| Perlasserry Sn 1 |
| Date: 01/06/2026 |
Work has been completed | 100% Completed
WORK COMPLETED. BILL UNDER PREPARATION.
| Perlasserry Sn 1 |
| Date: 25/05/2026 |
Work in progress | 98% Completed
road restoration work in progress.
| Perlasserry Sn 1 |
| Date: 20/05/2026 |
Work in progress | 98% Completed
road restoration work in progress.
| Perlasserry Sn 1 |
| Date: 15/05/2026 |
Work in progress | 94% Completed
road restoration work in progress.
| Perlasserry Sn 1 |
| Date: 11/05/2026 |
Work in progress | 94% Completed
road restoration work in progress.
| Perlasserry Sn 1 |
| Date: 05/05/2026 |
Work in progress | 94% Completed
road restoration work in progress.
| Perlasserry Sn 1 |
| Date: 30/04/2026 |
Work in progress | 94% Completed
road restoration work in progress.
| Perlasserry Sn 1 |
| Date: 25/04/2026 |
Work in progress | 94% Completed
road restoration work in progress.
| Perlasserry Sn 1 |
| Date: 21/04/2026 |
Work in progress | 94% Completed
road restoration work in progress.
| Perlasserry Sn 1 |
| Date: 15/04/2026 |
Work in progress | 94% Completed
road restoration work in progress.
| Perlasserry Sn 1 |
| Date: 10/04/2026 |
Work in progress | 94% Completed
road restoration work in progress.
| Perlasserry Sn 1 |
| Date: 05/04/2026 |
Work in progress | 94% Completed
road restoration work in progress.
| Perlasserry Sn 1 |
| Date: 30/03/2026 |
Work in progress | 92% Completed
road restoration work in progress.
| Perlasserry Sn 1 |
| Date: 25/03/2026 |
Work in progress | 90% Completed
road restoration work in progress.
| Perlasserry Sn 1 |
| Date: 21/03/2026 |
Work in progress | 90% Completed
road restoration work in progress.
| Perlasserry Sn 1 |
| Date: 17/03/2026 |
Work in progress | 90% Completed
road restoration work in progress.
| Perlasserry Sn 1 |
| Date: 13/03/2026 |
Work in progress | 90% Completed
road restoration work in progress.
| Perlasserry Sn 1 |
| Date: 10/03/2026 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 07/03/2026 |
Work in progress | 87% Completed
KNRGOK082416253
| Perlasserry Sn 1 |
| Date: 02/03/2026 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 27/02/2026 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 22/02/2026 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 19/02/2026 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 11/02/2026 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 04/02/2026 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 31/01/2026 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 29/01/2026 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 21/01/2026 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 17/01/2026 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 13/01/2026 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 06/01/2026 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 01/01/2026 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 26/12/2025 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 16/12/2025 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 09/12/2025 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 03/12/2025 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 26/11/2025 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 19/11/2025 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 13/11/2025 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 06/11/2025 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 01/11/2025 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 28/10/2025 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 22/10/2025 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 16/10/2025 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 03/10/2025 |
Work in progress | 87% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 26/09/2025 |
Work in progress | 86% Completed
105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.
| Perlasserry Sn 1 |
| Date: 12/09/2025 |
Work in progress | 86% Completed
105 connections replaced, chamber work completed and one interconnection work remaining.
| Perlasserry Sn 1 |
| Date: 08/09/2025 |
Work in progress | 86% Completed
105 connections replaced, chamber work completed and one interconnection work remaining.
| Perlasserry Sn 1 |
| Date: 29/08/2025 |
Work in progress | 85% Completed
one chamber work and one interconnection work remaining.
| Perlasserry Sn 1 |
| Date: 21/08/2025 |
Work in progress | 85% Completed
one chamber work and one interconnection work remaining.
| Perlasserry Sn 1 |
| Date: 14/08/2025 |
Work in progress | 85% Completed
105 connections replaced.
| Perlasserry Sn 1 |
| Date: 08/08/2025 |
Work in progress | 85% Completed
105 connections replaced
| Perlasserry Sn 1 |
| Date: 02/08/2025 |
Work in progress | 85% Completed
Out of 105 connections,102 connections replaced
| Perlasserry Sn 1 |
| Date: 28/07/2025 |
Work in progress | 85% Completed
Out of 105 connections,102 connections replaced.
| Perlasserry Sn 1 |
| Date: 16/07/2025 |
Work in progress | 73% Completed
Out of 105 connections, 85 connections replaced
| Perlasserry Sn 1 |
| Date: 10/07/2025 |
Work in progress | 71% Completed
Out of 105 connections, 85 connections replaced.
| Perlasserry Sn 1 |
| Date: 02/07/2025 |
Work in progress | 64% Completed
Pipe laying completed(2 kms)
| Perlasserry Sn 1 |
| Date: 28/06/2025 |
Work in progress | 63% Completed
pipe laying completed (2km)
| Perlasserry Sn 1 |
| Date: 24/06/2025 |
Work in progress | 60% Completed
pipe laying completed (2km)
| Perlasserry Sn 1 |
| Date: 17/06/2025 |
Work in progress | 53% Completed
Work started, 80% laying completed.
