Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Perlasserry Sn 1
Date: 01/06/2026

Work has been completed | 100% Completed

WORK COMPLETED. BILL UNDER PREPARATION.

Perlasserry Sn 1
Date: 25/05/2026

Work in progress | 98% Completed

road restoration work in progress.

Perlasserry Sn 1
Date: 20/05/2026

Work in progress | 98% Completed

road restoration work in progress.

Perlasserry Sn 1
Date: 15/05/2026

Work in progress | 94% Completed

road restoration work in progress.

Perlasserry Sn 1
Date: 11/05/2026

Work in progress | 94% Completed

road restoration work in progress.

Perlasserry Sn 1
Date: 05/05/2026

Work in progress | 94% Completed

road restoration work in progress.

Perlasserry Sn 1
Date: 30/04/2026

Work in progress | 94% Completed

road restoration work in progress.

Perlasserry Sn 1
Date: 25/04/2026

Work in progress | 94% Completed

road restoration work in progress.

Perlasserry Sn 1
Date: 21/04/2026

Work in progress | 94% Completed

road restoration work in progress.

Perlasserry Sn 1
Date: 15/04/2026

Work in progress | 94% Completed

road restoration work in progress.

Perlasserry Sn 1
Date: 10/04/2026

Work in progress | 94% Completed

road restoration work in progress.

Perlasserry Sn 1
Date: 05/04/2026

Work in progress | 94% Completed

road restoration work in progress.

Perlasserry Sn 1
Date: 30/03/2026

Work in progress | 92% Completed

road restoration work in progress.

Perlasserry Sn 1
Date: 25/03/2026

Work in progress | 90% Completed

road restoration work in progress.

Perlasserry Sn 1
Date: 21/03/2026

Work in progress | 90% Completed

road restoration work in progress.

Perlasserry Sn 1
Date: 17/03/2026

Work in progress | 90% Completed

road restoration work in progress.

Perlasserry Sn 1
Date: 13/03/2026

Work in progress | 90% Completed

road restoration work in progress.

Perlasserry Sn 1
Date: 10/03/2026

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 07/03/2026

Work in progress | 87% Completed

KNRGOK082416253

Perlasserry Sn 1
Date: 02/03/2026

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 27/02/2026

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 22/02/2026

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 19/02/2026

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 11/02/2026

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 04/02/2026

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 31/01/2026

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 29/01/2026

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 21/01/2026

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 17/01/2026

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 13/01/2026

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 06/01/2026

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 01/01/2026

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 26/12/2025

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 16/12/2025

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 09/12/2025

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 03/12/2025

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 26/11/2025

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 19/11/2025

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 13/11/2025

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 06/11/2025

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 01/11/2025

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 28/10/2025

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 22/10/2025

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 16/10/2025

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 03/10/2025

Work in progress | 87% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 26/09/2025

Work in progress | 86% Completed

105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining.

Perlasserry Sn 1
Date: 12/09/2025

Work in progress | 86% Completed

105 connections replaced, chamber work completed and one interconnection work remaining.

Perlasserry Sn 1
Date: 08/09/2025

Work in progress | 86% Completed

105 connections replaced, chamber work completed and one interconnection work remaining.

Perlasserry Sn 1
Date: 29/08/2025

Work in progress | 85% Completed

one chamber work and one interconnection work remaining.

Perlasserry Sn 1
Date: 21/08/2025

Work in progress | 85% Completed

one chamber work and one interconnection work remaining.

Perlasserry Sn 1
Date: 14/08/2025

Work in progress | 85% Completed

105 connections replaced.

Perlasserry Sn 1
Date: 08/08/2025

Work in progress | 85% Completed

105 connections replaced

Perlasserry Sn 1
Date: 02/08/2025

Work in progress | 85% Completed

Out of 105 connections,102 connections replaced

Perlasserry Sn 1
Date: 28/07/2025

Work in progress | 85% Completed

Out of 105 connections,102 connections replaced.

Perlasserry Sn 1
Date: 16/07/2025

Work in progress | 73% Completed

Out of 105 connections, 85 connections replaced

Perlasserry Sn 1
Date: 10/07/2025

Work in progress | 71% Completed

Out of 105 connections, 85 connections replaced.

