| Kannur WS Sn AE 2 |
| Date: 14/08/2026 |
Work in progress | 40% Completed
Tank cover slab completed. Parapet work started.
| Kannur WS Sn AE 2 |
| Date: 17/07/2026 |
Work in progress | 11% Completed
Deck slab concreting completed. Side wall 3m completed.
| Kannur WS Sn AE 2 |
| Date: 07/07/2026 |
Work in progress | 11% Completed
Ongoing Side wall concreting
| Kannur WS Sn AE 2 |
| Date: 18/06/2026 |
Work in progress | 9% Completed
Ongoing bottom main slab concreting
| Kannur WS Sn AE 2 |
| Date: 04/06/2026 |
| Kannur WS Sn AE 2 |
| Date: 29/04/2026 |
Work in progress | 7% Completed
Ongoing column concrete work.
| Kannur WS Sn AE 2 |
| Date: 17/04/2026 |
Work in progress | 7% Completed
Ongoing column concrete work.
| Kannur WS Sn AE 2 |
| Date: 08/04/2026 |
Work in progress | 7% Completed
Ongoing column concrete work.
| Kannur WS Sn AE 2 |
| Date: 24/03/2026 |
Work in progress | 7% Completed
Ongoing column concrete work.
| Kannur WS Sn AE 2 |
| Date: 06/03/2026 |
Work in progress | 7% Completed
Ongoing column concrete work
| Kannur WS Sn AE 2 |
| Date: 25/02/2026 |
Work in progress | 6% Completed
Plinth beam work completed.
| Kannur WS Sn AE 2 |
| Date: 16/02/2026 |
Work in progress | 6% Completed
Plinth beam work completed.
| Kannur WS Sn AE 2 |
| Date: 11/02/2026 |
Work in progress | 4% Completed
PCC Work of the footing completed.
| Kannur WS Sn AE 2 |
| Date: 06/02/2026 |
Work in progress | 4% Completed
PCC Work of the footing completed.
| Kannur WS Sn AE 2 |
| Date: 20/01/2026 |
Work in progress | 3% Completed
PCC Work of the footing is done.
| Kannur PH Dn EE |
| Date: 12/01/2026 |
Work in progress | 2% Completed
Old GLSR Tank Chalakkunnu - Demolished, New tank structural drawing submitted for approval.
| Kannur PH Dn EE |
| Date: 09/01/2026 |
Work in progress | 2% Completed
Old GLSR Tank Chalakkunnu - Demolished,New tank structural drawing submitted for approval.
| Kannur WS Sn AE 2 |
| Date: 05/01/2026 |
Work in progress | 2% Completed
Old GLSR Tank Chalakkunnu - Demolished,New tank structural drawing submitted for approval.
| Kannur WS Sn AE 2 |
| Date: 30/12/2025 |
Work in progress | 2% Completed
Old GLSR Tank Chalakkunnu - Demolished,New tank structural drawing submitted for approval.
| Kannur PH Dn EE |
| Date: 15/12/2025 |
Work has started | 0% Completed
Agreement Excecuted.
| Kannur PH Dn EE |
| Date: 28/11/2025 |
Work has started | 0% Completed
Agreement Excecuted.
| Kannur PH Dn EE |
| Date: 20/11/2025 |
Work has started | 0% Completed
Agreement Excecuted
| Kannur PH Dn EE |
| Date: 17/11/2025 |
Work has started | 0% Completed
Work order issued.
| Kannur PH Dn EE |
| Date: 27/10/2025 |
Work has started | 0% Completed
Work order issued