| Kannur WS Sn AE 2 |
| Date: 25/09/2026 |
Work in progress | 9% Completed
Work started.750 meter pipe laid. MOU regarding contonment land from contonment board pending
| Kannur WS Sn AE 2 |
| Date: 14/08/2026 |
Work in progress | 9% Completed
Work started.750 meter pipe laid. MOU regarding contonment land from contonment board pending
| Kannur WS Sn AE 2 |
| Date: 17/07/2026 |
Work in progress | 9% Completed
Work started.750 meter pipe laid. MOU regarding contonment land from contonment board pending.
| Kannur WS Sn AE 2 |
| Date: 07/07/2026 |
Work in progress | 8% Completed
Work started.750 meter pipe laid. awaiting road cutting permission
| Kannur WS Sn AE 2 |
| Date: 04/06/2026 |
Work in progress | 8% Completed
Work started.750 meter pipe laid. awaiting road cutting permission
| Kannur WS Sn AE 2 |
| Date: 29/04/2026 |
Work in progress | 8% Completed
Work started.750 meter pipe laid. awaiting road cutting permission
| Kannur WS Sn AE 2 |
| Date: 17/04/2026 |
Work in progress | 8% Completed
Work started.750 meter pipe laid. awaiting road cutting permission
| Kannur WS Sn AE 2 |
| Date: 08/04/2026 |
Work in progress | 8% Completed
Work started.750 meter pipe laid. awaiting road cutting permission
| Kannur WS Sn AE 2 |
| Date: 24/03/2026 |
Work in progress | 8% Completed
Work started.750 meter pipe laid. awaiting road cutting permission
| Kannur WS Sn AE 2 |
| Date: 07/03/2026 |
| Kannur WS Sn AE 2 |
| Date: 06/03/2026 |
Work in progress | 8% Completed
Work started.750 meter pipe laid. awaiting road cutting permission
| Kannur WS Sn AE 2 |
| Date: 25/02/2026 |
Work in progress | 8% Completed
Work started.750 meter pipe laid.
| Kannur WS Sn AE 2 |
| Date: 16/02/2026 |
Work in progress | 8% Completed
Work started.750 meter pipe laid.
| Kannur WS Sn AE 2 |
| Date: 09/02/2026 |
Work in progress | 8% Completed
Work started.750 meter pipe laid.