Kozhikode Dist 1 Sn 2 - AE
Date: 24/09/2024

Work has been completed | 100% Completed

Work completed. RE submitted.Final bill to be submitted.

Kozhikode Dist 1 Sn 2 - AE
Date: 11/09/2024

Work has been completed | 100% Completed

Work completed.RE under preperation.Final bill to be submitted

Kozhikode Dist 1 Sn 2 - AE
Date: 21/08/2024

Work in progress | 95% Completed

Work in progress

Kozhikode PH Dn EE
Date: 20/04/2024

Work in progress | 85% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 04/04/2024

Work in progress | 83% Completed

Work in progress

Kozhikode PH Dn EE
Date: 12/03/2024

Work in progress | 80% Completed

Work in progress

Kozhikode PH Dn EE
Date: 14/02/2024

Work in progress | 78% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 27/01/2024

Work in progress | 75% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 11/01/2024

Work in progress | 73% Completed

Work in progress

Kozhikode PH Dn EE
Date: 11/12/2023

Work in progress | 72% Completed

Work in progress

Kozhikode PH Dn EE
Date: 28/11/2023

Work in progress | 70% Completed

Work in progress

Kozhikode PH Dn EE
Date: 09/11/2023

Work in progress | 67% Completed

Work in progress

Kozhikode PH Dn EE
Date: 28/10/2023

Work in progress | 63% Completed

Work Started

Kozhikode PH Dn EE
Date: 17/10/2023

Work in progress | 60% Completed

Work Started

Kozhikode PH Dn EE
Date: 14/09/2023

Work in progress | 52% Completed

Work Started

Kozhikode PH Dn EE
Date: 05/09/2023

Work in progress | 50% Completed

Work Started

Kozhikode PH Dn EE
Date: 17/08/2023

Work in progress | 30% Completed

Work Started

Kozhikode PH Dn EE
Date: 08/08/2023

Work has started | 0% Completed

Site Handed Over. Work Not Yet Started

Kozhikode PH Dn EE
Date: 24/07/2023

Work has started | 0% Completed

Site Handed Over. Work Not Yet Started

Kozhikode PH Dn EE
Date: 12/07/2023

Work has started | 0% Completed

Tender Accepted

Kozhikode PH Dn EE
Date: 05/07/2023

Work has started | 0% Completed

Tender Accepted

Kozhikode PH Dn EE
Date: 30/06/2023

Work has started | 0% Completed

Tender Accepted

Kozhikode PH Dn EE
Date: 20/06/2023

Work has started | 0% Completed

Tender Accepted

Kozhikode PH Dn EE
Date: 13/06/2023

Work has started | 0% Completed

Tender Accepted

Kozhikode PH Dn EE
Date: 08/06/2023

Work in progress | 8% Completed

Pipe laying started. About 950 meter of pipe laid

Kozhikode PH Dn EE
Date: 05/06/2023

Work in progress | 1% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 01/06/2023

Work in progress | 1% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 26/05/2023

Work in progress | 1% Completed

Agreement Executed