Kalliassery W S Section - AE
Date: 10/06/2024

Work has been completed | 100% Completed

Work completed

Kalliassery W S Section - AE
Date: 06/06/2024

Work has been completed | 100% Completed

Work completed

Kalliassery W S Section - AE
Date: 28/05/2024

Work has been completed | 100% Completed

Work completed

Kalliassery W S Section - AE
Date: 14/05/2024

Work has been completed | 100% Completed

Work completed

Kalliassery W S Section - AE
Date: 10/05/2024

Work has been completed | 100% Completed

Work completed

Kalliassery W S Section - AE
Date: 06/05/2024

Work has been completed | 100% Completed

Work completed

Kalliassery W S Section - AE
Date: 23/04/2024

Work has been completed | 100% Completed

Work completed

Kalliassery W S Section - AE
Date: 16/04/2024

Work has been completed | 100% Completed

Work completed

Kalliassery W S Section - AE
Date: 03/04/2024

Work has been completed | 100% Completed

Work completed

Kalliassery W S Section - AE
Date: 20/03/2024

Work has been completed | 100% Completed

Work completed

Kalliassery W S Section - AE
Date: 11/03/2024

Work in progress | 50% Completed

site handed over, Pipe supplied by contractor, Pipe line work going on

Kalliassery W S Section - AE
Date: 28/02/2024

Work has started | 0% Completed

Work order issued. site handed over, Pipe supplied by contractor

Kalliassery W S Section - AE
Date: 22/02/2024

Work has started | 0% Completed

Work order issued. site handed over, Pipe supplied by contractor

Kalliassery W S Section - AE
Date: 17/02/2024

Work has started | 0% Completed

Work order issued. site handed over,Pipe supplied by contractor

Kalliassery W S Section - AE
Date: 14/02/2024

Work has started | 0% Completed

Work order issued. site handed over,Pipe supplied by contractor

Kalliassery W S Section - AE
Date: 13/02/2024

Work has started | 0% Completed

Work order issued. site handed over

Kalliassery W S Section - AE
Date: 07/02/2024

Work has started | 0% Completed

Work order issued. site handed over

Kalliassery W S Section - AE
Date: 02/02/2024

Work has started | 0% Completed

Work order issued. site handed over

Kalliassery W S Section - AE
Date: 23/01/2024

Work has started | 0% Completed

Work order issued. site handed over

Kalliassery W S Section - AE
Date: 20/01/2024

Work has started | 0% Completed

Work order issued. site handed over

Kalliassery W S Section - AE
Date: 17/01/2024

Work has started | 0% Completed

Work order issued. site handed over

Kalliassery W S Section - AE
Date: 08/01/2024

Work has started | 0% Completed

Work order issued. site handed over

Kalliassery W S Section - AE
Date: 06/01/2024

Work has started | 0% Completed

Work order issued. site handed over

Kalliassery W S Section - AE
Date: 03/01/2024

Work has started | 0% Completed

Work order issued. site handed over

Kalliassery W S Section - AE
Date: 31/12/2023

Work has started | 0% Completed

Work order issued. site handed over

Kalliassery W S Section - AE
Date: 26/12/2023

Work has started | 0% Completed

Work order issued. site handed over.

Kalliassery W S Section - AE
Date: 18/12/2023

Work has started | 0% Completed

Work order issued. site handed over.

Kalliassery W S Section - AE
Date: 13/12/2023

Work has started | 0% Completed

Work order issued. site handed over.

Kalliassery W S Section - AE
Date: 10/12/2023

Work has started | 0% Completed

Work order issued. site handed over.

Kalliassery W S Section - AE
Date: 30/11/2023

Work has started | 0% Completed

Work order issued

Kalliassery W S Section - AE
Date: 25/11/2023

Work in progress | 1% Completed

Work order issued