Pullad PH Sn - AE |
Date: 26/06/2024 |
Work in progress | 45% Completed
32000 M of PVC Pipes Laid. 611 FHTCs Provided & Geo Tagged
Pullad PH Sn - AE |
Date: 21/06/2024 |
Work in progress | 45% Completed
32000 M of PVC Pipes Laid. 611 FHTCs Provided & Geo Tagged
Pullad PH Sn - AE |
Date: 18/06/2024 |
Work in progress | 45% Completed
32000 M of PVC Pipes Laid. 611 FHTCs Provided & Geo Tagged. 590 Connections IMIS done.
Pullad PH Sn - AE |
Date: 13/06/2024 |
Work in progress | 45% Completed
32000 M of PVC Pipes Laid. 611 FHTCs Provided & Geo Tagged. 590 Connections IMIS done.
Pullad PH Sn - AE |
Date: 11/06/2024 |
Work in progress | 45% Completed
32000 M of PVC Pipes Laid. 611 FHTCs Provided & Geo Tagged.
Pullad PH Sn - AE |
Date: 07/06/2024 |
Work in progress | 45% Completed
32000 M of PVC Pipes Laid. 611 FHTCs Provided & Geo Tagged.
Pullad PH Sn - AE |
Date: 30/05/2024 |
Work in progress | 43% Completed
32000 M of PVC Pipes Laid. 600 FHTCs Provided, 547 FHTCs Geo Tagged.
Pullad PH Sn - AE |
Date: 25/05/2024 |
Work in progress | 43% Completed
32000 M of PVC Pipes Laid. 600 FHTCs Provided, 547 FHTCs Geo Tagged.
Pullad PH Sn - AE |
Date: 21/05/2024 |
Work in progress | 43% Completed
32000 M of PVC Pipes Laid. 600 FHTCs Provided, 547 FHTCs Geo Tagged.
Pullad PH Sn - AE |
Date: 17/05/2024 |
Work in progress | 43% Completed
32000 M of PVC Pipes Laid. 600 FHTCs Provided, 547 FHTCs Geo Tagged.
Pullad PH Sn - AE |
Date: 13/05/2024 |
Work in progress | 43% Completed
32000 M of PVC Pipes Laid. 600 FHTCs Provided, 547 FHTCs Geo Tagged.
Pullad PH Sn - AE |
Date: 06/05/2024 |
Work in progress | 40% Completed
32000 M of PVC Pipes Laid. 400 FHTCs Provided, 198 FHTCs Geo Tagged& IMIS Updated. GI gap work and interconnection works are ongoing.
Pullad PH Sn - AE |
Date: 02/05/2024 |
Work in progress | 40% Completed
32000 M of PVC Pipes Laid. 400 FHTCs Provided, 198 FHTCs Geo Tagged& IMIS Updated. GI gap work and interconnection works are ongoing.
Pullad PH Sn - AE |
Date: 27/04/2024 |
Work in progress | 40% Completed
32000 M of PVC Pipes Laid. 400 FHTCs Provided, 198 FHTCs Geo Tagged& IMIS Updated. GI gap work and interconnection works are ongoing.
Pullad PH Sn - AE |
Date: 23/04/2024 |
Work in progress | 40% Completed
32000 M of PVC Pipes Laid. 400 FHTCs Provided, 198 FHTCs Geo Tagged& IMIS Updated. GI gap work and interconnection works are ongoing.
Pullad PH Sn - AE |
Date: 19/04/2024 |
Work in progress | 40% Completed
32000 M of PVC Pipes Laid. 400 FHTCs Provided, 198 FHTCs Geo Tagged& IMIS Updated. GI gap work and interconnection works are ongoing.
Pullad PH Sn - AE |
Date: 16/04/2024 |
Work in progress | 35% Completed
32000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated. GI gap work and interconnection works are ongoing.
Pullad PH Sn - AE |
Date: 11/04/2024 |
Work in progress | 35% Completed
32000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated. GI gap work and interconnection works are ongoing.
