Thaliparamba WS Section |
Date: 08/08/2023 |
Work has been completed | 100% Completed
100% Completed
Thaliparamba WS Section |
Date: 05/08/2023 |
Work has been completed | 100% Completed
100% Completed
Thaliparamba WS Section |
Date: 03/08/2023 |
Work has been completed | 100% Completed
100% Completed
Thaliparamba WS Dn EE |
Date: 31/07/2023 |
Work has been completed | 100% Completed
100% Completed
Thaliparamba WS Section |
Date: 05/07/2023 |
Work has been completed | 100% Completed
100% Completed
Thaliparamba WS Section |
Date: 29/06/2023 |
Work has been completed | 100% Completed
Work has been completed
Thaliparamba WS Dn EE |
Date: 14/06/2023 |
Work has been completed | 100% Completed
100% Completed
Thaliparamba WS Dn EE |
Date: 08/06/2023 |
Work has been completed | 100% Completed
100% completed and payment done
Thaliparamba WS Dn EE |
Date: 24/05/2023 |
Work has been completed | 100% Completed
100% completed and payment done
Thaliparamba WS Section |
Date: 09/06/2022 |
Work has been completed | 100% Completed
final bill submitted
Thaliparamba WS Section |
Date: 02/06/2022 |
Work has been completed | 100% Completed
work completed,
Thaliparamba WS Section |
Date: 27/05/2022 |
Work in progress | 91% Completed
250 FHTCS COMPLETED
Thaliparamba WS Section |
Date: 18/05/2022 |
Work in progress | 85% Completed
250 FHTCS COMPLETED
Thaliparamba WS Section |
Date: 10/05/2022 |
Work in progress | 85% Completed
250 FHTCS COMPLETED
Thaliparamba WS Section |
Date: 06/05/2022 |
Work in progress | 83% Completed
245 FHTCS COMPLETED
Thaliparamba WS Section |
Date: 03/05/2022 |
Work in progress | 83% Completed
245 FHTCS COMPLETED
Thaliparamba WS Section |
Date: 27/04/2022 |
Work in progress | 82% Completed
235 FHTCS COMPLETED
Thaliparamba WS Section |
Date: 18/04/2022 |
Work in progress | 82% Completed
235 FHTCS COMPLETED
Thaliparamba WS Section |
Date: 13/04/2022 |
Work in progress | 82% Completed
235 FHTCS COMPLETED
Thaliparamba WS Section |
Date: 06/04/2022 |
Work in progress | 82% Completed
230 FHTCS COMPLETED
Thaliparamba WS Dn EE |
Date: 25/03/2022 |
Work in progress | 82% Completed
230 FHTCS COMPLETED
Thaliparamba WS Dn EE |
Date: 21/03/2022 |
Work in progress | 82% Completed
230 FHTCS COMPLETED
Thaliparamba WS Section |
Date: 15/03/2022 |
Work in progress | 72% Completed
230 FHTCS COMPLETED
Thaliparamba WS Section |
Date: 08/03/2022 |
Work in progress | 72% Completed
220 FHTCS COMPLETED
Thaliparamba WS Dn EE |
Date: 02/03/2022 |
Work in progress | 72% Completed
220 FHTCS COMPLETED
Thaliparamba WS Section |
Date: 22/02/2022 |
Work in progress | 72% Completed
220 FHTCS COMPLETED
Thaliparamba WS Section |
Date: 14/02/2022 |
Work in progress | 71% Completed
220 FHTCS COMPLETED
Thaliparamba WS Section |
Date: 11/02/2022 |
Work in progress | 71% Completed
220 FHTCS COMPLETED
Thaliparamba WS Section |
Date: 09/02/2022 |
Work in progress | 71% Completed
220 FHTCS COMPLETED
Thaliparamba WS Dn EE |
Date: 04/02/2022 |
Work in progress | 71% Completed
220 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 01/02/2022 |
Work in progress | 71% Completed
210 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 25/01/2022 |
Work in progress | 64% Completed
PIPPE LAYING WORK ALMOST COMPLETED
Thaliparamba WS Dn EE |
Date: 21/01/2022 |
Work in progress | 64% Completed
PIPPE LAYING WORK ALMOST COMPLETED
Thaliparamba WS Dn EE |
Date: 18/01/2022 |
Work in progress | 63% Completed
PIPPE LAYING WORK ALMOST COMPLETED
Thaliparamba WS Dn EE |
Date: 13/01/2022 |
Work in progress | 60% Completed
PIPPE LAYING WORK ALMOST COMPLETED
Thaliparamba WS Dn EE |
Date: 09/01/2022 |
Work in progress | 59% Completed
PIPPE LAYING WORK ALMOST COMPLETED
Thaliparamba WS Dn EE |
Date: 03/01/2022 |
Work in progress | 58% Completed
PIPPE LAYING WORK ALMOST COMPLETED
Thaliparamba WS Dn EE |
Date: 30/12/2021 |
Work in progress | 58% Completed
PIPE LAYING WORK ALMOST COMPLETED
Thaliparamba WS Dn EE |
Date: 26/12/2021 |
Work in progress | 55% Completed
PIPE LAYING WORK ALMOST COMPLETED
Thaliparamba WS Dn EE |
Date: 20/12/2021 |
Work in progress | 51% Completed
170 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 19/12/2021 |
Work in progress | 39% Completed
165 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 18/12/2021 |
