Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kannur WS Sn AE 2
Date: 14/08/2026

Work in progress | 40% Completed

Tank cover slab completed. Parapet work started.

Kannur WS Sn AE 2
Date: 17/07/2026

Work in progress | 11% Completed

Deck slab concreting completed. Side wall 3m completed.

Kannur WS Sn AE 2
Date: 07/07/2026

Work in progress | 11% Completed

Ongoing Side wall concreting

Kannur WS Sn AE 2
Date: 18/06/2026

Work in progress | 9% Completed

Ongoing bottom main slab concreting

Kannur WS Sn AE 2
Date: 04/06/2026

Work in progress | 8% Completed

Bottom main slab Shuttering and reinforcement work completed.

Attached images

img

Kannur WS Sn AE 2
Date: 29/04/2026

Work in progress | 7% Completed

Ongoing column concrete work.

Kannur WS Sn AE 2
Date: 17/04/2026

Work in progress | 7% Completed

Ongoing column concrete work.

Kannur WS Sn AE 2
Date: 08/04/2026

Work in progress | 7% Completed

Ongoing column concrete work.

Kannur WS Sn AE 2
Date: 24/03/2026

Work in progress | 7% Completed

Ongoing column concrete work.

Kannur WS Sn AE 2
Date: 06/03/2026

Work in progress | 7% Completed

Ongoing column concrete work

Kannur WS Sn AE 2
Date: 25/02/2026

Work in progress | 6% Completed

Plinth beam work completed.

Kannur WS Sn AE 2
Date: 16/02/2026

Work in progress | 6% Completed

Plinth beam work completed.

Kannur WS Sn AE 2
Date: 11/02/2026

Work in progress | 4% Completed

PCC Work of the footing completed.

Kannur WS Sn AE 2
Date: 06/02/2026

Work in progress | 4% Completed

PCC Work of the footing completed.

Kannur WS Sn AE 2
Date: 20/01/2026

Work in progress | 3% Completed

PCC Work of the footing is done.

Kannur PH Dn EE
Date: 12/01/2026

Work in progress | 2% Completed

Old GLSR Tank Chalakkunnu - Demolished, New tank structural drawing submitted for approval.

Kannur PH Dn EE
Date: 09/01/2026

Work in progress | 2% Completed

Old GLSR Tank Chalakkunnu - Demolished,New tank structural drawing submitted for approval.

Kannur WS Sn AE 2
Date: 05/01/2026

Work in progress | 2% Completed

Old GLSR Tank Chalakkunnu - Demolished,New tank structural drawing submitted for approval.

Kannur WS Sn AE 2
Date: 30/12/2025

Work in progress | 2% Completed

Old GLSR Tank Chalakkunnu - Demolished,New tank structural drawing submitted for approval.

Kannur PH Dn EE
Date: 15/12/2025

Work has started | 0% Completed

Agreement Excecuted.

Kannur PH Dn EE
Date: 28/11/2025

Work has started | 0% Completed

Agreement Excecuted.

Kannur PH Dn EE
Date: 20/11/2025

Work has started | 0% Completed

Agreement Excecuted

Kannur PH Dn EE
Date: 17/11/2025

Work has started | 0% Completed

Work order issued.

Kannur PH Dn EE
Date: 27/10/2025

Work has started | 0% Completed

Work order issued