Perlasserry Sn 1
Date: 02/07/2025

Work in progress | 64% Completed

Pipe laying completed(2 kms)

Perlasserry Sn 1
Date: 28/06/2025

Work in progress | 63% Completed

pipe laying completed (2km)

Perlasserry Sn 1
Date: 24/06/2025

Work in progress | 60% Completed

pipe laying completed (2km)

Perlasserry Sn 1
Date: 17/06/2025

Work in progress | 53% Completed

Work started, 80% laying completed.

Perlasserry Sn 1
Date: 27/05/2025

Work in progress | 53% Completed

Work started, 80% laying completed.

Perlasserry Sn 1
Date: 16/05/2025

Work in progress | 50% Completed

Work started, 75% laying completed.

Perlasserry Sn 1
Date: 07/05/2025

Work in progress | 45% Completed

Work started, 70% laying completed.

Perlasserry Sn 1
Date: 29/04/2025

Work in progress | 35% Completed

Work started, 48% laying completed.

Perlasserry Sn 1
Date: 19/04/2025

Work in progress | 35% Completed

Work started, 48% laying completed.

Perlasserry Sn 1
Date: 15/04/2025

Work in progress | 35% Completed

Work started, 48% laying completed.

Perlasserry Sn 1
Date: 10/04/2025

Work in progress | 35% Completed

Work started, 48% laying completed.

Perlasserry Sn 1
Date: 01/04/2025

Work in progress | 30% Completed

Work started, 45% laying completed.

Perlasserry Sn 1
Date: 24/03/2025

Work in progress | 25% Completed

Work started ,and 40% laying completed.

Perlasserry Sn 1
Date: 17/03/2025

Work in progress | 15% Completed

Work started ,excavation 20% completed.

Perlasserry Sn 1
Date: 27/02/2025

Work has started | 0% Completed

LOA issued. PBG submitted for restoration fee ,road cutting permission pending.

Perlasserry Sn 1
Date: 12/02/2025

Work has started | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 01/02/2025

Work has started | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 28/01/2025

Work has started | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 25/01/2025

Work in progress | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 18/01/2025

Work in progress | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 13/01/2025

Work has started | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 04/01/2025

Work has started | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 31/12/2024

Work has started | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 21/12/2024

Work has started | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 17/12/2024

Work has started | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 10/12/2024

Work has started | 0% Completed

LOA issued. Road cutting permission and pipe testing pending.

Kannur PH Dn EE
Date: 28/11/2024

Work has started | 0% Completed

LOA Issued.

Kannur PH Dn EE
Date: 18/11/2024

Work has started | 0% Completed

LOA issued on 08-11-2024.

Perlasserry Sn 1
Date: 13/11/2024

Work has started | 0% Completed

Tender under scrutiny

Perlasserry Sn 1
Date: 07/11/2024

Work has started | 0% Completed

Tender under scrutiny

Kannur PH Dn EE
Date: 02/11/2024

Work has started | 0% Completed

2 response received. Tender under scrutiny.

Perlasserry Sn 1
Date: 28/10/2024

Work has started | 0% Completed

No response , work retendered with due date 28.10.2024

Perlasserry Sn 1
Date: 22/10/2024

Work has started | 0% Completed

No response , work retendered with due date 28.10.2024

Perlasserry Sn 1
Date: 18/10/2024

Work has started | 0% Completed

No response, work retendered.

Kannur PH Dn EE
Date: 14/10/2024

Work has started | 0% Completed

No response, work retendered.

Kannur PH Dn EE
Date: 04/10/2024

Work has started | 0% Completed

Work Retendered.

Kannur PH Dn EE
Date: 27/09/2024

Work has started | 0% Completed

Work Retendered.

Kannur PH Dn EE
Date: 24/09/2024

Work has started | 0% Completed

Single offer received. Work to be retendered.

Kannur PH Dn EE
Date: 19/09/2024

Work has started | 0% Completed

Single offer received. Work to be retendered.

Perlasserry Sn 1
Date: 11/09/2024

Work has started | 0% Completed

Estimate submitted to SE.

Kannur PH Dn EE
Date: 05/09/2024

Work has started | 0% Completed

Estimate submitted to SE.

Kannur PH Dn EE
Date: 29/08/2024

Work has started | 0% Completed

Estimate submitted to SE.

Kannur PH Dn EE
Date: 23/08/2024

Work has started | 0% Completed

Estimate submitted to SE.

Kannur PH Dn EE
Date: 14/08/2024

Work has started | 0% Completed

AS Accorded on 06-08-2024, work to be tendered.