Pullad PH Sn - AE |
Date: 06/04/2024 |
Work in progress | 35% Completed
32000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated. GI gap work and interconnection works are ongoing.
Pullad PH Sn - AE |
Date: 01/04/2024 |
Work in progress | 35% Completed
32000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated. GI gap work and interconnection works are ongoing.
Pullad PH Sn - AE |
Date: 27/03/2024 |
Work in progress | 35% Completed
32000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated. GI gap work and interconnection works are ongoing.
Pullad PH Sn - AE |
Date: 23/03/2024 |
Work in progress | 35% Completed
32000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated
Pullad PH Sn - AE |
Date: 19/03/2024 |
Work in progress | 35% Completed
32000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated
Pullad PH Sn - AE |
Date: 15/03/2024 |
Work in progress | 35% Completed
32000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated
Pullad PH Sn - AE |
Date: 11/03/2024 |
Work in progress | 30% Completed
21000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated
Pullad PH Sn - AE |
Date: 04/03/2024 |
Work in progress | 30% Completed
21000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated
Pullad PH Sn - AE |
Date: 26/02/2024 |
Work in progress | 30% Completed
21000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated
Pullad PH Sn - AE |
Date: 21/02/2024 |
Work in progress | 30% Completed
21000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated
Pullad PH Sn - AE |
Date: 17/02/2024 |
Work in progress | 30% Completed
21000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated
Pullad PH Sn - AE |
Date: 15/02/2024 |
Work in progress | 30% Completed
21000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated
Pullad PH Sn - AE |
Date: 09/02/2024 |
Work in progress | 30% Completed
21000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated
Pullad PH Sn - AE |
Date: 05/02/2024 |
Work in progress | 30% Completed
21000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated
Pullad PH Sn - AE |
Date: 02/02/2024 |
Work in progress | 30% Completed
21000 M of PVC Pipes Laid 147 FHTCs Provided, Geo Tagged& IMIS Updated
Pullad PH Sn - AE |
Date: 31/01/2024 |
Work in progress | 25% Completed
Pipe work Ongoing. 101 FHTCs Provided
Pullad PH Sn - AE |
Date: 22/01/2024 |
Work in progress | 25% Completed
Pipe work Ongoing. 101 FHTCs Provided
Pullad PH Sn - AE |
Date: 16/01/2024 |
Work in progress | 25% Completed
Pipe work Ongoing. 101 FHTCs Provided
Pullad PH Sn - AE |
Date: 09/01/2024 |
Work in progress | 20% Completed
Pipe work Ongoing. 30 FHTCs Provided
Pullad PH Sn - AE |
Date: 01/01/2024 |
Work in progress | 20% Completed
Pipes fully supplied by the Contractor. 30 FHTCs Provided.
Pullad PH Sn - AE |
Date: 27/12/2023 |
Work in progress | 20% Completed
Pipes fully supplied by the Contractor. 30 FHTCs Provided.
Pullad PH Sn - AE |
Date: 23/12/2023 |
Work in progress | 20% Completed
PVC Pipes & GI Pipes fully supplied by the Contractor. 30 FHTCs Provided.
Pullad PH Sn - AE |
Date: 19/12/2023 |
Work in progress | 20% Completed
PVC Pipes & GI Pipes fully supplied by the Contractor. 30 FHTCs Provided.
Pullad PH Sn - AE |
Date: 15/12/2023 |
Work in progress | 20% Completed
PVC Pipes & GI Pipes fully supplied by the Contractor. 30 FHTCs Provided.
Pullad PH Sn - AE |
Date: 11/12/2023 |
Work in progress | 20% Completed
PVC Pipes & GI Pipes fully supplied by the Contractor. 12 FHTCs Provided.
Pullad PH Sn - AE |
Date: 07/12/2023 |
Work in progress | 20% Completed
PVC Pipes & GI Pipes fully supplied by the Contractor. 12 FHTCs Provided.