| Kottiyam PH Sn AE |
| Date: 15/03/2024 |
Work has been completed | 100% Completed
Disconnection of unusable street tap work completed. 635 nos Completed
| Kottiyam PH Sn AE |
| Date: 11/03/2024 |
Work in progress | 99% Completed
Disconnection of unusable street tap work in progress. 635 nos Completed
| Kottiyam PH Sn AE |
| Date: 06/03/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 610 nos Completed
| Kottiyam PH Sn AE |
| Date: 02/03/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 610 nos Completed
| Kottiyam PH Sn AE |
| Date: 28/02/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 610 nos Completed
| Kottiyam PH Sn AE |
| Date: 26/02/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 600 nos Completed
| Kottiyam PH Sn AE |
| Date: 21/02/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 590 nos Completed
| Kottiyam PH Sn AE |
| Date: 17/02/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 580 nos Completed
| Kottiyam PH Sn AE |
| Date: 14/02/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 550 nos Completed
| Kottiyam PH Sn AE |
| Date: 12/02/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 550 nos Completed
| Kottiyam PH Sn AE |
| Date: 08/02/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval
| Kottiyam PH Sn AE |
| Date: 05/02/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval
| Kottiyam PH Sn AE |
| Date: 01/02/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval
| Kottiyam PH Sn AE |
| Date: 29/01/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval
| Kottiyam PH Sn AE |
| Date: 23/01/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval
| Kottiyam PH Sn AE |
| Date: 19/01/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval
| Kottiyam PH Sn AE |
| Date: 15/01/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval
| Kottiyam PH Sn AE |
| Date: 12/01/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval
| Kottiyam PH Sn AE |
| Date: 09/01/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval
| Kottiyam PH Sn AE |
| Date: 06/01/2024 |
| Kottiyam PH Sn AE |
| Date: 02/01/2024 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 530 nos Completed
| Kottiyam PH Sn AE |
| Date: 30/12/2023 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress
| Kottiyam PH Sn AE |
| Date: 26/12/2023 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 501 nos Completed
| Kottiyam PH Sn AE |
| Date: 19/12/2023 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 490 nos Completed
| Kottiyam PH Sn AE |
| Date: 15/12/2023 |
Work in progress | 98% Completed
Disconnection of unusable street tap work in progress. 490 nos Completed
| Kottiyam PH Sn AE |
| Date: 11/12/2023 |
| Kottiyam PH Sn AE |
| Date: 05/12/2023 |
Work in progress | 90% Completed
Disconnection of unusable street tap work in progress. 450 nos Completed
| Kottiyam PH Sn AE |
| Date: 30/11/2023 |
| Kottiyam PH Sn AE |
| Date: 29/11/2023 |
| Kottiyam PH Sn AE |
| Date: 25/11/2023 |
Work in progress | 76% Completed
Disconnection of unusable street tap work in progress. 380 nos Completed
| Kottiyam PH Sn AE |
| Date: 20/11/2023 |
| Kottiyam PH Sn AE |
| Date: 15/11/2023 |
Work in progress | 64% Completed
Disconnection of unusable street tap work in progress. 321 nos Completed
| Kottiyam PH Sn AE |
| Date: 09/11/2023 |
| Kottiyam PH Sn AE |
| Date: 04/11/2023 |