| Painavu PH Section AE |
| Date: 22/12/2025 |
Work has been completed | 100% Completed
Work completed.
| Painavu PH Section AE |
| Date: 10/12/2025 |
Work in progress | 98% Completed
Laying of pipe completed, connection alteration in 25mm GI pipe ongoing
| Painavu PH Section AE |
| Date: 05/12/2025 |
Work in progress | 98% Completed
Laying of pipe completed, connection alteration in 25mm GI pipe ongoing
| Painavu PH Section AE |
| Date: 02/12/2025 |
Work in progress | 98% Completed
Laying of pipe completed, connection alteration in 25mm GI pipe ongoing
| Painavu PH Section AE |
| Date: 24/11/2025 |
Work in progress | 95% Completed
Laying of pipe completed, connection alteration in 25mm GI pipe ongoing
| Painavu PH Section AE |
| Date: 20/11/2025 |
Work in progress | 90% Completed
Laying of pipe completed, connection alteration in 25mm GI pipe ongoing
| Painavu PH Section AE |
| Date: 17/11/2025 |
Work in progress | 71% Completed
25mm GI pipe laying in progress, connection alteration in 20mm GI pipe completed
| Painavu PH Section AE |
| Date: 14/11/2025 |
Work in progress | 70% Completed
25mm GI pipe laying in progress, connection alteration in 20mm GI pipe completed
| Painavu PH Section AE |
| Date: 13/11/2025 |
Work in progress | 10% Completed
20mm GI pipe laying ongoing
| Painavu PH Section AE |
| Date: 10/11/2025 |
Work in progress | 9% Completed
20mm GI pipe laying ongoing
| Painavu PH Section AE |
| Date: 03/11/2025 |
Work in progress | 4% Completed
20mm GI pipe laying ongoing
| Painavu PH Section AE |
| Date: 28/10/2025 |
Work in progress | 4% Completed
20mm GI pipe laying ongoing
| Painavu PH Section AE |
| Date: 24/10/2025 |
Work in progress | 4% Completed
20mm GI pipe laying ongoing
| Painavu PH Section AE |
| Date: 21/10/2025 |
Work in progress | 4% Completed
20mm GI pipe laying ongoing
| Painavu PH Section AE |
| Date: 18/10/2025 |
Work in progress | 4% Completed
20mm GI pipe laying ongoing
| Painavu PH Section AE |
| Date: 16/10/2025 |
Work in progress | 3% Completed
20mm GI pipe laying ongoing
| Painavu PH Section AE |
| Date: 10/10/2025 |
Work in progress | 3% Completed
20mm GI pipe laying ongoing
| Painavu PH Section AE |
| Date: 06/10/2025 |
Work in progress | 3% Completed
20mm GI pipe laying ongoing
| Painavu PH Section AE |
| Date: 03/10/2025 |
Work has started | 0% Completed
Pipe Supply work is in progress
| Painavu PH Section AE |
| Date: 29/09/2025 |
Work has started | 0% Completed
Pipe Supply work is in progress
| Painavu PH Section AE |
| Date: 25/09/2025 |
Work has started | 0% Completed
Pipe Supply work is in progress
| Painavu PH Section AE |
| Date: 22/09/2025 |
Work has started | 0% Completed
Pipe Supply work is in progress
| Painavu PH Section AE |
| Date: 18/09/2025 |
Work has started | 0% Completed
Pipe Supply work is in progress
| Painavu PH Section AE |
| Date: 15/09/2025 |
Work has started | 0% Completed
Pipe Supply work is in progress
| Painavu PH Section AE |
| Date: 11/09/2025 |
Work has started | 0% Completed
Pipe Supply work is in progress
| Painavu PH Section AE |
| Date: 08/09/2025 |
Work has started | 0% Completed
Pipe Supply work is in progress
| Painavu PH Section AE |
| Date: 02/09/2025 |
Work has started | 0% Completed
Pipe Supply work is in progress
| Painavu PH Section AE |
| Date: 29/08/2025 |
Work in progress | 0% Completed
Pipe Supply work is in progress
| Painavu PH Section AE |
| Date: 25/08/2025 |
Work has started | 0% Completed
agreement executed ,pipe testing in progress
| Painavu PH Section AE |
| Date: 22/08/2025 |
Work has started | 0% Completed
agreement executed ,pipe testing in progress
| Painavu PH Section AE |
| Date: 19/08/2025 |
Work has started | 0% Completed
cuted ,pipe testing in progress
| Painavu PH Section AE |
| Date: 16/08/2025 |
Work has started | 0% Completed
agreement executed ,pipe testing in progress
| Painavu PH Section AE |
| Date: 11/08/2025 |
Work has started | 0% Completed
agreement executed ,pipe testing in progress
| Painavu PH Section AE |
| Date: 08/08/2025 |
Work has started | 0% Completed
agreement executed ,pipe testing in progress
| Painavu PH Section AE |
| Date: 04/08/2025 |
Work has started | 0% Completed
agreement executed ,pipe testing in progress
| Painavu PH Section AE |
| Date: 01/08/2025 |
Work has started | 0% Completed
agreement executed ,pipe testing in progress
| Painavu PH Section AE |
| Date: 29/07/2025 |
Work in progress | 0% Completed
agreement executed ,pipe testing in progress
| Painavu PH Section AE |
| Date: 14/07/2025 |
Work has started | 0% Completed
Tendering process ongoing
| Painavu PH Section AE |
| Date: 10/07/2025 |
Work has started | 0% Completed
Tendering process completed. Agreement execution pending.