work in progress | 73% Completed
Since road restoration amount is not included in the Work Estimate, RoW Application is processed along with the Ongoing JJM Vazhathope Work
| Painavu PH Section AE |
| Date: 24/05/2023 |
Work in progress | 73% Completed
RoW Application for laying of Pipes in Progress
| Painavu PH Section AE |
| Date: 17/05/2023 |
Work in progress | 73% Completed
Row Application for laying of Pipes in Progress
| Painavu PH Section AE |
| Date: 10/05/2023 |
Work in progress | 73% Completed
KSTP Officials informed that they could not give permission for concrete cutting since the road is under DLP Period
| Painavu PH Section AE |
| Date: 05/05/2023 |
Work in progress | 73% Completed
KSTP Officials informed that they could not give permission for concrete cutting since the road is under DLP Period
| Painavu PH Section AE |
| Date: 28/04/2023 |
Work in progress | 73% Completed
KSTP Officials informed that they could not give permission for concrete cutting since the road is under DLP Period
| Painavu PH Section AE |
| Date: 18/04/2023 |
Work in progress | 73% Completed
KSTP Officials informed that they could not give permission for concrete cutting since the road is under DLP Period
| Painavu PH Section AE |
| Date: 10/04/2023 |
Work in progress | 73% Completed
KSTP Officials informed that they could not give permission for concrete cutting since the road is under DLP Period
| Painavu PH Section AE |
| Date: 28/03/2023 |
Work in progress | 73% Completed
Had a joint inspection with KSTP Officials on 22/03/23. They informed that, sanction details will be intimated after discussing with their higher officials
| Painavu PH Section AE |
| Date: 23/03/2023 |
Work in progress | 73% Completed
Had a joint inspection with KSTP Officials on 22/03/23. They informed that, sanction details will be intimated after discussing with their higher officials
| Painavu PH Section AE |
| Date: 16/03/2023 |
Work in progress | 73% Completed
KSTP Road Irish cutting sanction needed. Sanction availing procedures are going on
| Painavu PH Section AE |
| Date: 08/03/2023 |
Work in progress | 73% Completed
KSTP Road Irish cutting sanction needed. Sanction availing procedures are going on
| Painavu PH Section AE |
| Date: 27/02/2023 |
Work in progress | 73% Completed
KSTP Road Irish cutting sanction needed. Sanction availing procedures are going on
| Painavu PH Section AE |
| Date: 21/02/2023 |
Work in progress | 73% Completed
KSTP Road Irish cutting sanction needed. Sanction availing procedures are going on
| Painavu PH Section AE |
| Date: 14/02/2023 |
Work in progress | 73% Completed
KSTP Road Irish cutting sanction needed. Sanction availing procedures are going on
| Painavu PH Section AE |
| Date: 06/02/2023 |
Work in progress | 73% Completed
KSTP Road Irish cutting sanction needed. Sanction availing procedures are going on
| Painavu PH Section AE |
| Date: 27/01/2023 |
Work in progress | 73% Completed
Pipe Laying work is going on
| Painavu PH Section AE |
| Date: 20/01/2023 |
Work in progress | 69% Completed
Pipe Laying works in progress
| Painavu PH Section AE |
| Date: 10/01/2023 |
Work in progress | 66% Completed
Pipe laying work is going on
| Painavu PH Section AE |
| Date: 04/01/2023 |
Work in progress | 64% Completed
Pipe laying work is going on
| Painavu PH Section AE |
| Date: 26/12/2022 |
Work in progress | 61% Completed
Pipe Laying Works in Progress
| Painavu PH Section AE |
| Date: 19/12/2022 |
Work in progress | 57% Completed
Pipe Laying in Progress
| Painavu PH Section AE |
| Date: 13/12/2022 |
Work in progress | 55% Completed
Pipe Laying in Progress
| Painavu PH Section AE |
| Date: 08/12/2022 |
Work in progress | 53% Completed
Work in progress
| Painavu PH Section AE |
| Date: 03/12/2022 |
Work in progress | 48% Completed
Work in progress
| Painavu PH Section AE |
| Date: 29/11/2022 |
Work in progress | 45% Completed
Work on going
| Painavu PH Section AE |
| Date: 24/11/2022 |
Work in progress | 30% Completed
Work on going
| Painavu PH Section AE |
| Date: 16/11/2022 |
Work in progress | 20% Completed
Pipe supply done, work started
| Painavu PH Sub Dn AEE |
| Date: 06/11/2022 |
Work has started | 0% Completed
pipe supplied ,not started
| Painavu PH Sub Dn AEE |
| Date: 15/10/2022 |
Work has started | 0% Completed
pipe tested
| Painavu PH Section AE |
| Date: 03/10/2022 |
Work in progress | 0% Completed
pipe supply order placed in the firm
| Painavu PH Sub Dn AEE |
| Date: 02/10/2022 |
Work has started | 0% Completed
pipe supply order placed in the firm
| Painavu PH Sub Dn AEE |
| Date: 20/09/2022 |
Work has started | 0% Completed
Agreement executed
| Painavu PH Section AE |
| Date: 17/09/2022 |
Work has started | 0% Completed
work order issued
| Painavu PH Section AE |
| Date: 13/09/2022 |
Work has started | 0% Completed
work order issued
| Painavu PH Section AE |
| Date: 01/09/2022 |
Work has started | 0% Completed
work order issued
| Thodupuzha PH Dn EE |
| Date: 27/08/2022 |
Work has started | 0% Completed
Work Order Issued