| Kundara PH Sn - AE |
| Date: 24/11/2022 |
Work has been completed | 100% Completed
Completed
| Kundara PH Sn - AE |
| Date: 07/10/2022 |
Work in progress | 50% Completed
Work in progress
| Kottarakkara PH Dn EE |
| Date: 16/09/2022 |
Work in progress | 50% Completed
work in progress
| Kottarakkara PH Dn EE |
| Date: 01/09/2022 |
Work in progress | 4% Completed
Pipe Laying Work In Progress
| Kottarakkara PH Dn EE |
| Date: 30/08/2022 |
Work in progress | 3% Completed
Agreement executed
| Kottarakkara PH Dn EE |
| Date: 28/08/2022 |
Work in progress | 3% Completed
Agreement executed
| Kottarakkara PH Dn EE |
| Date: 26/08/2022 |
Work in progress | 3% Completed
Agreement executed
| Kottarakkara PH Dn EE |
| Date: 24/08/2022 |
Work in progress | 3% Completed
Agreement executed
| Kottarakkara PH Dn EE |
| Date: 21/08/2022 |
Work in progress | 3% Completed
Agreement executed
| Kottarakkara PH Dn EE |
| Date: 20/08/2022 |
Work in progress | 3% Completed
Agreement Executed
| Kottarakkara PH Dn EE |
| Date: 15/08/2022 |
Work in progress | 3% Completed
Agreement Executed
| Kottarakkara PH Dn EE |
| Date: 04/08/2022 |
Work in progress | 3% Completed
on going