Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Thiruvananthapuram - Med col - AE
Date: 21/10/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 18/10/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 16/10/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 13/10/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 11/10/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 01/10/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 28/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 24/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 22/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 20/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 17/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 15/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 13/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 09/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 07/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 04/09/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 02/09/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 27/08/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 26/08/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 24/08/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 22/08/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 18/08/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 16/08/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 14/08/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 13/08/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 11/08/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 09/08/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 05/08/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 02/08/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 29/07/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 26/07/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 23/07/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 20/07/2021

Work has been completed | 100% Completed

Work Completed

Pattoor Sewerage Dn
Date: 16/07/2021

Work has been completed | 100% Completed

Work Completed

Pattoor Sewerage Dn
Date: 14/07/2021

Work has been completed | 100% Completed

Work Completed

Pattoor Sewerage Dn
Date: 12/07/2021

Work has been completed | 100% Completed

Work Completed

Pattoor Sewerage Dn
Date: 09/07/2021

Work has been completed | 100% Completed

Work Completed

Pattoor Sewerage Dn
Date: 05/07/2021

Work has been completed | 100% Completed

Work Completed

Pattoor Sewerage Dn
Date: 02/07/2021

Work has been completed | 100% Completed

Work Completed

Pattoor Sewerage Dn
Date: 30/06/2021

Work has been completed | 100% Completed

Work Completed

Pattoor Sewerage Dn
Date: 25/06/2021

Work has been completed | 100% Completed

Work Completed

Pattoor Sewerage Dn
Date: 21/06/2021

Work has been completed | 100% Completed

Work Completed

Pattoor Sewerage Dn
Date: 17/06/2021

Work has been completed | 100% Completed

Work Completed

Pattoor Sewerage Dn
Date: 14/06/2021

Work has been completed | 100% Completed

Work Completed

Pattoor Sewerage Dn
Date: 10/06/2021

Work has been completed | 100% Completed

Work Completed

Pattoor Sewerage Dn
Date: 02/06/2021

Work has been completed | 100% Completed

Work Completed

Pattoor Sewerage Dn
Date: 31/05/2021

Work has been completed | 100% Completed

Work Completed and Final Bill submitted on 9.04.21

Pattoor Sewerage Dn
Date: 28/05/2021

Work has been completed | 100% Completed

Work completed

Pattoor Sewerage Dn
Date: 24/05/2021

Work has been completed | 100% Completed

Work completed

Pattoor Sewerage Dn
Date: 20/05/2021

Work has been completed | 100% Completed

Work completed

Pattoor Sewerage Dn
Date: 17/05/2021

Work has been completed | 100% Completed

Work completed

Pattoor Sewerage Dn
Date: 14/05/2021

Work has been completed | 100% Completed

Final bill submitted to Sewerage Subdivision, Pattoor

Pattoor Sewerage Dn
Date: 30/04/2021

Work has been completed | 100% Completed

Final bill submitted to Sewerage Subdivision, Pattoor

Pattoor Sewerage Dn
Date: 26/04/2021

Work has been completed | 100% Completed

Final bill submitted to Sewerage Subdivision, Pattoor

Pattoor Sewerage Dn
Date: 16/04/2021

Work has been completed | 100% Completed

Final bill submitted to Sewerage Subdivision, Pattoor

Pattoor Sewerage Dn
Date: 12/04/2021

Work has been completed | 100% Completed

Final bill submitted to Sewerage Subdivision, Pattoor

Pattoor Sewerage Dn
Date: 09/04/2021

Work has been completed | 100% Completed

Final bill submitted to Sewerage Subdivision, Pattoor

Pattoor Sewerage Dn
Date: 07/04/2021

Work has been completed | 100% Completed

Final Bill Preparation in progress

Pattoor Sewerage Dn
Date: 31/03/2021

Work has been completed | 100% Completed

Final Bill Preparation in progress

Pattoor Sewerage Dn
Date: 27/03/2021

Work has been completed | 100% Completed

Final Bill Preparation in progress

Pattoor Sewerage Dn
Date: 22/03/2021

Work has been completed | 100% Completed

Work Completed. Bill Preparation in progress

Pattoor Sewerage Dn
Date: 16/03/2021

Work in progress | 60% Completed

Work in Progress. Total Six MH construction Completed

Pattoor Sewerage Dn
Date: 05/03/2021

Work in progress | 25% Completed

Work in Progress. Three MH construction Completed

Pattoor Sewerage Dn
Date: 17/02/2021

Work in progress | 5% Completed

Work Started on 17.02.2021

Pattoor Sewerage Dn
Date: 16/02/2021

Work has started | 0% Completed

Work Order Issued

Pattoor Sewerage Dn
Date: 09/02/2021

Work has started | 0% Completed

Work Tendered

Pattoor Sewerage Dn
Date: 27/01/2021

Work has started | 0% Completed

tendered