| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 25/06/2025 |
Work has been completed | 100% Completed
WORK COMPLETED and BILL SUBMITTED
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 20/01/2025 |
Work has been completed | 100% Completed
WORK COMPLETED
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 07/12/2024 |
Work in progress | 81% Completed
ONGOING
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 03/12/2024 |
Work in progress | 80% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 26/11/2024 |
Work in progress | 79% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 22/11/2024 |
Work in progress | 79% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 21/11/2024 |
Work in progress | 79% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 06/11/2024 |
Work in progress | 78% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 26/10/2024 |
Work in progress | 78% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 23/10/2024 |
Work in progress | 77% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 05/10/2024 |
Work in progress | 76% Completed
Work in progress
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 24/09/2024 |
Work in progress | 75% Completed
ON GOING
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 21/08/2024 |
Work in progress | 75% Completed
2 interconnection work is pending
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 75% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 58% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 55% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 01/03/2024 |
Work in progress | 53% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 50% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 45% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 11/01/2024 |
Work in progress | 43% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work in progress | 40% Completed
Work Started
| Kozhikode PH Dn EE |
| Date: 28/11/2023 |
Work in progress | 37% Completed
Work Started
| Kozhikode PH Dn EE |
| Date: 09/11/2023 |
Work in progress | 33% Completed
Work Started
| Kozhikode PH Dn EE |
| Date: 27/10/2023 |
Work in progress | 30% Completed
Work Started
| Kozhikode PH Dn EE |
| Date: 17/10/2023 |
Work in progress | 25% Completed
Work Started
| Kozhikode PH Dn EE |
| Date: 14/09/2023 |
Work has started | 0% Completed
Work not yet started
| Kozhikode PH Dn EE |
| Date: 17/08/2023 |
Work has started | 0% Completed
Site Handed Over
| Kozhikode PH Dn EE |
| Date: 07/08/2023 |
Work has started | 0% Completed
Site Handed Over
| Kozhikode PH Dn EE |
| Date: 24/07/2023 |
Work has started | 0% Completed
Site Handed Over
| Kozhikode PH Dn EE |
| Date: 12/07/2023 |
Work has started | 0% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 05/07/2023 |
Work has started | 0% Completed
Work not yet started
| Kozhikode PH Dn EE |
| Date: 30/06/2023 |
Work has started | 0% Completed
Work not yet started
| Kozhikode PH Dn EE |
| Date: 20/06/2023 |
Work has started | 0% Completed
Work not yet started
| Kozhikode PH Dn EE |
| Date: 13/06/2023 |
Work has started | 0% Completed
Work not yet started
| Kozhikode PH Dn EE |
| Date: 08/06/2023 |
Work has started | 0% Completed
Work not yet started
| Kozhikode PH Dn EE |
| Date: 05/06/2023 |
Work has started | 0% Completed
Single offer received. Letter send to SE for approval
| Kozhikode PH Dn EE |
| Date: 01/06/2023 |
Work has started | 0% Completed
Single offer received. Letter send to SE for approval