Painavu PH Section AE
Date: 22/12/2025

Work has been completed | 100% Completed

Work completed.

Painavu PH Section AE
Date: 10/12/2025

Work in progress | 98% Completed

Laying of pipe completed, connection alteration in 25mm GI pipe ongoing

Painavu PH Section AE
Date: 05/12/2025

Work in progress | 98% Completed

Laying of pipe completed, connection alteration in 25mm GI pipe ongoing

Painavu PH Section AE
Date: 02/12/2025

Work in progress | 98% Completed

Laying of pipe completed, connection alteration in 25mm GI pipe ongoing

Painavu PH Section AE
Date: 24/11/2025

Work in progress | 95% Completed

Laying of pipe completed, connection alteration in 25mm GI pipe ongoing

Painavu PH Section AE
Date: 20/11/2025

Work in progress | 90% Completed

Laying of pipe completed, connection alteration in 25mm GI pipe ongoing

Painavu PH Section AE
Date: 17/11/2025

Work in progress | 71% Completed

25mm GI pipe laying in progress, connection alteration in 20mm GI pipe completed

Painavu PH Section AE
Date: 14/11/2025

Work in progress | 70% Completed

25mm GI pipe laying in progress, connection alteration in 20mm GI pipe completed

Painavu PH Section AE
Date: 13/11/2025

Work in progress | 10% Completed

20mm GI pipe laying ongoing

Painavu PH Section AE
Date: 10/11/2025

Work in progress | 9% Completed

20mm GI pipe laying ongoing

Painavu PH Section AE
Date: 03/11/2025

Work in progress | 4% Completed

20mm GI pipe laying ongoing

Painavu PH Section AE
Date: 28/10/2025

Work in progress | 4% Completed

20mm GI pipe laying ongoing

Painavu PH Section AE
Date: 24/10/2025

Work in progress | 4% Completed

20mm GI pipe laying ongoing

Painavu PH Section AE
Date: 21/10/2025

Work in progress | 4% Completed

20mm GI pipe laying ongoing

Painavu PH Section AE
Date: 18/10/2025

Work in progress | 4% Completed

20mm GI pipe laying ongoing

Painavu PH Section AE
Date: 16/10/2025

Work in progress | 3% Completed

20mm GI pipe laying ongoing

Painavu PH Section AE
Date: 10/10/2025

Work in progress | 3% Completed

20mm GI pipe laying ongoing

Painavu PH Section AE
Date: 06/10/2025

Work in progress | 3% Completed

20mm GI pipe laying ongoing

Painavu PH Section AE
Date: 03/10/2025

Work has started | 0% Completed

Pipe Supply work is in progress

Painavu PH Section AE
Date: 29/09/2025

Work has started | 0% Completed

Pipe Supply work is in progress

Painavu PH Section AE
Date: 25/09/2025

Work has started | 0% Completed

Pipe Supply work is in progress

Painavu PH Section AE
Date: 22/09/2025

Work has started | 0% Completed

Pipe Supply work is in progress

Painavu PH Section AE
Date: 18/09/2025

Work has started | 0% Completed

Pipe Supply work is in progress

Painavu PH Section AE
Date: 15/09/2025

Work has started | 0% Completed

Pipe Supply work is in progress

Painavu PH Section AE
Date: 11/09/2025

Work has started | 0% Completed

Pipe Supply work is in progress

Painavu PH Section AE
Date: 08/09/2025

Work has started | 0% Completed

Pipe Supply work is in progress

Painavu PH Section AE
Date: 02/09/2025

Work has started | 0% Completed

Pipe Supply work is in progress

Painavu PH Section AE
Date: 29/08/2025

Work in progress | 0% Completed

Pipe Supply work is in progress

Painavu PH Section AE
Date: 25/08/2025

Work has started | 0% Completed

agreement executed ,pipe testing in progress

Painavu PH Section AE
Date: 22/08/2025

Work has started | 0% Completed

agreement executed ,pipe testing in progress

Painavu PH Section AE
Date: 19/08/2025

Work has started | 0% Completed

cuted ,pipe testing in progress

Painavu PH Section AE
Date: 16/08/2025

Work has started | 0% Completed

agreement executed ,pipe testing in progress

Painavu PH Section AE
Date: 11/08/2025

Work has started | 0% Completed

agreement executed ,pipe testing in progress

Painavu PH Section AE
Date: 08/08/2025

Work has started | 0% Completed

agreement executed ,pipe testing in progress

Painavu PH Section AE
Date: 04/08/2025

Work has started | 0% Completed

agreement executed ,pipe testing in progress

Painavu PH Section AE
Date: 01/08/2025

Work has started | 0% Completed

agreement executed ,pipe testing in progress

Painavu PH Section AE
Date: 29/07/2025

Work in progress | 0% Completed

agreement executed ,pipe testing in progress

Painavu PH Section AE
Date: 14/07/2025

Work has started | 0% Completed

Tendering process ongoing

Painavu PH Section AE
Date: 10/07/2025

Work has started | 0% Completed

Tendering process completed. Agreement execution pending.