| Kozhikode Dist 1 Sn 2 - AE |
| Date: 23/10/2024 |
Work has been completed | 100% Completed
Corrected RE submitted and Final bill to be submitted.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 22/10/2024 |
Work has been completed | 100% Completed
Corrected RE to be resubmitted and Final bill to be submitted.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 24/09/2024 |
Work has been completed | 100% Completed
Work completed.RE under preparation.Final bill to be submitted.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 21/08/2024 |
Work in progress | 95% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 92% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 89% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 86% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 01/03/2024 |
Work in progress | 84% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 82% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 80% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 11/01/2024 |
Work in progress | 78% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work in progress | 75% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 28/11/2023 |
Work in progress | 73% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 09/11/2023 |
Work in progress | 68% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 27/10/2023 |
Work in progress | 65% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 17/10/2023 |
Work in progress | 60% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 14/09/2023 |
Work in progress | 51% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 05/09/2023 |
Work in progress | 50% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 17/08/2023 |
Work in progress | 40% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 07/08/2023 |
Work in progress | 30% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 24/07/2023 |
Work in progress | 25% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 12/07/2023 |
Work in progress | 12% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 05/07/2023 |
Work in progress | 10% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 30/06/2023 |
Work in progress | 9% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 20/06/2023 |
Work in progress | 7% Completed
Pipe laying started.
| Kozhikode PH Dn EE |
| Date: 13/06/2023 |
Work in progress | 6% Completed
Pipe laying started.
| Kozhikode PH Dn EE |
| Date: 08/06/2023 |
Work in progress | 5% Completed
Pipe laying started. About 240 meter of pipe laid
| Kozhikode PH Dn EE |
| Date: 05/06/2023 |
Work in progress | 1% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 01/06/2023 |
Work in progress | 1% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 25/05/2023 |
Work in progress | 1% Completed
Agreement Executed