| Kozhikode PH Dn EE |
| Date: 21/04/2024 |
Work has been completed | 100% Completed
work completed
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 82% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 75% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 25% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 20% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 12/01/2024 |
Work has started | 0% Completed
Site Handed Over