Work in progress | 29% Completed
155 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 17/12/2021 |
Work in progress | 20% Completed
133 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 12/12/2021 |
Work in progress | 20% Completed
133 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 07/12/2021 |
Work in progress | 20% Completed
133 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 02/12/2021 |
Work in progress | 20% Completed
133 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 28/11/2021 |
Work in progress | 20% Completed
133 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 21/11/2021 |
Work in progress | 19% Completed
110 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 17/11/2021 |
Work in progress | 16% Completed
110 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 11/11/2021 |
Work in progress | 16% Completed
110 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 09/11/2021 |
Work in progress | 16% Completed
110 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 08/11/2021 |
Work in progress | 15% Completed
106 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 05/11/2021 |
Work in progress | 14% Completed
106 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 31/10/2021 |
Work in progress | 13% Completed
106 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 24/10/2021 |
Work in progress | 12% Completed
96 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 19/10/2021 |
Work in progress | 12% Completed
88 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 12/10/2021 |
Work in progress | 11% Completed
88 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 07/10/2021 |
Work in progress | 11% Completed
86 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 02/10/2021 |
Work in progress | 11% Completed
78 fhtcs completed
Thaliparamba WS Dn EE |
Date: 27/09/2021 |
Work in progress | 10% Completed
66 FHTC COMPLETED
Thaliparamba WS Dn EE |
Date: 23/09/2021 |
Work in progress | 9% Completed
59 FHTCS COMPLETED
Thaliparamba WS Dn EE |
Date: 19/09/2021 |
Work in progress | 9% Completed
48 FHTCS COMPLETED
Thaliparamba WS Dn EE |
Date: 14/09/2021 |
Work in progress | 8% Completed
40 FHTCS COMPLETED
Thaliparamba WS Dn EE |
Date: 06/09/2021 |
Work in progress | 3% Completed
30 FHTCS COMPLETED
Thaliparamba WS Dn EE |
Date: 01/09/2021 |
Work in progress | 3% Completed
26 FHTCS COMPLETED
Thaliparamba WS Dn EE |
Date: 27/08/2021 |
Work in progress | 3% Completed
23 FHTCS COMPLETED
Thaliparamba WS Dn EE |
Date: 23/08/2021 |
Work in progress | 2% Completed
13 FHTCS COMPLETED
Thaliparamba WS Dn EE |
Date: 17/08/2021 |
Work in progress | 1% Completed
10 fhtcs completed
Thaliparamba WS Dn EE |
Date: 13/08/2021 |
Work has started | 0% Completed
not started
Thaliparamba WS Dn EE |
Date: 07/08/2021 |
Work has started | 0% Completed
not started
Thaliparamba WS Dn EE |
Date: 30/07/2021 |
Work has started | 0% Completed
not started
Thaliparamba WS Dn EE |
Date: 22/07/2021 |
Work has started | 0% Completed
not started
Thaliparamba WS Dn EE |
Date: 15/07/2021 |
Work has started | 0% Completed
Not started work
Thaliparamba WS Dn EE |
Date: 14/07/2021 |
Work has started | 0% Completed
Not started work
Thaliparamba WS Dn EE |
Date: 13/07/2021 |
Work has started | 0% Completed
Not started work
Thaliparamba WS Dn EE |
Date: 12/07/2021 |
Work has started | 0% Completed
Not started work
Thaliparamba WS Dn EE |
Date: 09/07/2021 |
Work has started | 0% Completed
NOT WORK STARTED
Thaliparamba WS Dn EE |
Date: 08/07/2021 |
Work has started | 0% Completed
NOT WORK STARTED
Thaliparamba WS Dn EE |
Date: 07/07/2021 |
Work has started | 0% Completed
NOT WORK STARTED
Thaliparamba WS Dn EE |
Date: 06/07/2021 |
Work has started | 0% Completed
NOT WORK STARTED
Thaliparamba WS Dn EE |
Date: 05/07/2021 |
Work has started | 0% Completed
NOT WORK STARTED
Thaliparamba WS Dn EE |
Date: 03/07/2021 |
Work has started | 0% Completed
NOT WORK STARTED
Thaliparamba WS Dn EE |
Date: 02/07/2021 |
Work has started | 0% Completed
NOT WORK STARTED
Thaliparamba WS Dn EE |
Date: 01/07/2021 |
Work has started | 0% Completed
NOT STARTED
Thaliparamba WS Dn EE |
Date: 30/06/2021 |
Work has started | 0% Completed
NOT STARTED
Thaliparamba WS Dn EE |
Date: 29/06/2021 |
Work has started | 0% Completed
not started issued