| Perlasserry Sn 1 |
| Date: 27/05/2025 |
Work in progress | 53% Completed
Work started, 80% laying completed.
| Perlasserry Sn 1 |
| Date: 16/05/2025 |
Work in progress | 50% Completed
Work started, 75% laying completed.
| Perlasserry Sn 1 |
| Date: 07/05/2025 |
Work in progress | 45% Completed
Work started, 70% laying completed.
| Perlasserry Sn 1 |
| Date: 29/04/2025 |
Work in progress | 35% Completed
Work started, 48% laying completed.
| Perlasserry Sn 1 |
| Date: 19/04/2025 |
Work in progress | 35% Completed
Work started, 48% laying completed.
| Perlasserry Sn 1 |
| Date: 15/04/2025 |
Work in progress | 35% Completed
Work started, 48% laying completed.
| Perlasserry Sn 1 |
| Date: 10/04/2025 |
Work in progress | 35% Completed
Work started, 48% laying completed.
| Perlasserry Sn 1 |
| Date: 01/04/2025 |
Work in progress | 30% Completed
Work started, 45% laying completed.
| Perlasserry Sn 1 |
| Date: 24/03/2025 |
Work in progress | 25% Completed
Work started ,and 40% laying completed.
| Perlasserry Sn 1 |
| Date: 17/03/2025 |
Work in progress | 15% Completed
Work started ,excavation 20% completed.
| Perlasserry Sn 1 |
| Date: 27/02/2025 |
Work has started | 0% Completed
LOA issued. PBG submitted for restoration fee ,road cutting permission pending.
| Perlasserry Sn 1 |
| Date: 12/02/2025 |
Work has started | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
| Perlasserry Sn 1 |
| Date: 01/02/2025 |
Work has started | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
| Perlasserry Sn 1 |
| Date: 28/01/2025 |
Work has started | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
| Perlasserry Sn 1 |
| Date: 25/01/2025 |
Work in progress | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
| Perlasserry Sn 1 |
| Date: 18/01/2025 |
Work in progress | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
| Perlasserry Sn 1 |
| Date: 13/01/2025 |
Work has started | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
| Perlasserry Sn 1 |
| Date: 04/01/2025 |
Work has started | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
| Perlasserry Sn 1 |
| Date: 31/12/2024 |
Work has started | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
| Perlasserry Sn 1 |
| Date: 21/12/2024 |
Work has started | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
| Perlasserry Sn 1 |
| Date: 17/12/2024 |
Work has started | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
| Perlasserry Sn 1 |
| Date: 10/12/2024 |
Work has started | 0% Completed
LOA issued. Road cutting permission and pipe testing pending.
| Kannur PH Dn EE |
| Date: 28/11/2024 |
Work has started | 0% Completed
LOA Issued.
| Kannur PH Dn EE |
| Date: 18/11/2024 |
Work has started | 0% Completed
LOA issued on 08-11-2024.
| Perlasserry Sn 1 |
| Date: 13/11/2024 |
Work has started | 0% Completed
Tender under scrutiny
| Perlasserry Sn 1 |
| Date: 07/11/2024 |
Work has started | 0% Completed
Tender under scrutiny
| Kannur PH Dn EE |
| Date: 02/11/2024 |
Work has started | 0% Completed
2 response received. Tender under scrutiny.
| Perlasserry Sn 1 |
| Date: 28/10/2024 |
Work has started | 0% Completed
No response , work retendered with due date 28.10.2024
| Perlasserry Sn 1 |
| Date: 22/10/2024 |
Work has started | 0% Completed
No response , work retendered with due date 28.10.2024
| Perlasserry Sn 1 |
| Date: 18/10/2024 |
Work has started | 0% Completed
No response, work retendered.
| Kannur PH Dn EE |
| Date: 14/10/2024 |
Work has started | 0% Completed
No response, work retendered.
| Kannur PH Dn EE |
| Date: 04/10/2024 |
Work has started | 0% Completed
Work Retendered.
| Kannur PH Dn EE |
| Date: 27/09/2024 |
Work has started | 0% Completed
Work Retendered.
| Kannur PH Dn EE |
| Date: 24/09/2024 |
Work has started | 0% Completed
Single offer received. Work to be retendered.
| Kannur PH Dn EE |
| Date: 19/09/2024 |
Work has started | 0% Completed
Single offer received. Work to be retendered.
| Perlasserry Sn 1 |
| Date: 11/09/2024 |
Work has started | 0% Completed
Estimate submitted to SE.
| Kannur PH Dn EE |
| Date: 05/09/2024 |
Work has started | 0% Completed
Estimate submitted to SE.
| Kannur PH Dn EE |
| Date: 29/08/2024 |
Work has started | 0% Completed
Estimate submitted to SE.
| Kannur PH Dn EE |
| Date: 23/08/2024 |
Work has started | 0% Completed
Estimate submitted to SE.
| Kannur PH Dn EE |
| Date: 14/08/2024 |
Work has started | 0% Completed
AS Accorded on 06-08-2024, work to be tendered.